FFB GEN DB SOW 2024-04-25.docx

DOCX document 58 KB Posted

Attached to
Haines / Fairbanks Generators Federal contract opportunity
Solicitation number
47PL0124R0032
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document is a Statement of Work (SOW) for a design-build contract to replace the emergency generator at the Fairbanks Federal Building in Fairbanks, Alaska. The key details are:

The project requires the contractor to develop a full set of engineering drawings and specifications to replace the existing 175kW diesel backup generator, which is beyond its service life. The new generator must be similar in size, EPA compliant, and integrated with the existing cooling system and building automation. The contractor must also demolish and replace the existing automatic transfer switch, fuel day tank, and generator accessories. The contractor will be required to provide a warranty for the new generator system as well as operational and maintenance training for GSA. The period of performance is 335 calendar days from award to substantial completion, plus 30 days to final completion. The contract includes specific submittal and documentation requirements, testing procedures, acceptance criteria, and general project management responsibilities.

View the file

Other files for this federal contract opportunity

Other files attached to Haines / Fairbanks Generators, newest first.
File Type Posted
Sol_SBSA_GC_April 2024 amend 05.pdf PDF
Solicitation Amendment 47PL0124R0032_0005.pdf PDF
2017-12-18 Fairbanks Arc Flash Hazard Analysis Report.pdf PDF
Copy of Fairbanks Original MCC Drawings.pdf PDF
Copy of Fairbanks002.PDF PDF
Copy of Fairbanks Original Safety Switches.pdf PDF
R10 SOW for Dispose Replace Electrical Generators REV 1 8_2_2024.docx DOCX document
Solicitation Amendment 47PL0124R0032_0004.pdf PDF
Copy of Fairbanks Original Panelboard Drawings.pdf PDF
Copy of AK0029ZZ 1979-07-10 FEDERAL BUILDING - ELECTRICAL - POWER ONE LINE AND RISER DIAGRAM.pdf PDF
Copy of 2016-11-11 FBKS HVACR - Updated Electrical As-Builts E3-2.pdf PDF
2017-10-10 Fairbanks One Line (2).pdf PDF
Copy of Fairbanks Original Dist Panel Drawings.pdf PDF
Copy of Fairbanks001.PDF PDF
Generator PPI Log- Questions and Responses.xlsx XLSX spreadsheet
Sol_SBSA_GC_April 2024 amend 03.pdf PDF
Solicitation Amendment 47PL0124R0032_0003.pdf PDF
Solicitation Amendment 47PL0124R0032_0002.pdf PDF
Sol_SBSA_GC_April 2024 amend 02.pdf PDF
Sol_SBSA_GC_April 2024 amend 01.pdf PDF
FFB GEN DB SOW 2024-07-08.docx DOCX document
Solicitation Amendment 47PL0124R0032_0001.pdf PDF
Att 3_PMIS Kahua.pdf PDF
Att 7_R10 - Electrical and Telecom DC Reqs.pdf PDF
7_8 Haines LPOE Replace ATS SOW.pdf PDF
R10 SOW for Dispose Replace Electrical Generators 4_26_2024.docx DOCX document
Exhibit 1 - Key Personnel Resume Format.pdf PDF
Exhibit 2 - Project Experience Form.pdf PDF
Att 4_CD_Waste_Mgmt_Plan_Report_Temp.xlsx XLSX spreadsheet
Att 6_P-120.pdf PDF
Att 5_R10 NCMMS Asset ImpExp Template.xlsx XLSX spreadsheet
7_2_Vendor Security Training_6_2021.pptx PPTX presentation
7_5 R10 NCMMS Asset Equipment In-Place Template .xlsx XLSX spreadsheet
Sol_SBSA_GC_April 2024.pdf PDF
Att 1_Vendor Security Training_6_2021.pptx PPTX presentation
Att 8_GSA Func requirements.pdf PDF
7_3_Controlled Unclassified Information CUI 3490_3.pdf PDF
WD AK20240001 06142024.pdf PDF
Exhibit 3 Past Performance Questionnaire.docx DOCX document
Exhibit 00 - Read Me First - CUI Document.docx DOCX document
47PL0124R0032 Form.pdf PDF
Att 9_Exhib 5a - Fire Alarm Design-Install-Test Policy.pdf PDF
Att 2_Controlled Unclassified Information.pdf PDF
Att 10_Exhib 5b - Policy for Fire Watch-Suppression.pdf PDF
Att 11_GSA FFB Project location.pdf PDF
7_4 External Users Access To Kahua .pptx PPTX presentation
7_6_ PBS 120 .pdf PDF
7_7_LPOE_Replace Day tank SOW Rv2.pdf PDF
Reps and Certs GC May 2024.pdf PDF
Agr_SBSA_GC_May 2024.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. General Services Administration Region 10 Public Buildings Service www.gsa.gov

Statement of Work for Design Build (DB) Contract April 25, 2024

PROJECT IDENTIFICATION

Project Title: GSA Replace Emergency Generator

Building: Fairbanks Federal Building

Building ID #: AK0029ZZ

Building Location: 709 W 9th St, Fairbanks, AK 99801

TABLE OF CONTENTS

1. Project Information3
2. Scope of Work5
3. Deliverables and Submittal Schedule9
4. Applicable Standards19
5. Acceptance Criteria20
6. General Requirements22
7. Attachments27

1. Project Information

1.1. Location of Work:

1.1.1. Building Number: AK0029ZZ

1.1.2. Name: Fairbanks Federal Building

1.1.3. Address: 709 W. 9th St, Fairbanks, AK 99801

1.1.4. Area: Construction area will be in the basement area surrounding the Generator room and fuel tank. Access is also available from the exterior of the building via removable patio panels.

