7_8 Haines LPOE Replace ATS SOW.pdf

PDF 836 KB Posted

Attached to
Haines / Fairbanks Generators Federal contract opportunity
Solicitation number
47PL0124R0032
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document is a Statement of Work (SOW) for the replacement of a 400A electrical automatic transfer switch (ATS) at the Haines Land Port of Entry (LPOE) building in Alaska. The existing ATS has failed, creating a risk of building freeze-up during power outages when the backup generator does not automatically start.

The SOW requires the contractor to remove and replace the non-functional ATS with a new 400A ATS that meets specified requirements, including automatic open transition, 208V 3-phase, 125A seismic rating, and various control features. The work must be coordinated with the on-site operations and maintenance staff and tenant, and completed before the onset of harsh winter conditions. The contractor is responsible for obtaining permits, maintaining utilities, protecting the public, and properly disposing of all waste. Submittals include equipment specifications, drawings, and test reports.

This SOW is related to a federal contract opportunity for design-build services to replace electrical generators at the Dalton Cache LPOE in Haines and the Fairbanks Federal Building in Fairbanks, Alaska. The solicitation also includes two optional projects for the Skagway LPOE and Alcan LPOE.

View the file

Other files for this federal contract opportunity

Other files attached to Haines / Fairbanks Generators, newest first.
File Type Posted
Solicitation Amendment 47PL0124R0032_0005.pdf PDF
Sol_SBSA_GC_April 2024 amend 05.pdf PDF
Copy of Fairbanks Original MCC Drawings.pdf PDF
Copy of Fairbanks002.PDF PDF
Copy of Fairbanks Original Safety Switches.pdf PDF
R10 SOW for Dispose Replace Electrical Generators REV 1 8_2_2024.docx DOCX document
Solicitation Amendment 47PL0124R0032_0004.pdf PDF
Copy of Fairbanks Original Dist Panel Drawings.pdf PDF
Copy of Fairbanks001.PDF PDF
Generator PPI Log- Questions and Responses.xlsx XLSX spreadsheet
Copy of Fairbanks Original Panelboard Drawings.pdf PDF
Copy of AK0029ZZ 1979-07-10 FEDERAL BUILDING - ELECTRICAL - POWER ONE LINE AND RISER DIAGRAM.pdf PDF
Copy of 2016-11-11 FBKS HVACR - Updated Electrical As-Builts E3-2.pdf PDF
2017-10-10 Fairbanks One Line (2).pdf PDF
2017-12-18 Fairbanks Arc Flash Hazard Analysis Report.pdf PDF
Solicitation Amendment 47PL0124R0032_0003.pdf PDF
Sol_SBSA_GC_April 2024 amend 03.pdf PDF
Sol_SBSA_GC_April 2024 amend 02.pdf PDF
Solicitation Amendment 47PL0124R0032_0002.pdf PDF
Solicitation Amendment 47PL0124R0032_0001.pdf PDF
Sol_SBSA_GC_April 2024 amend 01.pdf PDF
FFB GEN DB SOW 2024-07-08.docx DOCX document
Att 4_CD_Waste_Mgmt_Plan_Report_Temp.xlsx XLSX spreadsheet
Att 6_P-120.pdf PDF
Att 5_R10 NCMMS Asset ImpExp Template.xlsx XLSX spreadsheet
7_2_Vendor Security Training_6_2021.pptx PPTX presentation
7_5 R10 NCMMS Asset Equipment In-Place Template .xlsx XLSX spreadsheet
Sol_SBSA_GC_April 2024.pdf PDF
Att 9_Exhib 5a - Fire Alarm Design-Install-Test Policy.pdf PDF
Att 2_Controlled Unclassified Information.pdf PDF
Att 10_Exhib 5b - Policy for Fire Watch-Suppression.pdf PDF
FFB GEN DB SOW 2024-04-25.docx DOCX document
Att 11_GSA FFB Project location.pdf PDF
7_4 External Users Access To Kahua .pptx PPTX presentation
7_6_ PBS 120 .pdf PDF
7_7_LPOE_Replace Day tank SOW Rv2.pdf PDF
Reps and Certs GC May 2024.pdf PDF
Agr_SBSA_GC_May 2024.pdf PDF
Att 1_Vendor Security Training_6_2021.pptx PPTX presentation
Att 8_GSA Func requirements.pdf PDF
7_3_Controlled Unclassified Information CUI 3490_3.pdf PDF
WD AK20240001 06142024.pdf PDF
Exhibit 3 Past Performance Questionnaire.docx DOCX document
Exhibit 00 - Read Me First - CUI Document.docx DOCX document
47PL0124R0032 Form.pdf PDF
Att 3_PMIS Kahua.pdf PDF
Att 7_R10 - Electrical and Telecom DC Reqs.pdf PDF
R10 SOW for Dispose Replace Electrical Generators 4_26_2024.docx DOCX document
Exhibit 1 - Key Personnel Resume Format.pdf PDF
Exhibit 2 - Project Experience Form.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL SERVICE ADMINISTRATION Region 10

Haines Dalton Cache LPOE: Replace Automatic Transfer Switch (ATS)

U.S. GENERAL SERVICES ADMINISTRATION, NORTHWEST/ARCTIC REGION 10

Section 1:

Project Location & Building Number

Section 2:

Background

Section 3:

Work Hours

Section 4:

Parking/ Loading Dock

Section 5:

General Information

Haines Dalton Cache Land Port of Entry Mile 40 Haines, AK 99827

AK0521AB

The United States General Services Administration requires the replacement of 400A electrical automatic transfer switchgear (ATS) at Haines LPOE building. The existing transfer switchgear has failed and will not automatically switch between utility power and backup generator power. This creates a condition for our building in the winter, that without manual intervention, should the power go out at the building, emergency power is not started or transferred to the backup generator, risking the building of freeze-up during the winter, and interrupting the tenant’s mission at the site. There is only one O&M staff member at the site, and it is impossible for them to be at the building 24/7 through the winter. The intent of the emergency work is to be accomplished before the hard days of winter set in at the site.

