Att 8_GSA Func requirements.pdf

PDF 774 KB Posted

Attached to
Haines / Fairbanks Generators Federal contract opportunity
Solicitation number
47PL0124R0032
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document is a Functional Requirements document for the Fairbanks Federal Building generator replacement project. The key details are:

The existing 175kW diesel backup generator is old, not functioning, and lacks replacement parts. The project requires demolishing and replacing the existing generator with a similar size that is fully EPA compliant. The new generator must have a main overcurrent protective device and be connected to the existing heat exchanger and cooling system. The project also requires installing a permanently mounted load bank, seismic bracing, replacing the automatic transfer switch, and connecting the generator status to the building automation system. A selective coordination study of the emergency system is also required. The project must comply with current P-100, NFPA, and other applicable codes and standards. This generator replacement project is part of a larger solicitation (47PL0124R0032) issued by the General Services Administration's Public Buildings Service to design, build, and dispose/replace electrical generators at multiple federal facilities in Alaska.

View the file

Other files for this federal contract opportunity

Other files attached to Haines / Fairbanks Generators, newest first.
File Type Posted
Solicitation Amendment 47PL0124R0032_0005.pdf PDF
Sol_SBSA_GC_April 2024 amend 05.pdf PDF
2017-12-18 Fairbanks Arc Flash Hazard Analysis Report.pdf PDF
Copy of Fairbanks Original Dist Panel Drawings.pdf PDF
Copy of Fairbanks001.PDF PDF
Generator PPI Log- Questions and Responses.xlsx XLSX spreadsheet
Copy of Fairbanks Original MCC Drawings.pdf PDF
Copy of Fairbanks002.PDF PDF
Copy of Fairbanks Original Safety Switches.pdf PDF
R10 SOW for Dispose Replace Electrical Generators REV 1 8_2_2024.docx DOCX document
Solicitation Amendment 47PL0124R0032_0004.pdf PDF
Copy of Fairbanks Original Panelboard Drawings.pdf PDF
Copy of AK0029ZZ 1979-07-10 FEDERAL BUILDING - ELECTRICAL - POWER ONE LINE AND RISER DIAGRAM.pdf PDF
Copy of 2016-11-11 FBKS HVACR - Updated Electrical As-Builts E3-2.pdf PDF
2017-10-10 Fairbanks One Line (2).pdf PDF
Sol_SBSA_GC_April 2024 amend 03.pdf PDF
Solicitation Amendment 47PL0124R0032_0003.pdf PDF
Solicitation Amendment 47PL0124R0032_0002.pdf PDF
Sol_SBSA_GC_April 2024 amend 02.pdf PDF
Sol_SBSA_GC_April 2024 amend 01.pdf PDF
FFB GEN DB SOW 2024-07-08.docx DOCX document
Solicitation Amendment 47PL0124R0032_0001.pdf PDF
Att 3_PMIS Kahua.pdf PDF
Att 7_R10 - Electrical and Telecom DC Reqs.pdf PDF
7_8 Haines LPOE Replace ATS SOW.pdf PDF
R10 SOW for Dispose Replace Electrical Generators 4_26_2024.docx DOCX document
Exhibit 1 - Key Personnel Resume Format.pdf PDF
Exhibit 2 - Project Experience Form.pdf PDF
Att 9_Exhib 5a - Fire Alarm Design-Install-Test Policy.pdf PDF
Att 2_Controlled Unclassified Information.pdf PDF
Att 10_Exhib 5b - Policy for Fire Watch-Suppression.pdf PDF
FFB GEN DB SOW 2024-04-25.docx DOCX document
Att 11_GSA FFB Project location.pdf PDF
7_4 External Users Access To Kahua .pptx PPTX presentation
7_6_ PBS 120 .pdf PDF
7_7_LPOE_Replace Day tank SOW Rv2.pdf PDF
Reps and Certs GC May 2024.pdf PDF
Agr_SBSA_GC_May 2024.pdf PDF
Att 4_CD_Waste_Mgmt_Plan_Report_Temp.xlsx XLSX spreadsheet
Att 6_P-120.pdf PDF
Att 5_R10 NCMMS Asset ImpExp Template.xlsx XLSX spreadsheet
7_2_Vendor Security Training_6_2021.pptx PPTX presentation
7_5 R10 NCMMS Asset Equipment In-Place Template .xlsx XLSX spreadsheet
Sol_SBSA_GC_April 2024.pdf PDF
Att 1_Vendor Security Training_6_2021.pptx PPTX presentation
7_3_Controlled Unclassified Information CUI 3490_3.pdf PDF
WD AK20240001 06142024.pdf PDF
Exhibit 3 Past Performance Questionnaire.docx DOCX document
Exhibit 00 - Read Me First - CUI Document.docx DOCX document
47PL0124R0032 Form.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. General Services Administration

Region 10

Public Buildings Service www.gsa.gov

Functional Requirements

PROJECT IDENTIFICATION

Project Title: Fairbanks FB Generator Replacement

Building Name: Fairbanks Federal Building

Building ID #: AK0029ZZ

Building Location: 709 W 9th ST, Fairbanks, AK 99801

A. Project Background:

1. Meetings, emails, or information:

Description Date Meeting Notes Link

Field Observation 8/8/2022 Field observation report

2. Building Background:

The Fairbanks FB was built in 1977.