1.2. Background: The Fairbanks Federal Building (AK0029) was built in 1977 and was constructed to replace the older, downtown federal building/courthouse, later disposed of by GSA, and now known as the privately-owned Courthouse Square. The significant increase in the population of Fairbanks during the 1970’s oil industry expansion prompted the need for a new building with increased space for federal offices and courts. The Fairbanks Federal Building has a steel and glass exterior, a steel and concrete interior, and has 3 floors as well as a partial basement level. A four-story attached, open air, covered, garage is located on the west side of the building, and there is an asphalt surface parking lot adjacent to the building. There is adequate parking for tenants and visitors. As seen from an aerial perspective, the building is L-shaped and has a flat roof. The architectural style is considered to be “Great Society-International,” but the building had to be designed to cope with a harsh arctic climate in which temperatures range from 90 degrees in the summer to -40 degrees in the winter (as well as heavy snow loads). The Fairbanks Federal Building is located in the Central Business District and should be classified as providing approximately Class B+ space as compared to other commercial buildings in Fairbanks.

1.2.1. Project Purpose and Summary:

1. The Fairbanks Federal Building emergency backup generator in the basement is not operable and is beyond its service life. Additionally due to the age of the generator replacement parts are no longer available.

It was noted that the existing emergency distribution system does not meet NEC article 700 which applies to the installation of emergency systems that are essential for safety to human life and are legally required by state and federal.

It was also noted that the existing electrical service and equipment is old and original to the building (1977). The equipment has been maintained regularly but has exceeded their service life.

The existing 175kW diesel backup generator is in the basement dedicated emergency generator room. There is a fuel day tank located in the room which is as old as the emergency generator. The day tank is also connected to the building’s diesel fuel storage tank located outside the building.

It was indicated that the current generator is not functioning, old and cannot obtain replacement parts. There is a rented portable generator in the front of the building that is currently serving as a temporary fix.

1.3. Period of Performance:

1.3.1. The period of performance is “three-hundred-thirty-five"(335) calendar days from Award to Substantial Completion and "thirty" (30) calendar days from Substantial Completion to Final Completion, for a total period of performance of (example: "three-hundred-sixty-five" (365) calendar days.

1.3.1.1. The design is required to follow the Design Deliverable schedule in Section 3

1.3.1.2. The construction schedule is required to follow the Construction Notice to Proceed (NTP) and per the negotiated schedule based upon the design progress. (See Section 1.3.1.4)

1.3.1.3. The contractor is required to commence all non-physical construction requirements to include, but not limited to:

1.3.1.3.1. Submission of bonds and/or insurance documents within “ten” (10) calendar days of contract award. The acceptance of the Bonds and Insurance will set the Post Award Meeting date (see Section 6).

1.3.1.3.2. The commencement of background investigation documents within “ten” (10) calendar Days of contract award (see Section 6).

1.3.1.3.3. Approved project submittal log is required prior to the issuance of NTP and as described in Section 3, within “ten” (10) calendar days of award.

1.3.1.3.4. Product submittals are required to be submitted within “fifteen” (15) calendar days of contract award unless otherwise noted (see Section 3).

1.3.1.4. The Contracting Officer will issue a Construction NTP upon acceptance by the GSA of all required documents, submittals, and approval of security clearances. Physical construction work is required to only be allowed after the issuance of NTP by the Contracting Officer.

1.3.1.5. Final completion is required to occur no later than "thirty" (30) calendar days after Substantial Completion. Final completion includes all site cleanup, demobilization, completed and accepted punch list and closeout documents (see Section 3.2.11).

1.4. Project Collaboration and Documentation

1.4.1. Project Management Information System (PMIS) (see attachment 7.3)

1.4.1.1. Project Management Information System (PMIS) - GSA uses PMIS throughout the design and construction phases as a repository for all project information and as a tool to manage and monitor progress and modifications. Unless as otherwise provided, the Contractor will rely exclusively on PMIS to post, review, access, comment on, collaborate, or otherwise submit all project information.

1.4.1.2. The Contractor is required to use GSA’s web-based electronic Project Management Information System (PMIS). PMIS is a web-based project management tool which provides GSA with an automated workflow, collaboration, document management and project management solution to assist GSA in the management of design and construction projects.

1.4.1.3. The current PMIS system in use by GSA is Kahua Project Management Software.

1.4.1.3.1. The Contractor is required to request access to Kahua using the Kahua Account Request Form.

1.5. Work Hours:

1.5.1. The Contractor may perform all work specified for this project during daytime hours: 7 am to 5 pm Monday through Friday, excluding weekends and Federal holidays or nighttime hours: 6 pm to 6 am Monday through Friday, excluding weekends and Federal holidays.

1.5.1.1. The CO/COR reserves the right to direct work activities that disturb the daily operations of the Fairbanks Federal Building and its tenants to be completed during nighttime hours. These activities include but are not limited to: loud noises, closing of access, and power outages.

1.5.2. However, due to several conditions, work that is desired to be performed on the weekend or federal holiday is required to be requested in advance and in writing by the Contractor. The request is required to be reviewed by the Contracting Officer’s Representative (COR) and approved in writing by the CO.

2. Scope of Work

2.1. Task 1 – Design

2.1.1. Develop a full set of engineered, sealed and signed construction documents, with fully developed specifications in CSI Masterformat. The design and specifications are required to be based upon and guided by the latest versions of GSA’s PBS P-100 and PBS P-120. Final documents may be electronically signed. The contractor is required to prepare the construction documents and project design per the attached Design Intent Document (DIDs), the Program of Requirements (POR) and applicable standards (see Section 4).

2.1.2. The contractor is required to prepare the construction documents and project design per attachment 7.8 GSA Generator Functional Requirements.

