This Data Item Description outlines reporting requirements for an in-progress review and report to provide oversight of contractor activities and monitor progress on work performed under the Logistics Modernization Integration Support contract for the Defense Logistics Agency Distribution. The report must include general information such as the contractor's name and CAGE code, contract number, address, phone number, period of performance, and place of performance. It must also detail all activities and deliverables completed in the preceding month, the total percentage complete of tasks and subtasks according to the project schedule, and anticipated activity for the next reporting period. The report is required to identify all known contractor risks to schedule, deliverables, projects, milestones, tasks, or other activities that could prevent or degrade performance, along with the consequence and likelihood of each risk. Additional information necessary for successful government surveillance or items requiring attention must also be provided.
View the file
Other files
Show 40 more
Latest 50 of 84 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Form Approved OMB No. 0704-0188
Page ___ of ___ Pages
PREVIOUS EDITION MAY BE USED.DD FORM 1664, AUG 96 (EG)
DATA ITEM DESCRIPTION
1. TITLE 2. IDENTIFICATION NUMBER
3. DESCRIPTION/PURPOSE
4. APPROVAL DATE
(YYYYMMDD)
5. OFFICE OF PRIMARY RESPONSIBILITY (OPR) 6a. DTIC APPLICABLE 6b. GIDEP APPLICABLE
7. APPLICATION/INTERRELATIONSHIP
8. APPROVAL LIMITATION 9a. APPLICABLE FORMS 9b. AMSC NUMBER
10. PREPARATION INSTRUCTIONS
11. DISTRIBUTION STATEMENT
Distribution Statement A: Approved for public release; distribution is unlimited.
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS.
| DI-LMIS-00011 Certificate of Compliance |
| DI-LMIS-00003 Drawings, Engineering, and Associated Lists |
| Untitled |
DD Form 1664 (BLANK)
Certificate of Compliance (Figure 1)
10 PREPARATION INSTRUCTIONS: 10.1 Format: The IPR and report must be in the Contractor's design unless otherwise specified on the Contract Data Requirements List (CDRL / DD Form 1423). Unless stated otherwise on the CDRL, the deliverable to the Government must be provided in digital format and viewable using the latest version of Microsoft Office or Adobe software products as applicable.
10.2 Content: The IPR and report must contain all of the following:
10.2.a General Information: The Contractor's Name and CAGE Code; Contract Number; Contractor's Address; Contractor's Commercial Telephone Number; Period of Performance (PoP) (if applicable); and physical place of contract performance.
10.2.b Activities: All activities and deliverables completed during the preceding month; a total percentage % complete of deliverables, tasks, and subtasks according to the project schedule and/or Integrated Master Schedule (IMS) (if utilized); and anticipated activity for the next reporting period.
10.2.c Risk Management: Identification of all Contractor known risks to schedule, deliverables, projects, milestones, tasks, subtasks, or any other activities that would prevent and/or degrade performance on the contract. The risks must be identified by both consequence and likelihood of occurrence if they were to result in issues. Additionally, the report must provide any additional information necessary for successful Government surveillance and/or items / problems requiring Government attention.
| PAGE NUMBER 1: 1 |
| 1 TITLE: In-Progress Review (IPR) and Report Requirements |
| 2 IDENTIFICATION NUMBER: DI-DLAMGMT-00014 |
| 3 DESCRIPTIONPURPOSE: The IPR provides the Government oversight of Contractor activities and supports the monitoring of progress on work performed. This documentation is necessary for Government verification of successful performance throughout the duration of the contract. |
| 4 APPROVAL DATE YYYYMMDD: N/A |
| 5 OFFICE OF PRIMARY RESPONSIBILITY OPR: DLA Information Operations - J62B |
| 6a DTIC APPLICABLE: N/A |
| 6b GIDEP APPLICABLE: N/A |
| 7 APPLICATIONINTERRELATIONSHIP: 7.1 This Data Item Description (DID) is applicable to all contractor performance and work actions necessary to comply with requirements described within the contract. |
7.2 This DID may be applied to programs or projects during Material Solution Analysis (MSA), Technology Maturation & Risk Reduction (TMRR), Engineering & Manufacturing Development (EMD), Production & Deployment (P&D), and Operations & Support (O&S) phases of the Defense Acquisition Life Cycle.
| 8 APPROVAL LIMITATION: N/A |
| 9a APPLICABLE FORMS: N/A |
| 9b AMSC NUMBER: N/A |
| PAGE NUMBER 2: 1 |