Sol_SBSA_GC_April 2024.pdf
PDF 288 KB Posted
- Attached to
- Haines / Fairbanks Generators Federal contract opportunity
- Solicitation number
- 47PL0124R0032
About this file
This document is a solicitation for a design-build contract to replace electrical generators at the Dalton Cache Land Port of Entry in Haines, Alaska and the Fairbanks Federal Building in Fairbanks, Alaska. The contract will be set aside for small businesses and has an estimated price range between $1,000,000 and $5,000,000, including options.
The solicitation requires offerors to submit a price proposal, technical proposal, representations and certifications, and other required forms. The technical proposal should address the offeror's proposed plan and management approach, experience on comparable projects, past performance, and schedule. The General Services Administration (GSA) will evaluate offers using a best value trade-off process, considering both price and non-price factors. The solicitation provides instructions for submitting proposals, which are due by July 31, 2024. The contract award is anticipated around October 1, 2024.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Solicitation No. 47PL0124R0032
Document: C201-SB GC/April 2024 (The Solicitation)
Construction Contract for: Haines/Fairbanks Generators
The Solicitation
Table of Contents
I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers
II. Proposals
A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors
III. General Provisions
A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding and Dissemination of Controlled Unclassified Information
(CUI) Building Information
IV. FAR/GSAR Solicitation Provisions
A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR 101-29
B. FAR 52.211-3, Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Items Description
C. FAR 52.216-1 Type Of Contract D. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of
Work E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure
Equal Employment Opportunity for Construction F. Buy American Requirements G. Buy American Exceptions H. FAR 52.233-2 Service of Protest I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference J. GSAR 552.102 Incorporating Provisions and Clauses by Reference K. Additional Provisions
(i) GSAR 552.236-74, Evaluation of Options (Mar 2019)
(iii) GSAR Clause 552.236-77, Government’s Right to Exercise Options (Mar 2019)
L. Certified Cost or Pricing Data
V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition B. Security Requirements C. Additional Clauses
VI. Method Of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Non Price Factors F. Evaluation of Joint Ventures
Notice of Equal Employment Opportunity (EEO) Compliance Plan GSA has partnered with the Department of Labor to ensure compliance with equal employment opportunity requirements that apply to this project. An EEO Compliance Plan is required after the award.
Notice of Commercial Package Carriers Because of increased security standards, commercial package carriers may experience delays in making deliveries to the address designated for receipt of offers. United States Mail delivered to Government offices in the Washington, DC area is subject to irradiation, significantly delaying deliveries and potentially damaging or defacing mail contents. Offerors should take these facts into consideration when determining how and when to transmit offers to the office designated for receipt.
I. General Information
I.A. The Solicitation and Contract
(1) This Solicitation is set-aside for Small Businesses, in accordance with FAR 19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein.
The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
I.B. List of Solicitation Documents The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Standard Form (SF) 1442 – Solicitation Offer and Award
(4) The Agreement and Attachments to the Agreement
(5) Other Forms Required For Submission with Proposals
I.C. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this Solicitation:
Authorized Representative Information:
Contracting Officer’s Information
Name: Heather M. Bowden
Address: 1301 A Street, Suite 610 Tacoma, WA 98401
Telephone: 253.204.5631
Email: heather.bowden@gsa.gov
Alternate POC Information
Name: Vergel M. Dancel
Address: 904 W. Riverside Ave, Room 135 Spokane, WA 99201
Telephone: 509.564.6372
Email: vergel.dancel@gsa.gov
I.D. Pre-Proposal Conference N/A – See below for site visit information for each project.
I.E. Estimated Price Range The estimated price range for the Project is between $1,000,000.00 and $5,000,000.00 (includes optional CLINs).