2.1.3. Architectural services and project specific elements integral to the design, to include, but not limited to:

2.1.3.1. Chairing design charrettes, providing meetings agendas and minutes and project planning.

2.1.3.2. Phased architectural designs, plans, sections, elevations, details and schedules.

2.1.3.3. Engineering and Consultant coordination

2.1.3.4. Design phase submittals with product options

2.1.3.5. Design phase estimates

2.1.3.6. Specifications

2.1.3.7. Facility Specifications, Divisions 01-27, as applicable

2.1.3.8. GSA Fire and Life Safety Design, Installation and Testing Policy (see attachment 7.9 GSA R10 Fire Alarm Design-Install-Test Policy and Attachment 7.10 GSA R10 – Policy for Fire Watch)

2.1.3.9. Design deliverables in AutoCAD 2020 (minimum) and PDF documents.

2.1.4. The design services are required to be derived from GSA and O&M interviews, prior study evaluations (attachment 7.8 “GSA Generator Functional Requirements “) and on-site reviews, to include, but not limited to:

2.1.4.1. Planning charrettes and study reviews with GSA

2.1.4.2. Selective demolition and repair

2.1.4.3. System and assembly deconstruction and repair

2.1.4.4. MEP plans, sections, elevations and details, as applicable

2.1.4.5. Engineering calculations and signed and sealed documents.

2.1.4.6. AutoCAD 2020, PDF documents

2.1.5. General Guidance

2.1.5.1. The project work is required to comply with all federal, state and local environmental laws, regulations, and standards, as well as guidelines on the Sustainable Facilities Tool.

2.1.5.2. Specifications supporting the construction, to include the areas addressed in the construction drawings in CSI Masterformat or COR approved equal.

2.1.5.3. Proposal is required to be broken down by Shell, Tenant Improvements, Security Upgrades, and Hazardous Abatement costs as defined by the GSA Pricing Policy.

2.2. Task 2 - Construction

2.2.1. The contractor is required to construct the accepted design per Section 2.1.

2.2.2. Remove and replace the existing 175kW, 480Y/277V (1800 RPM) diesel backup generator with similar size. New generator must be provided with a main overcurrent protective device.

2.2.3. New generators must be certified as fully EPA compliant at the manufacturing facility.

2.2.4. Tie the Generator coolant system to the existing heat exchanger and verify the cooling tower’s pumps are tied to the generator ensuring that the pumps run when the generator is in use. The heat exchanger transfers heat to the cooling tower's closed loop cooling system.

2.2.5. Provide a permanently installed load bank, sized at a minimum of 50 percent of generator rating. The load bank shall be permanently installed in the fresh air adjacent intake room's east wall. The load bank must not hinder any other room components. The load bank must provide a load add/shed feature that will maintain load levels at a minimum, including building load, of the generator manufacturer's recommended loads when operating at 50 percent of generator KW nameplate. The load bank must have a minimum of four automatic load taps controlled by a load add/shed relay incorporated into the run circuit on the generator.

2.2.6. Seismically anchor/brace new generator and all equipment associated with it.

2.2.7. Utilize existing housekeeping pad.

2.2.8. Remove and replace all generator accessories (FA connections, battery connection, etc.) including the existing generator exhaust. Verify and/or provide the emergency generator's supervision points (i.e. run, trouble, etc), manual start, and transfer features are being monitored by the building's fire alarm system.

2.2.9. Remove the generator room day tank and replace it with a new properly sized day tank in the boiler mechanical room. Tank is to be large enough to support both the generator and boilers. Verify proper piping sizes and fittings to support the new tank to equipment (approximately 400 gallons). Install Day tank per required code/safety requirements. Remove/dispose of any unused fuel pipe from the main fuel piping system.

2.2.10. Install isolation valves to the fuel delivery infrastructure for future Fuel Polishing System. Location to be coordinated with CO/COR.

2.2.11. Remove the continuously operating fuel recirculation motor and any unnecessary fuel lines. Verify properly installed check valves to ensure proper fuel pressure is maintained.

2.2.12. Demolish and replace the existing Automatic Transfer Switch (ATS) with new N10 type (transfer of power within 10 seconds).

2.2.13. Provide a fairly sized pull box (sized per NEC article 314) for future generator emergency feeder splicing to correct NEC article 700 deficiency (future project).

2.2.14. Generator annunciator panel (location to be determined during design/construction phase) with connection to the Fire Alarm Control Panel. Additional remote annunciator panel(s) are optional.

2.2.15. Replace existing feeders associated with the generator replacement.

2.2.16. Connect generator and transfer panel status into the current building automation system.

2.2.17. Refer to the one-line diagram in Attachment 8.

2.2.18. All work must comply with the latest versions of the P-100, NFPA and other codes that are applicable to this project.

2.2.19. Once the generator is replaced, a selective coordination study is required. Fuses and circuit breakers have time/current characteristics that determine the time it takes to clear the fault for a given value of fault current. Selectivity occurs when the device closest to the fault opens before the next device upstream operates. Any fault on a branch circuit should open the branch-circuit breaker rather than the feeder overcurrent protection. All faults on a feeder should open the feeder overcurrent protection rather than the service overcurrent protection. With coordinated overcurrent protection, the faulted or overloaded circuit is isolated by the selective operation of only the overcurrent protective device closest to the overcurrent condition. The main goal of selective coordination is to isolate the faulted portion of the electrical circuit quickly while at the same time maintaining power to the remainder of the electrical system. Provide selective coordination study of the emergency system. Building system model (pdf) as well as input report (pdf only) can be provided. Contractor must confirm existing field data including but not limited to existing breaker sizes, types, conductor sizes, etc.

2.2.20. Provide operational and maintenance training to GSA and designees.

2.2.21. Disconnect and remove temporary generator cabling and repair penetrations.

2.2.22. Install infrastructure to include switches, breakers, and access panels from the Generator room to the exterior of the building for external generator connection.