This project shall be accomplished during or after normal working hours of 7:00 AM to 5:00 PM weekdays, except Federal holidays. Contractor shall schedule the work in writing at least 5 business days in advance with the GSA Project Manager (PM).

Contractor parking is very limited and available on first-come-first-serve basis only.

Access to the parking lots/loading dock requires written coordination with the GSA Project Manager at least 5 business days in advance.

1. All work shall comply with the latest versions of GSA’s PBS-P100, Facility Standards for the Public Buildings Service http://www.gsa.gov/portal/content/104821, and GSA Region 10 Fire Alarm Design, Installation and Testing Policy

2. Specific attention should be given to PBS P-100 Chapter One requirements including Laws, Regulations, Codes and Standards, and Key Sustainable Product requirements for carpet, interior paint, gyp board, ceiling tiles, and concrete.

3. Contractor shall provide all supplies, equipment, materials, services, and labor to perform the work.

4. Contractor shall be responsible for obtaining all necessary local, state, and federal permits, licenses, and clearances.

5. Field Verification: All work dimensions, quantities, and locations shall be field verified by the contractor.

6. Contractor Use of Premises: The Contractor shall coordinate with the GSA PM to arrange a schedule for site access during construction. Construction processes disruptive to normal facility operations shall be coordinated with the GSA PM in writing at least 5 business days in advance. The Contractor shall be authorized to use building restrooms.

7. Utilities: Contractor shall be authorized to use utilities during the course of this project. The contractor is responsible for making connections to the existing utility systems. Temporary electrical work shall meet the requirements of NFPA 70.

When temporary connections are removed, the Contractor is responsible for restoring existing utility services to their original condition.

8. Utility Outages and Locates: No utility outages will be approved without the written consent and approval of the GSA PM. Requests for utility outages shall be coordinated in writing at least 5 business days in advance with the GSA PM.

9. Protection of Public: The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

10. Housekeeping: The project site shall be kept in a neat, orderly, and safe condition at all times and all work areas shall be cleaned at the end of each work day. A final cleaning of the entire construction area will be required at substantial completion of the project. Final Cleaning to include (1) Removal of all tools, equipment, surplus material, and rubbish/debris; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Removal of grease, dirt, stains, foreign materials, and labels from finished surfaces; and (4) thoroughly clean building interiors.

11. Disposal: Ensure all waste materials and debris is disposed at an Alaska

Department of Environmental Conservation (DEC) approved disposal site, in accordance with applicable environmental regulations. Unless otherwise specified, all material(s) removed becomes the property of the Contractor.

12. Painting/Staining: If necessary, all painting, staining, or other activity which may cause noxious or undesirable fumes must be performed outside of the normal working hours of 8AM-5PM. Painting/Staining shall be coordinated in writing with the GSA Project Manager at least 5 business days in advance. The Contractor is responsible for using “low or no VOC” paints and stains.

13. Communications: Contractor project designee must be available to provide project status updates to GSA each workday.

Section 6:

Description

Section 7:

Submittals

As indicated, execute the project as follows:

1. The Contractor is responsible for maintaining electricity to the building during the demolition and installation of the new automatic transfer switch (ATS). It is estimated that the work will require 2 electricians for 5 days to accomplish this task.

Contractor shall stage work to minimize interruption to power as much as possible to accomplish this task. Contractor shall coordinate with on-site O&M staff, COR, and tenant occupant for all power interruptions.

2. The Contractor shall remove and replace the existing non-functional ATS with a similar code compliant 400A ATS.

3. The ATS shall have, but not limited to, the following minimum features.

a. Automatic Open Transition Transfer Switch

b. 208V, 3-phase, 400 Amp capacity, 3-Pole

c. Controller with

i. RS-485 MODBUS controller

ii. Multi-schedule Engine Exerciser

iii. A 300 Entry Event Log

iv. A common alarm output function when applied on 3-phase systems it also enables the following:

1. 3-Phase emergency source VLL sensing

2. Phase Rotation Monitoring

3. Emergency Source VLL unbalance monitoring

d. 125A Seismic rating

e. Type 1 Enclosure

4. As much as possible use existing conduit raceway and conductors.

5. The Contractor must label all new equipment and update labeling on any impacted electrical panels. Labels must include equipment name & upstream source/equipment name, voltage, amperage, short circuit current ratings, etc.

6. All work must comply with all applicable codes to include but not limited to NFPA 110, NEC 408, GSA PBS100, etc.

7. The Contractor shall perform a functional test of all repaired/replaced items and ensure normal operation under normal and emergency power.

8. The Contractor is responsible for proper disposal of all construction waste.

The following submittals shall be provided with this project.

Contractor proposed new equipment spec sheets and drawings.

Contractor to provide all testing reports to COR upon completion.

END OF SCOPE