I.F. FAR 52.228-1 Bid Guarantee (Sep 96)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds— mailto:heather.bowden@gsa.gov mailto:vergel.dancel@gsa.gov
(1) To unsuccessful bidders as soon as practicable after the opening of bids;
and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) Site visits will be held at the following dates and times:
Date: July 2, 2024 Time: 11:00AM AKDT Location: Fairbanks Federal Building – 709 W. 9th St, Fairbanks, AK 99801
- NOTE: Vendors will meet Doug Fell at the 1st floor lobby, past security.
Date: July 11, 2024 Time: 11:00AM AKDT Location: Dalton Cache Land Port of Entry – Milepost 42 – Haines Highway Dalton Cache, AK
- NOTE: Vendors will meet Ronnie at the main port of entry building.
https://www.acquisition.gov/far/part-52#FAR_52_236_2 https://www.acquisition.gov/far/part-52#FAR_52_236_3
(3) Pre-registration is required for all attendees to the pre-proposal Site Visit. The Site Visit shall be limited to not more than four (4) representatives from each Offeror. Offerors shall submit a Visit Authorization Request (VAR) identifying all attendees from their respective team. Participants must have a valid, Government issued picture identification, driver’s license preferred, to gain access for the pre-proposal Site Visit. Notification of the location of entry, where attendees are required to meet, and all other requirements for the Site Visit will be issued to the Offerors. Submit the VAR to the point of contact listed below.
Vergel Dancel, vergel.dancel@gsa.gov
Heather Bowden, heather.bowden@gsa.gov
For further information about the site visit or access requirements, please contact:
Name: Ronnie Mayfield Project Location: Dalton Cache Land Port of Entry – Milepost 42 – Haines Highway Dalton Cache, AK Telephone: 907.740.8782 Email: ronnie.mayfield@gsa.gov
Name: Doug Fell Project Location: Fairbanks Federal Building – 709 W. 9th St, Fairbanks, AK 99801 Telephone: 907.317.1468 Email: douglas.fell@gsa.gov
I.H. Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 3:00 pm local time on the following date and at the following address.
Date: July 31, 2024 Address: Email to heather.bowden@gsa.gov and vergel.dancel@gsa.gov (ONLY) mailto:ronnie.mayfield@gsa.gov mailto:douglas.fell@gsa.gov
II. Proposals
II.A. Proposal Contents
Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
1. Price Proposal
2. Technical Proposal
3. Representations and Certifications
4. Standard Form 24, Bid Bond
5. GSA Form 527 – Contractor’s Qualification and Financial Information
6. Proprietary Information Agreement(s)
7. Other Documents as Required
II.B. Proposal Format Submit the documents below by email, as separate files, no later than the date and time due as established by this solicitation as noted on the SF1442. Additional information may be submitted as it relates to the project.
Volume ITO Paragraph Number Volume Title Page Limit
I Administrative No Limit
Section A A1. Cover Letter 3 Pages
A2. List of ALL Sub-Contractors to include UEI
Section B B. Completed/signed SF 1442 and Continuation Page with CLIN Structure No Limit
Section C C. Acknowledged/signed Amendments (if any) No Limit
II Detailed Evaluation Factor Responses
Section A A. Factor 1: Proposed Plan and Management Approach 20
Section B B. Factor 2: Experience on Comparable Projects No Limit
Section C C. Factor 3: Past Performance No Limit
Section D D. Factor 4: Schedule No Limit
III Price No Limit
Section A A.
Factor 5.1: Price - CLINs 0001 and CLIN 0002 - Fairbanks: Replace Emergency Generator
Offerors shall submit a price proposal on the SF1442 with a separate cost breakdown for CLINs 0001 and 0002. The cost breakdown shall be in CSI Level III format and shall include copies of all subcontractor proposals/quotes.
No Limit
Section B B.
Factor 5.2: Price - CLINs 1001 and CLIN 1002 - Dalton Cache: Replace Automatic Transfer Switch
(ATS)
Offerors shall submit a price proposal on the SF1442 with a separate cost breakdown for CLINs 1001 and 1002. The cost breakdown shall be in CSI Level III format and shall include copies of all subcontractor proposals/quotes.