3. Deliverables and Submittal Schedule

3.1. Task 1 - Design

3.1.1. The contractor and teams are required to attend the Post Award Meeting. GSA will host an administrative Post Award meeting within ten (10) calendar days from the contract award date to review contractual and technical issues, objectives of the project and communication protocols. This meeting will include the discussion of schedules, submittal dates, site conditions and requirements and establish points of contact prior to the commencement of work. At the meeting, the contractor is required to provide evidence that all employees and subs are in the process of being badged (see Section 6.11) and provide for approval of any revisions in the Project Schedule or PMP, per Section 6 below. As a minimum, the following items are required to be discussed:

3.1.1.1. Confirm all preliminary documentation and badging is in process.

3.1.1.2. Clarify outstanding questions.

3.1.1.3. Review security and safety issues.

3.1.1.4. Review the Initial RO List and identify POC 1.

3.1.1.5. Schedule, phasing, integration, and coordination.

3.1.1.6. Schedule site visits and additional discussions.

3.1.1.7. Site conditions and rules.

3.1.1.8. Submittals (see Section 3.1.3)

3.1.2. The days in the schedule below are calendar days. The schedule includes the project’s preparation time, security investigations, kick off meeting and charrette, site investigation and full design and government reviews as follows:

Design Activity
Activity Duration
Remarks
A/E
GSA Team

Security investigations

A/E Coordination Approx. 30 days

Required for unescorted access to Fairbanks Federal Building (concurrent with A/E Prep and Design Kickoff Meeting below).

Design Kickoff Meeting
2 days

Review site and all attachments; Initial charrette, chaired by A/E. Document review. Location to be determined

Investigations, demolition, deconstruction, and repairs
20 days

On site investigations, (Following completed security investigations)

Pre-Design meeting
1 day

Review findings from demolition/investigations; review any developed options or alternatives. Location to be determined.

Planning review and comments

14 days
GSA review
35% Concept Design Preparation
20 days

35% Concept Design Review

14 days
GSA review
35% Design Review Meeting
1 day

35% document submission is required to include the following:

· Schematic plans and options

· ROM Estimate demonstrating design and options cost @ 35% Location to be determined

65% Design Development Preparation
10 days

65% Design Development Review

14 days
GSA review
65% Design Review Meeting
1 day

65% document submission is required to include the following:

· Development plans

· Outline Specifications

· ROM Estimate demonstrating design to cost @ 65%, including selected options Location to be determined.

95% Design Preparation
10 days

Pre-final

95% Design Review

14 days
GSA review
95% Pre-Final Design Review Meeting
1 day

95% document submission is required to include the following:

· Plans

· Specifications

· Construction Estimate demonstrating design to cost. Location to be determined.

100% Construction Design Preparation
10 days

100% document submission is required to include the following:

Stamped plans, specifications, calculations, engineered assemblies and final estimate of construction

100% Acceptance

14 days
GSA review and acceptance

3.1.3. The A/E is required to submit the design documents in an electronic format through Kahua. The final submission is required to include all drawings in .pdf and .dwg format using AutoCAD 2020 and specifications in .pdf with professional seals and signatures of registered architect(s) and engineer(s) of record. Refer to PBS P-100 Appendix A.

Design State

Plans
Specifications
Construction Estimate
Remarks
35%
Electronic Format Acceptable to GSA - Refer to PBS P-100 Appendix A
N/A

The A/E is required to provide pdf versions of all submittals, to include schematic layouts, propose products and assemblies; (see Attachment)

65%
Electronic Format Acceptable to GSA - Refer to PBS P-100 Appendix A
Outline specifications in Microsoft word; CSI MasterSpec divisional format

The A/E is required to provide pdf versions of all submittals, to include Developed plans outline specification and/or product proposals, Budgetary estimate – high confidence -20% +35%

95%
Electronic Format Acceptable to GSA - Refer to PBS P-100 Appendix A
Specifications in Microsoft word; CSI MasterSpec divisional format

The A/E is required to provide pdf versions of all submittals, to include Plans, specifications, and products. In addition, the A/E is required to provide plans in AutoCAD 2020.

100%
Electronic Format Acceptable to GSA - Refer to PBS P-100 Appendix A
Specifications in Microsoft word; CSI MasterSpec divisional format

The A/E is required to provide pdf versions of all submittals, to include Plans, specifications, and products. The final submission is required to include all drawings in .pdf and .dwg format using AutoCAD 2020 and specifications in .pdf.

3.1.4. Meetings - The contractor is required to attend meetings per the schedule in Section 6 and additionally as follows:

3.1.4.1. Upon award the A/E is required to attend an onsite design kickoff meeting. The A/E team composition and attendance is at the A/E’s discretion and cost. The GSA Project Manager will ensure:

3.1.4.2. The GSA Property Manager and his maintenance contractor’s foreman are available to share information and answer questions regarding the building’s infrastructure.

3.1.4.3. Other Government representatives the A/E requests and who are approved for travel or attendance by GSA. GSA will plan and schedule the meetings using GSA meeting tools.

3.1.4.4. The A/E is required to provide the agenda 2 calendar days prior to the meeting and provide meeting minutes no later than 3 calendar days after the meeting.

3.1.5. Following the design kickoff meeting the A/E is required to attend and chair the Pre-Design meeting. The A/E team composition and attendance is at the A/E’s discretion and cost.

3.1.6. The A/E is required to attend and chair all Design Review meetings to present and discuss design phase comments and facilitate progress discussions.

3.1.6.1. Prior to each Design Review meeting the A/E is required to review the Government Review Comments, prepare a written response to those comments and be prepared to discuss each one at the Design Review Meeting.

3.1.7. The A/E is required to generate a submittal register that lists the construction specifications by division number and submit to the COR for review as part of the 95% design review package.

3.2. Task 2 – Construction

3.2.1. PMP - The Contractor is required to prepare and submit to the COR for approval, a Project Management Plan within 10 calendar days following award. The Plan is required to communicate the contractor management approach to the work and is required to include, but is not limited to, the following:

3.2.1.1. Work Plans - The work plan is required to communicate the intent such as work breakdown structures, iterative approach, etc.

