D W
HH GG FF EE DD CC BB AA Z Y X
TEMP LOBBY HERE
TEMP STAFF DESK
AND WORK AREA
HERE
PHASE 1
PHASE 2
PHASE 3
PHASE 4
PHASE 5
NOTE: AREAS WHERE THE PHASING HATCH PATTES
OVERLAP INDICATE THAT WORK IN TATH AREA WILL OCCUR
OVER MULTIPLE PHASES. REFER TO PHASING NOTES FOR A
SUMMARY OF THE SCOPE FOR EACH PHASE.
PHASING HATCH LEGEND
NOTE: AREA FOR PHASE 6 IS NOT DEFINED BY HATCH. THIS AREA
WILL BE DETERMINED BY THE CONTRACTOR DURING THE
CREATION OF THE FINAL PHASING PLAN
30 x 42
G E
N E
R A
L
N O
T E
S
618-16-111
Project Title
V.A. MEDICAL CENTER
ONE VETERANS DRIVE
MINNEAPOLIS, MN 55417
REGISTRATION NUMBER:
Office of Facilities
Management Drawing Scale
Plot Scale
Drawing Title
Approved: Division Chief
Approved: Service Director
Building Number
Checked Drawn
Location
Date
Project No.
DRAWING NO.
o n e -e ig h th i n c h o n e f o o t o n e -q u a rt e r in c h o n e f o o t th re e -e ig h th s i n c h o n e f o o t o n e -h a lf i n c h o n e f o o t th re e -q u s rt e r in c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e
-h a lf i n c h o n e f o o t th re e i n c h e s o n e f o o t
TRUE NORTH
PLAN NORTH
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENING SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS
PREPARED BY ME OR UNDER MY DIRECT
SUPERVISION AND THAT I AM A DULY
LICENSED ARCHITECT UNDER
THE LAWS OF THE STATE OF MINNESOTA
C U s e rs \e b e rl y d r\ D o c u m e n ts
\R e v it T e m p \3
B L
D G
A R
C H
C
F e b e rl y d r.
rv t
/9
/2
:5
:1
P
M
As indicated
1322 - G-005
TW DRE
EXPAND OUTPATIENT MENTAL HEALTH
AREA K - FIRST FLOOR PHASING PLAN
GENERAL
05-05-2017 DWG. 5 OF 94
1/8" = 1'-0"
1 AREA K FIRST FLOOR PHASING PLAN
PHASING GENERAL NOTES
1 PHASING PLAN IS TO GIVE THE GENERAL
CONTRACTOR THE INTENT OF THE SEQUENCE FOR
THE WORK.
2 GENERAL CONTRACTOR SHALL BE RESPONSIBLE
FOR PREPARING A DETAILED PHASING PLAN AND
ENSURING ALL WORK IS COMPLETED TO ALLOW FOR
TURN OF SPACES IN THE ORDER INDICATED BY THE
PHASING PLAN.
3 GENERAL CONTRACTOR SHALL COORDINATE THE
DETAILED PHASING PLAN WITH ALL TRADES.
4 ADDITIONAL COSTS INCURRED DUE TO IMPROPER
SEQUENCING OF THE WORK SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR ALONE.
5 PROTECT ALL ITEMS NOT SHOWN TO BE DEMOLISHED
FROM ANY DAMAGE. REPAIR ANY DAMAGE TO
LIKE-NEW CONDITION.
6 GENERAL CONTRACTOR IS RESPONSIBLE FOR
PROVIDING TEMPORARY PARTITIONS AS REQUIRED
TO ENSURE THE SAFETY AND SECURITY OF THE
FACILITY DURING CONSTRUCTION.
7 COORDINATE REMOVAL ALL EQUIPMENT WITH ALL
OTHER TRADES AND VA STAFF.
PHASING STAGES
PHASE 1
1.1 CONSTRUCT NEW STORAGE ROOM
1.2 DEMOLISH WORK TO CREATE TEMPORARY LOBBY
1.3 CREATE TEMPORARY STAFF DESK AND WORK AREA
1.4 INSTALL FINISHES FOR TEMPORARY FACILITIES
1.5 TURN OVER TEMPORARY FACILITIES
PHASE 2
2.1 INSTALL TEMPORARY PARTITIONS FOR ATRIUM
DEMO AND BUILD-OUT
2.2 DEMOLISH EXISTING PLANTERS
2.3 DEMOLISH EXISTING WORK IN PHASE 2 AREA
2.4 CONSTRUCT NEW STRUCTURAL FRAMING SYSTEM
AND FIREPROOF NEW STRUCTURAL WORK
2.5 CONSTRUCT CORRIDORS 1P-108 AND 1P-109; TURN
OVER FOR USE
2.6 BUILD-OUT OF NEW WORK IN PHASE 2 AREA
2.7 TURN OVER PHASE 2 AREA
PHASE 3
3.1 INSTALL TEMPORARY PARTITIONS FOR PHASE 3
DEMO AND BUILD-OUT
3.2 DEMOLISH EXISTING WORK IN PHASE 3 AREA
3.3 CONSTRUCT BUILD-OUT OF PHASE 3 AREA
3.4 TURN OVER PHASE 3 AREA
PHASE 4
4.1 INSTALL TEMPORARY PARTITIONS FOR PHASE 4
DEMO AND BUILD-OUT
4.2 DEMOLISH EXISTING WORK IN PHASE 4 AREA
4.3 CONSTRUCT BUILD-OUT OF PHASE 4 AREA
4.4 TURN OVER PHASE 4 AREA
PHASE 5
5.1 INSTALL TEMPORARY PARTITIONS FOR PHASE 5
DEMO AND BUILDOUT
5.2 DEMOLISH TEMPORARY LOBBY, STAFF DESK AND
STAFF WORK AREA.
5.3 CONSTRUCT BUILD-OUT OF PHASE 5 AREA
5.4 TURN OVER PHASE 5 AREA
PHASE 6
6.1 REMOVAL OF EXISTING CORRIDOR FINISHES AND
PREP FOR NEW FINISHES
6.2 INSTALLATION OF NEW CORRIDOR FINISHES
6.2 PROJECT SUBSTANTIAL COMPLETION AND
CLOSE-OUT
DESCRIPTION DATE