No Limit
Section C C. *NOTE: CLINs 2001 and 3001 will not be priced at this time. See CLIN details for additional information.
NOTE: Page limitations shall be treated as maximums. Pages in excess of the above limitations will be removed and disregarded during the evaluation. Each page shall be counted except as annotated above.
Volume II – Detailed Evaluation Factor Responses. Offerors shall submit an electronic file of all
Volumes and shall be organized according to the above outline. The intent of the above outline is to give the offeror a general format to facilitate a timely evaluation by the Government:
The technical approach (Volume II) shall not make reference to price data. The technical approach will primarily describe the capability of your organization to perform the requirements of the contract, it should be specific and complete in every detail. A positive statement to the effect that you will accomplish all requirements per the statement of work (SOW) is not acceptable. The proposal shall not merely offer to perform work in accordance with the SOW but shall outline the actual methods proposed as specifically as possible. It is the Offeror’s responsibility to ensure the completeness of the technical approach; hence, the Government technical review team will evaluate on the basis of the information provided in the technical approach. The Government shall not assume that an Offeror possesses any capability unless specified in the proposal. All requirements specified in the SOW are mandatory. By submission of a proposal, the Offeror represents that they will perform all requirements specified in the SOW. Evaluation Factors are located in II.D. and will be used to evaluate offers proposal based on the written information submitted by the Offeror.
Volume III, Factor 5 - Price. All CLIN pricing information shall be addressed in Volume III only.
The completed CLIN schedule with total cost breakout shall be included in Volume III, Factor 5 - Price. All dollar amounts provided in response to these instructions shall be stated in United States (U.S.) currency.
Text size and formatting. Pages shall be single-spaced. Except for the reproduced sections of the solicitation document, the text size shall be no less than font size 10. Use at least one inch margins on all four sides of the page. Pages shall be numbered sequentially by volume.
II.C. Price Proposal
(1) Contents
The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) Additional Proposal Requirements ~ N/A
II.D. Technical Proposal
The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.
FACTOR 1: Proposed Plan and Management Approach
Proposed plan and Management Approach to provide design-build services for each project in accordance with attached Statement of Work.
The offeror shall submit a narrative (maximum of twenty (20) pages) that describes the offeror’s technical approach and management plan for the project demonstrating an acceptable understanding of job responsibilities and requirements, and strategy for completing the construction within the project limits – in accordance with the Statement of Work, Section 2, “Scope of Work”. Narrative shall address each and every aspect described in Section 2. Narrative shall describe the Offeror’s Quality Control Plan and Site Safety Plan.
Narrative shall include name of key prime contractor employees and qualifications of each discipline that will be working on this project to include the Design Team. Design Team Professionals must be licensed in the State of Alaska. This narrative must include trades for subcontractors and names of subcontractors that will be working on this project. Manufacture product information is to be included as attachment to narrative.
Offeror shall use the Key Personnel format, Exhibit 1 included in the Solicitation, to identify and define requirements for Key personnel.
Narrative shall demonstrate Offeror’s ability to effectively coordinate trades, ability to complete project within the approved schedule, and critical phasing of work. Narrative should demonstrate offerors’ ability to ensure delivery of quality product and service, and management of resources and subcontractors.
FACTOR 2: Experience on Comparable Projects
The offeror shall submit a minimum of three with a maximum of four project examples demonstrating relevant experience examples utilizing the Exhibit 2 Project Experience form demonstrating relevant experience. Each project shall be no more than two pages.
“Relevant” is defined as projects similar to the project describe in this RFP in scope, magnitude and complexity and have a logical connection with the requirements of this RFP. Examples of relevant experience include similar design/build generator replacement projects in cold climate, remote locations.
Examples shall include Offeror’s ability to effectively coordinate trades, ability to complete projects within the approved schedule, and critical phasing of work. Narrative should demonstrate offeror’s ability to ensure delivery of quality product and service;
effectively control costs, manage contract changes; complete projects within the approved schedule; and management of resources/subcontractors.