3.2.1.1.1. Protection of surrounding materials during operations.

3.2.1.1.2. Describe in detail materials, methods, and equipment to be used for each phase of work.

3.2.1.1.3. Provide sequencing of work, and how the contractor will work with GSA to assure continuity of government operations and services during the work.

3.2.1.2. Communication Plan - The communication plan is required to include a list of key personnel, with contact information.

3.2.1.3. Schedule - The schedule is required to be prepared using Gantt chart format with Critical Path, in Microsoft Project. The schedule shall be submitted in pdf and Microsoft Project formats.

3.2.2. Waste Management Plan per the PBS P-100 1.7.2.2

3.2.2.1. The contractor is required to prepare and submit a Waste Management Plan to the COR no later than 14 calendar days prior to starting Construction Demolition.

3.2.2.2. Construction and Demolition (C&D) Waste Management Requirements: GSA's minimum requirement is to divert 50% of C&D waste from landfills/incinerators, (See Attachments, Waste Management Plan).

3.2.2.3. Document their actual waste diversion performance throughout the project. The Waste Management Plan, therefore, should also include progress reporting procedures to record actual diversion and cost corresponding to each diversion and cost estimate.

3.2.2.4. Provide monthly reports with documentation to the COR.

3.2.3. Site Safety Plan - The Contractor is required to prepare and submit to the COR for approval, an Accident Prevention and Site Safety Plan within 10 calendar days following award. The Site Safety Plan is a living document and is required to be updated to address emergent, current or national conditions. The Plan is required to define how the contractor will protect the general public, their employees and the environment, to include, but not limited to:

3.2.3.1. Responsibilities and Lines of Authority

3.2.3.2. Prime Subcontractors and their participation in the Plan

3.2.3.3. Activity Hazard Analysis (AHA).

3.2.3.4. Accident Prevention Plan

3.2.4. Schedule of Values - The Contractor is required to prepare and submit to the COR for approval, a Schedule of Values (SOV) within 10 calendar days following award. The SOV is required to be defined and expressed in CSI MasterSpec divisional order or as otherwise agreed upon.

3.2.5. Testing Plans and Submittals -

3.2.5.1. The Government reserves the right to witness all specified in-factory and on-site tests of the generator, components, and subsystem. The Contracting Officer shall be notified at least 30 days before in-factory tests are scheduled to be performed and at least 14 days before on-site tests are scheduled to be performed.

3.2.5.2. Submit Facility Acceptance Testing and Final Acceptance Testing Plans at least 30 days prior to testing.

3.2.5.3. Submit certified copies of inspection reports and test reports. Reports shall include certification of compliance with specified requirements, identify deficiencies, and recommend corrective action when appropriate. Type and neatly bind test reports to form a part of the final record. Submit test reports documenting the results of each test not more than 10 days after the test is completed.

3.2.6. Construction Quality Control Plan (CQC) - The Contractor is required to prepare a CQC plan like the Army Corps of Engineer's three phase format - preparatory, initial and follow up phases. Detail of the plan to be commensurate with the complexity and level of the project. (See Section 5.2.1)

3.2.7. Daily Reports - The Contractor is required to submit to the COR a daily report for days when site work is being performed. As a minimum, include the following in the daily report form: report number, date, weather (if an impact to the project), work performed, numbers of workers, list of subcontractors on site, photos and test performed and results. Also include any three-phase inspection performed.

3.2.8. Shop Drawings, Material and Product Submittals

3.2.8.1. The Contractor is required to submit shop drawings and product data as stipulated in the (project plans and specifications in attachment “x”) and/or this Statement of Work. All submissions are required to be made to the Contracting Officer's Representative (COR). Prior to submitting shop drawings to the COR, the Contractor is required to review the shop drawings for completeness and is required to establish that the shop drawings meet the contract requirements.

3.2.8.2. The Contractor is required to provide shop drawings and product data for all systems, equipment and materials per the approved design review documents.

3.2.8.3. All technical drawings are required to have the professional seals and signatures of the preparing Registered Professional Engineers and/or Architects, as applicable.

3.2.8.4. The Contractor is required to utilize early submission to minimize lead time.

3.2.8.5. Each submittal is required to be presented with a letter of transmittal or cover sheet, and provide the following:

3.2.8.5.1. Each submittal is required to be delivered through the Kahua Packaged Submittal App with a letter of transmittal and supporting information included as attachments. Prime Contractor will list themselves as the Vendor and Submittal Coordinator with the GSA PM listed as the Official Reviewer.

3.2.8.5.2. Each submittal is required to be titled, serially numbered and included in an approved submittal log. Rejected submittals are required to be resubmitted with an additional number or character such as .1, .2 or a, b. to identify the submittal history.

3.2.8.5.3. Submittals are required to be logged and outlined using CSI MasterSpec Divisions.

3.2.8.5.4. Provide product sheets defining and demonstrating what and how the product meets the intent of the contract documents and complies with the Buy American Act under the contract.

3.2.8.5.5. Provide SDS as applicable, defining and demonstrating what and how the submittal conforms to PBS Key Sustainable Products Initiative PBS 1096.1.

3.2.8.5.6. The Government requires (14) calendar days for product submittals and (21) calendar days for shop drawings.

3.2.9. Request For Interpretation (RFI)

3.2.9.1. RFIs are required to be provided through the Kahua RFI App with an RFI transmittal form and supporting information included as attachments. Prime Contractor will be listed as Author, and both GSA Project Manager and GSA Contracting Officer will be listed as Primary Responder. Include the following:

3.2.9.1.1. Information Requested - explain in detail your request, including referencing drawings, specification, codes, etc.

3.2.9.1.2. Contractor’s Recommendation - provide a recommendation to the CO to address RFI concerns.

3.2.9.1.3. Time and Cost Impact - indicate if the RFI is for clarification only, no-cost minor field change, or if the RFI may result in a modification for additional time and/or cost.

3.2.9.2. As part of project quality control, the contractor is required to maintain an RFI log to keep track of RFIs. RFI log will be reviewed at QC or progress meetings to discuss RFI status and will be made available to the COR upon request.