3. Development Issue / Bonafide Need:

It was noted that the existing emergency distribution system does not meet NEC article 700 which applies to the installation of emergency systems that are essential for safety to human life and are legally required by state and federal. The three alternate emergency loads are emergency, legally required standby, and optional standby system. To comply with this article, three separate Automatic Transfer Switches, as well as individual distribution boards, are required. Refer to photo #7 for an illustration of the three different emergency loads and distribution systems. This is going to be expensive to fix so I do not recommend including this as part of the generator replacement project.

It was also noted that the existing electrical service and equipment is old and original to the building (1977). The equipment has been maintained regularly but have exceeded their service life. Note that the building is already rated as “High risk” in the R10 Owned Buildings Info & Systems Dashboard.

4. Documents and Resources:

One-line diagram

Drawings

Existing Arc Flash Study https://docs.google.com/document/d/1DPegaKMY2SQXpmPem_TranUSsK1OvKJPkGdV7EIu7mc/edit https://docs.google.com/spreadsheets/d/1qvGcSSR7_SbdL8lvYk5mSDk1_E0HbiB7i6eUgoF-KnM/edit#gid=1989486960 https://drive.google.com/drive/folders/18qRnJbtuBNHK1xZRzKFGCGwGhtrbLdEV https://drive.google.com/drive/folders/1yXxyQWdpUsx1SV4XlVenNjAoMmzrPrtH https://drive.google.com/drive/folders/1unMNLRcH6DGdwPZEZpiLIQecCEtTj22Q

5. Current Conditions:

● The existing 175kW diesel backup generator is in the basement dedicated emergency generator room. There is a fuel day tank located in the room which is as old as the emergency generator. The day tank is also connected to the building’s diesel fuel storage tank located outside the building. Refer to photos #1 thru 6 for existing conditions inside the electrical room.

● It was indicated that the current generator is not functioning, old and cannot obtain replacement parts. There is a rented portable generator in the front of the building that is currently serving as a temporary fix.

B. Scope of Work

1. Demolish and replace the existing 175kW, 480Y/277V (1800 RPM) diesel backup generator with similar size. New generator must be provided with a main overcurrent protective device.

2. New generators must be certified as fully EPA compliant at the manufacturing facility.

3. The generator coolant system is to be tied to the existing heat exchanger. The heat exchanger transfers heat to the cooling tower's closed loop cooling system.

4. Provide a permanently installed load bank, sized at a minimum of 50 percent of generator rating. The load bank shall be permanently installed in the fresh air adjacent intake room's east wall. The load bank must not hinder any other room components. The load bank must provide a load add/shed feature that will maintain load levels at a minimum, including building load, of the generator manufacturer's recommended loads when operating at 50 percent of generator KW nameplate. The load bank must have a minimum of four automatic load taps controlled by a load add/shed relay incorporated into the run circuit on the generator.

5. Seismically anchor/brace new generator and all equipment associated with it.

6. Utilize existing pad.

7. Demolish and replace all generator accessories (FA connections, battery connection, etc..) including the existing generator exhaust.

8. Remove the generator room day tank and replace with new properly sized day tank in the boiler mechanical room. Tank is to be large enough to support both the generator and boilers. Verify proper piping sizes and fittings to support new tank to equipment. Remove any unused fuel pipe from the main fuel piping system.

9. Install Government furnished Mobile Fuel Polishing System in the Fish and Wildlife basement storage room closest to the fuel tank. Polishing system will be programmed with an automatic fuel polishing cycle suggested by fuel polisher manufacturer.

10. Remove the continuously operating fuel recirculation motor and any unnecessary fuel lines. Verify properly installed check valves.

11. Demolish and replace the existing Automatic Transfer Switch (ATS) with N10 type (transfer of power within 10 seconds).

12. Fairly sized pull box (sized per NEC article 314) for future generator emergency feeder splicing to correct NEC article 700 deficiency (future project)

13. Generator annunciator panel (location to be determined during design/construction phase) with connection to the Fire Alarm Control Panel.

Additional remote annunciator panel(s) are optional.

14. Replace existing feeders associated with the generator replacement.

15. Connect generator and transfer panel status into the current building automation system.

16. Provide selective coordination study of the emergency system. Building system model (pdf) as well as input report (pdf only) can be provided. Contractor must confirm existing field data including but not limited to existing breaker sizes, types, conductor sizes, etc.

17. Refer to the one-line diagram in photo no.8 for additional information.

18. All work must comply with the latest versions of the P-100, NFPA and other codes that are applicable to this project.

19. Once the generator is replaced, a selective coordination study is required.

Recommend including this study as part of the replacement project. Fuses and circuit breakers have time/current characteristics that determine the time it takes to clear the fault for a given value of fault current. Selectivity occurs when the device closest to the fault opens before the next device upstream operates. Any fault on a branch circuit should open the branch-circuit breaker rather than the feeder overcurrent protection. All faults on a feeder should open the feeder overcurrent protection rather than the service overcurrent protection. With coordinated overcurrent protection, the faulted or overloaded circuit is isolated by the selective operation of only the overcurrent protective device closest to the overcurrent condition. The main goal of selective coordination is to isolate the faulted portion of the electrical circuit quickly while at the same time maintaining power to the remainder of the electrical system.

Photo no. 1: Existing Electrical room layout.

Photo no. 2: Existing 175kW generator (front view)

Photo no. 3: Existing 175kW generator (side view)

Photo no. 4: Existing 175kW generator nameplate

Photo no. 5: Existing Automatic Transfer Switch

Photo no. 6: Existing emergency distribution board

Photo no. 7: Illustration of the three different emergency loads and distribution systems

Photo no. 8: Existing Partial One-line diagram

File details come from the government source that posted it. Updated .