Offerors shall submit a current Point of Contact (POC) for each project. The POC information shall include the name, phone number, and email address for each project submitted. The Government reserves the right to contact the point of contact provided by the offeror to verify the offeror’s experience on comparable projects. All projects submitted must be at least 75% complete or must have been completed within the last three (3) years from the date proposals are due (for this RFP).
FACTOR 3: Past Performance of the Offeror
In accordance with FAR 42.1503(e) and GSAM 515.305, past performance of the proposed offeror will be evaluated using the Contractor Performance Assessment Reporting System (CPARS). If an offeror does not have past performance information available from CPARS, the information received from the examples submitted from the Offeror will be used. A lack of past performance information will result in a neutral rating during evaluation. Government databases will be checked and previous customers may be contacted as references. In accordance with FAR 15.306, the offeror will be given the opportunity to respond to adverse past performance information. This factor will be evaluated based upon the written response to the RFP by the Offeror and the past experience demonstrated by the presented projects. The Offeror must submit a Past Performance Questionnaire (PPQ) (included in the solicitation as Exhibit 3), completed by the applicable client, for each project included in its proposal for Factor 3.
Questionnaires should demonstrate offerors ability to ensure delivery of quality product and service; effectively control costs, manage contract changes; complete projects within the approved schedule; and management of resources/subcontractors.
Completed PPQs should be submitted with the proposal. Ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the Offeror is unable to obtain a completed PPQ from a client for a project before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the project. If the client requests, the client may submit a questionnaire directly to the Government’s point of contact, via email at heather.bowden@gsa.gov and Vergel.Dancel@gsa.gov prior to proposal closing date. Offerors may resubmit questionnaires previously submitted with other proposals or may obtain an updated/new PPQ from a client for any submission.
Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.
Also include performance recognition documents received within the last 6 years such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all UEI numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal, inquiries of owner representative(s), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror.
While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain database of PPQs submitted by Offerors.
FACTOR 4: Schedule The offeror shall submit a construction schedule, assuming that reflects the full period of performance of the base, options and alternate item, showing the order in which the Offeror proposes to perform the work. The schedule start date shall use an award date on/or about October 1, 2024.
The schedule shall include the dates on which the Offeror anticipates starting and completing the work (including options, proposed alternate, security clearances, submittals, acquiring materials, labor, and equipment). The schedule shall be in an electronic format that can be uploaded into, and is fully compatible with, Microsoft Office Project 2010®. The elements of the schedule shall be able to be copied and manipulated for analysis by the Government (e.g. no locked or protected cells, worksheets, etc.) The schedule shall be of suitable scale to indicate the percentage of work scheduled for completion by any given date during the construction period. In addition to the schedule, Offeror is to provide a schedule and narrative not to exceed three (3) pages describing scheduling and coordination. The schedule is excluded from the page limitation. The narrative shall identify milestones critical to the project, schedule coordination to meet construction time frame, inspection and testing, submittals, long lead items and risks. The Narrative should clearly define the offerors’ understanding of the project and ability to meet the construction period of performance requirements as described in the RFP Scope of Work.
METHOD OF AWARD:
Tradeoff Analysis/Information: The Government will utilize Best Value - Trade-off process to select the best value offer for this project. Award of a contract resulting from this procurement will be to the responsible Offeror whose offer conforming to the Solicitation will be most advantageous to the Government, price and non-price (Technical) factors considered. The “Best Value Trade- Off” approach is a method of evaluating price and other factors specified in the RFP with the goal to select the proposal that offers the greatest value to the Government in terms of performance and other factors. The objective is to select the proposal that represents the best value for the proposed price, not necessarily the lowest price. This approach provides the opportunity to evaluate cost/technical trade-offs and does not require the award to be made to the Offeror submitting the lowest price proposal or highest technically rated.