3.2.10. Closeout submittals

3.2.10.1. The contractor is required to provide the following closeout documents in electronic format no later than "thirty" (30) calendar days after Substantial Completion, to include, but not limited to:

3.2.10.1.1. Final inspection and test results specified in this Statement of Work, Architectural/Engineer plans and specifications (see Section 5).

3.2.10.1.2. As-built drawing and redline documents.

3.2.10.1.3. Specifications manuals, as applicable, with changes approved during the project.

3.2.10.1.4. Product data and shop drawings:

3.2.10.1.4.1. The contractor is required to combine all inspection and test results, As-builts and shop drawings, product data and specification changes into an electronic record, like pdf.

3.2.10.1.4.2. The data is required to be organized in CSI MasterSpec divisional format and hierarchy.

3.2.10.1.5. Operations and Maintenance Manuals (O&M) in PDF format

3.2.10.1.5.1. The contractor is required to provide detailed O&M manuals identifying the building, floor number, specific space, tools, procedures, equipment and parts necessary to assure satisfactory operation and maintenance per the manufacturer's recommendations.

3.2.10.1.5.2. The contractor is required to provide maintenance training that addresses cycles of replacement and use of any special tools, etc. Include references to record documents, spare parts and material lists, warranties, maintenance agreements and similar continuing commitments.

3.2.10.1.6. Warranty

3.2.10.1.6.1. The Contractor is responsible to provide workmanship warranty of no less than one-year (365-days) from GSA’s acceptance of the project.

3.2.10.1.6.2. The complete system shall be warranted by the manufacturer and/or contractor for a period no less than three years from the date of acceptance. Any component failing to perform its function as specified and documented shall be repaired or replaced by the contractor at no additional cost to the Government. Items repaired or replaced shall be warranted for an additional period of at least one year from the date that it becomes functional again.

3.2.10.1.6.3. The contractor will be required to provide an external backup generator until the warranty repairs are completed and the generator system is back online.

3.2.10.1.6.4. The Contractor is required to provide the government with official copies in electronic format of all warranties. The warranty start date is required to begin no earlier than the date of the installation and acceptance. The warranty letters are required to include the point of contact with current contact information and response times.

3.2.10.1.6.5. The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. Conduct a bi-annual warranty inspections with the Contractor COR and/or Fairbanks Federal Building Property Manager.

3.2.10.1.6.6. The Contractor is required to provide a warranty management plan which will include, but is not limited to, the following:

3.2.10.1.6.6.1. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers, or suppliers involved.

3.2.10.1.6.6.2. For each warranty, the name, address, telephone number, and e-mail of each of the guarantor's representatives nearest to the project location.

3.2.10.1.6.6.3. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.

3.2.10.1.6.6.4. As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:

(1) Name of item.

(2) Model and serial numbers.

(3) Location where installed.

(4) Name and phone numbers of manufacturers or suppliers.

(5) Names, addresses and telephone numbers of sources of spare parts.

(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have warranties longer than one year must be indicated with separate warranty expiration dates.

(7)Cross-reference to warranty certificates as applicable.
(8)Starting point and duration of warranty period.

(9) Summary of maintenance procedures required to continue the warranty in force.

(10) Cross-reference to specific pertinent Operation and Maintenance manuals.

(11) Organization, names and phone numbers of persons to call for warranty service.

(12) Typical response time and repair time expected for various warranted equipment.

3.2.10.1.6.6.5. The plans for attendance at the 4- and 9-month post-construction warranty inspections.

3.2.10.1.6.6.6. Procedure and status of tagging of equipment covered by warranties longer than one year.

3.2.10.1.6.6.7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty or safety reasons.

3.2.10.1.7. Attic Stock

3.2.10.1.7.1. N/A

3.2.10.1.8. Final Requesting Official Contractor Approval List (ROCAL) and Access Credentials

3.2.10.1.8.1. The contractor is required to provide a final ROCAL to the sponsoring GSA Official (COR/PM), indicating the dates that all staff have been removed from the project.

3.2.10.1.8.2. The Contractor is required to return all access credentials to the GSA issuing officials (Property Managers) and provide the COR/PM with written or email confirmation from the issuing official.

4. Applicable Standards

4.1. Conflicts Between Codes or Standards and GSA Requirements - To ensure flexibility, GSA’s policy is to make maximum use of equivalency clauses in all codes and standards. If a conflict exists between GSA requirements and the GSA-adopted codes or standards, the GSA requirements take precedence. All such conflicts must be brought to the attention of the GSA project manager as appropriate for resolution.

4.2. The Contractor is required to be responsible for ensuring compliance with federal, state, and local codes and design standards at the time of award, using the latest editions, including, but not limited to the following:

4.2.1. PBS P-100

4.2.2. PBS P-120

4.2.3. Pricing Desk Guide

4.2.4. 1000.8 PBS Indoor Air Quality Management

4.2.5. PBS Key Sustainable Products Initiative PBS 1096.1

4.2.5.1. In addition to the above listed key sustainable products, all other interior finishes must meet, at a minimum, the baseline environmental requirements specified in the GSA P100 facilities standards, Chapter 3, Architecture and Interior Design. Contractor shall submit product data for each finish material used, demonstrating compliance with the appropriate environmental requirements. Sustainability requirements for specific interior finishes and construction materials may also be found at https://sftool.gov/.

4.2.6. Occupational Safety and Health Administration (OSHA) https://www.osha.gov/Publications/OSHA3990.pdf

4.2.7. Job site standards incorporated into the work.

4.2.8. Region 10 Policy (Fire Life Safety (FLS), Asbestos, etc.)

4.2.9. GSA Emergency Generator Requirements

4.2.10. International Building Code (IBC)

4.2.11. National Electrical Code (NEC)

4.2.12. National Fire Protection Association (NFPA)

4.2.13. Painting and Decorating Contractors of America (PDCA)

4.2.14. Architectural Barriers Act Accessibility Standard (ABAAS)

4.2.15. Building Specific Design Standards (Include as an attachment)

4.2.16. GSA Region 10 - Electrical and Telecommunications Design and Construction Requirements

5. Acceptance Criteria

5.1. Design Review Process

5.1.1. Submittal Reviews

5.1.1.1. Each submittal will have a Government review period of 14 calendar days, during which time the Contractor will not continue development until Government comments are received.

5.1.1.2. Milestone submittal reviews will be electronic reviews, the Contractor will provide PDF versions of the submittal to the COR for distribution to the Government team. The COR will consolidate written comments from the Government team and provide them back to the Contractor.

5.1.1.3. Concluding each Government review period there will be a meeting with the Contractor and the Government team to discuss comments and concerns in a workshop format. These meetings will be held using teleconference and screen-sharing technology, to be coordinated with the COR. See various meetings as stated in Section 6. The Contractor will respond to all comments provided by the Government during each meeting, to be added to the overall written Government comments for that phase of the study.

5.1.1.4. Submittals are not valid until they are accepted in writing by the CO or COR.

5.1.1.5. The Contractor is required to formally respond to all written review comments from GSA within 7 calendar days of receipt. This response, directed to the COR, should indicate agreement/disagreement, how the concern will be addressed within the next submission or resubmission and identify any post meeting follow up that may be required.

5.1.2. Each sheet of the construction documents (100% CDs) are required to bear the seal and signature of the responsible design professional.

5.1.2.1. The specification and calculations are required to be sealed and signed on the cover page only.

5.1.2.2. Each design professional is required to comply with any seal, stamp, and/or signature requirements in accordance with State law. Electronic plans may have digital signatures and seals (reference P-100).

5.2. Construction Submittal Review Process

5.2.1. The Contractor is required to prepare and submit to the Government a Construction Quality Control Plan (CQC) for review, modification and/or acceptance (refer to Section 3.2.7)

5.2.2. The CQC is required to follow the standard format like Army Corps of Engineering and as follows:

5.2.2.1. The Preparatory Phase is required to be performed prior to beginning work on each definable feature of work and after all required documents and submittal materials are approved and/or accepted. Document in the contractor's daily report the results of the preparatory phase action.

5.2.2.2. The Initial Phase is required to be performed at the start of the definable features of work and soon after a reasonable sample of work is completed to establish basic workmanship acceptance standards. Document in the contractor's daily report the results of the initial phase inspection performed.

5.2.2.3. The Follow Up Phase is required to be performed daily or routinely to assure acceptable workmanship standards are maintained and control activities, including testing and safety, are providing continued compliance with contract requirements.

5.3. Visual inspections

5.3.1. Visual inspections are required to be performed for all work elements prior to closing the assembly from vision or upon completion of the installation and are required to be recorded on GSA form 220 by the Contracting Officer's Representative (COR) or Construction Manager (CM).

5.3.1.1. Inspections are required to verify that the assembly or work product meets applicable standards (see Section 4.0) and CQC plans.

5.3.1.2. Inspection Criteria for visual inspections of completed installations are required to be conducted with “normal” lighting, “normal” viewing angles, without magnifications:

· Normal lighting conditions - Normal lighting conditions are described as those in place when the project is finished. This includes, but not limited to, design lighting (e.g. wall washers, spots and floods, etc) and natural lighting.

· Normal viewing position - The normal viewing position is required to be established at a minimum distance of five feet perpendicular from the surface to be viewed.

5.3.1.2.1. Inspection lighting is required to be representative of normal lighting conditions in intensity and location. Consideration is required to be given to window treatment and/or any other decorative finishes that could affect lighting and viewing.

5.3.1.2.2. A normal viewing position is required to be used. Visual evaluation for acceptance can be determined from a normal viewing position, at any angle, provided it is established at a minimum distance of five feet perpendicular from the surface to be viewed.

5.3.1.2.3. When viewed without magnification under occupancy conditions with normal lighting conditions and from a normal viewing position, a level of visual appearance is achieved as established by the approved job site standard.

5.4. Testing And Balancing Report

5.5. Commissioning Report

6. General Requirements

6.1. Post Award Meeting

6.1.1. The contractor and teams are required to attend the Post Award Meeting. The CO/COR will host an administrative Post Award meeting within “ten” (10) calendar days from the contract award date to review contractual and technical issues, objectives of the project and communication protocols. This meeting will include the discussion of schedules, submittal dates, site conditions and requirements and establish points of contact prior to the commencement of work. At the meeting, the contractor is required to provide evidence that all employees and subs are in the process of obtaining security clearances (see Section 6.11) and provide for approval any revisions in the Project Schedule or PMP, per Section 6 below. As a minimum, the following items are required to be discussed:

6.1.1.1. Confirm all preliminary documentation and badging is in process.

6.1.1.2. Clarify outstanding questions.

6.1.1.3. Review security and safety issues

6.1.1.4. Review the Initial RO List and identify POC 1

6.1.1.5. Schedule, phasing, integration, and coordination

6.1.1.6. Schedule site visits and additional discussions

6.1.1.7. Site conditions and rules

6.1.1.8. Submittals (see Section 3)

6.2. Pre-Construction Meeting

6.2.1. The Contractor is required to attend Pre-Construction Meeting conducted on site and coordinated by GSA. Prior to this meeting all Pre-Construction activities (submittals, contractor adjudications, etc.) are required to be complete.

6.2.1.1. Agenda - GSA will provide the agenda NLT 2 days prior to meeting. This meeting will discuss all expectations of each stakeholder associated with this contract.

6.2.1.2. Meeting Minutes - GSA will capture the minutes and distribute to stakeholders NLT one business day after meeting.

6.3. Progress Meetings

6.3.1. The Contractor is required to be available to meet with the GSA Project Manager upon request to present deliverables, discuss progress, exchange information and resolve emergent technical problems and issues.