It is the intent of the Government to award without discussions. Therefore, Offerors will be required to initially submit proposals to the Government on the most favorable terms from a technical and price standpoint. However, the Government reserves the right to enter into discussions if it so desires. If it is determined that the award cannot be made without discussions, a competitive range will be established.
II.E. Other Information to Submit with Proposal
(1) Representations and Certifications
Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management.
Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301).
(2) Qualifications of Offerors
Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.
Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.
https://www.sam.gov/
II.F. Requirements of Joint Venture Offerors
(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.
(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.
(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.
(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.
III. General Provisions
III.A. Availability of Funds
Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation
The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 5 calendar days. Prospective Offerors should make such requests not less than 10 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms
A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
http://www.sba.gov/ http://www.sba.gov/
III.D. Information Concerning the Disclosure of Solicitation Results
This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program
GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement.
Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.
III.F. Notice Concerning Preparation of Proposals
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
III.G. Bond Requirements
If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.
III.H. Contractor Performance Information
(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment
Completed CPARS evaluations may then be used by Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.
http://www.cpars.gov/ http://www.cpars.gov/
(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an email that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.
(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information
Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
https://www.cpars.gov/lc.htm
IV. FAR/GSAR Solicitation Provisions
IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101–29, and copies of Federal specifications, standards, and product descriptions can be downloaded from the ASSIST website at https://assist.dla.mil.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained from the ASSIST website identified in paragraph (a) of this provision.
(End of provision)
IV.B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (JUN 1988)
(Applicable to solicitations that cite specifications not listed in the Index and are not furnished with the solicitation)
(a) The specifications cited in this solicitation may be obtained from: GSA Specifications Unit at (202) 755-0325. MIL Specifications may be obtained by calling
(215) 697-2179.
(b) The request should identify the solicitation number and the specification required by date, title, and number as cited in the solicitation.
IV.C. FAR 52.216-1 Type of Contract (APR 84) The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
IV.D. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 14)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
https://assist.dla.mil/ https://assist.dla.mil/ https://assist.dla.mil/
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
IV.E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the
Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade
Goals for Female Participation for Each Trade
15.1% 6.9%
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade.
The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is: Alaska, Haines & Fairbanks county and Skagway. Additional covered areas will be included as part of negotiations for CLINs 2001 and 3001.
IV.F. Buy American Requirements
FAR 52.225-10 Notice of Buy American Requirement-Construction Materials (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.acquisition.gov/far/part-52#FAR_52_225_9
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
IV.G. Buy American Exceptions
N/A
IV.H. FAR 52.233-2 Service of Protest (SEP 06)
(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
IV.I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference
(FEB 98)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.gsa.gov/forms-library/solicitation-offer-and-award-construction-alteration-or-repair provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:
Federal Acquisition Regulation
NUMBER TITLE DATE
52.204-22 Alternative Line Item Proposal JAN 17
52.214-34 Submission of Offers in the English Language
APR 91
52.215-16 Facilities Capital Cost of Money JUN 03 52.236-28 Preparation of Proposals -
Construction
OCT 97
IV.J. GSAR Clause 552.102 Incorporating Provisions and Clauses
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
IV.L. Additional Provisions
(i) GSAR 552.236-74, Evaluation of Options (Mar 2019) The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options (Mar 2019)
(a)The Government may exercise any option in writing in accordance with the terms and conditions of the contract within 90 calendar days of contract award.
(b)If the Government exercises the option, the contract shall be considered to include this option clause.
IV.M. Requiring Certified Cost or Pricing Data [15.403-4]
N/A
V. Instructions and Clauses
V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (NOV 2021)
(a) Definitions. As used in this provision-
Discussions are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.
In writing, "writing," or "written" means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
Proposal modification is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
Proposal revision is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
Time, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show–
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal.
Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals. (i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii) (A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and-
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
https://www.acquisition.gov/far/52.215-5#FAR_52_215_5…