6.3.2. The Contractor is required to keep GSA informed, through meetings or reports, onsite discussions or emails of progress and potential problems with the project.

6.3.3. The Contractor is required to Chair (weekly/bi-monthly) progress meetings.

6.4. Building Requirements

6.4.1. The building will be occupied by federal staff and potentially the public during the construction phase. The Contractor is required to minimize disruptions and ensure the safety of building tenants and the public is maintained at all times, to include, but not limited to:

6.4.1.1. Keep supplies and materials in their staging areas and provide safety features such as cones, fencing or locked doors.

6.4.1.2. Provide dust and odor containment, meeting GSA Indoor Air Quality standards.

6.4.1.3. Plan noisy or vibrating work to ensure disruptions to the Government operations and work are minimal. Provide planning documents like “Sequence of Operations” or “Look-ahead Schedules” to inform stakeholders.

6.4.1.4. Erect safety barriers (passive and/or active) and provide warning signs.

6.5. Daily Cleanup

6.5.1. The contractor is required to keep all areas open to the public or the tenant free from hazards, dirt and debris.

6.5.1.1. Remove all waste and debris from the worksite and building, by the end of each day.

6.5.1.2. The building disposal system may not be used for construction waste.

6.5.1.3. The contractor is required to provide waste removal for construction debris and a dumpster or roll-off bin with a lockable lid.

6.6. Utilities

6.6.1. Water and electric service will be provided to the Contractor at no cost.

6.6.2. The contractor facility restroom use is approved by the Property Manager.

6.6.3. Utility outages shall be coordinated and requested through the CO/COR no less than twenty-one (21) days.

6.7. Protection

6.7.1. The Contractor is required to provide all labor, material, and equipment necessary to protect personnel, furnishings, equipment or the building structure from damage.

6.7.2. The Contractor is required to provide all engineering controls to protect all areas being worked on from the migration of dirt, dust, oils and spray.

6.7.3. The Contractor is required to replace or repair to the original condition any items damaged due to work performed under this contract, at no additional cost to the Government.

6.8. Work Site Access

6.8.1. The Contractor is required to ensure access to the site maintains the following protocols:

6.8.1.1. Entrance to the worksite is required to be through employee entries or roll up doors for the dock access.

6.8.1.2. Coordinate all deliveries with the Property Manager.

6.8.1.3. Use rubber-tired vehicles for conveying material inside the building and provide temporary covering to protect floors.

6.8.1.4. Provide and/or coordinate elevator wall protections.

6.8.1.5. Provide safety barriers per the site safety plan.

6.9. Safeguard of Equipment, Supplies, and Materials

6.9.1. The Contractor is required to safeguard all equipment, supplies and materials. The Government will not be responsible for any loss or damage to materials, supplies, tools, or equipment on the site, including materials in which salvage value may have been reflected in bid.

6.10. Site Closeout Requirements

6.10.1. The Contractor is required to complete all tasks listed below prior to submitting the final invoice for payment:

6.10.1.1. Clean each surface or unit to the condition expected in a normal, commercial cleaning and maintenance program. Ensure that cleaning covers the pathways to the work site as well as inside the work site. Ensure cleaning materials comply with all manufacturer’s written instructions and meet GSA PBS Key Sustainable Products Initiative PBS 1096.1 and 1000.8 PBS Indoor Air Quality Management.

6.10.1.2. Remove all debris, tools, equipment and materials from the job site.

6.11. Security and Access

6.11.1. General Guidelines.

6.11.1.1. Federally controlled facilities refer to all occupied building areas housing federal operations. Unoccupied building areas under construction are not considered federally controlled facilities, if access to any adjacent or surrounding occupied building areas housing federal operations is separately controlled.

6.11.1.2. All Contractor personnel accessing federally controlled information systems are required to have Homeland Security Presidential Directive 12 (HSPD-12) clearance.

6.11.1.3. In the performance of work required under this contract, all Contractor personnel must present proper identification to gain access to occupied building areas housing federal operations.

6.11.2. HSPD-12 Compliance

6.11.2.1. An HSPD-12 security clearance is not required to access the GSA PMIS. Further information on HSPD-12 may be found at the following website: www.gsa.gov/hspd12. The time to process and obtain clearances may vary in length.

6.11.2.2. If an individual works 15 cumulative days or less in a 6-month period in the existing buildings or secured exterior areas: That person must be escorted by someone with an HSPD-12 badge. Government designated personnel must issue a badge to these individuals.

6.11.2.3. If an individual works less than 6-months in the existing buildings or secured exterior areas: That person must have a short-term HSPD-12 clearance. Government designated personnel must issue a badge to these individuals.

6.11.2.4. If an individual works more than 6 months in the existing buildings or secured exterior areas: That person must have a long-term HSPD-12 clearance with an HSPD-12 badge (GSA Access Card). GSA will issue the GSA Access Card to these individuals.

6.11.3. Security Requirements

6.11.3.1. Comply with all GSA and occupant agency security requirements to access and work with the site/buildings. Contractor’s personnel who require access to GSA PMIS require a GSA Access Card.

6.11.3.2. Refer to FAR 52.204-9 GSA’s HSPD-12 Personal Identity Verification and Credentialing Standard Operation Procedure (SOP). The required Contractor Information Worksheet (CIW) forms will be supplied by the GSA Project Manager. Processing and verification may take 90 calendar days or more to complete and must be factored into the project schedule.

6.11.3.3. The Government bears the cost of performing Tier 1 investigations and credentialing for no greater than fifteen (15) individuals for this project. The Government bears the cost of performing no more than fifty (50) SAC investigations. The GSA Contracting Officer may reduce the Contract Sum by the amount of total expenses associated with additional background investigations and credentialing in accordance with the following schedule:

If the individual requires:
Access to the facility for no more than 15 days in any 6-month period