7_8 Haines LPOE Replace ATS SOW.pdf
PDF 836 KB Posted
- Attached to
- Haines / Fairbanks Generators Federal contract opportunity
- Solicitation number
- 47PL0124R0032
About this file
This document is a Statement of Work (SOW) for the replacement of a 400A electrical automatic transfer switch (ATS) at the Haines Land Port of Entry (LPOE) building in Alaska. The existing ATS has failed, creating a risk of building freeze-up during power outages when the backup generator does not automatically start.
The SOW requires the contractor to remove and replace the non-functional ATS with a new 400A ATS that meets specified requirements, including automatic open transition, 208V 3-phase, 125A seismic rating, and various control features. The work must be coordinated with the on-site operations and maintenance staff and tenant, and completed before the onset of harsh winter conditions. The contractor is responsible for obtaining permits, maintaining utilities, protecting the public, and properly disposing of all waste. Submittals include equipment specifications, drawings, and test reports.
This SOW is related to a federal contract opportunity for design-build services to replace electrical generators at the Dalton Cache LPOE in Haines and the Fairbanks Federal Building in Fairbanks, Alaska. The solicitation also includes two optional projects for the Skagway LPOE and Alcan LPOE.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL SERVICE ADMINISTRATION Region 10
Haines Dalton Cache LPOE: Replace Automatic Transfer Switch (ATS)
U.S. GENERAL SERVICES ADMINISTRATION, NORTHWEST/ARCTIC REGION 10
Section 1:
Project Location & Building Number
Section 2:
Background
Section 3:
Work Hours
Section 4:
Parking/ Loading Dock
Section 5:
General Information
Haines Dalton Cache Land Port of Entry Mile 40 Haines, AK 99827
AK0521AB
The United States General Services Administration requires the replacement of 400A electrical automatic transfer switchgear (ATS) at Haines LPOE building. The existing transfer switchgear has failed and will not automatically switch between utility power and backup generator power. This creates a condition for our building in the winter, that without manual intervention, should the power go out at the building, emergency power is not started or transferred to the backup generator, risking the building of freeze-up during the winter, and interrupting the tenant’s mission at the site. There is only one O&M staff member at the site, and it is impossible for them to be at the building 24/7 through the winter. The intent of the emergency work is to be accomplished before the hard days of winter set in at the site.
This project shall be accomplished during or after normal working hours of 7:00 AM to 5:00 PM weekdays, except Federal holidays. Contractor shall schedule the work in writing at least 5 business days in advance with the GSA Project Manager (PM).
Contractor parking is very limited and available on first-come-first-serve basis only.
Access to the parking lots/loading dock requires written coordination with the GSA Project Manager at least 5 business days in advance.
1. All work shall comply with the latest versions of GSA’s PBS-P100, Facility Standards for the Public Buildings Service http://www.gsa.gov/portal/content/104821, and GSA Region 10 Fire Alarm Design, Installation and Testing Policy
2. Specific attention should be given to PBS P-100 Chapter One requirements including Laws, Regulations, Codes and Standards, and Key Sustainable Product requirements for carpet, interior paint, gyp board, ceiling tiles, and concrete.
3. Contractor shall provide all supplies, equipment, materials, services, and labor to perform the work.
4. Contractor shall be responsible for obtaining all necessary local, state, and federal permits, licenses, and clearances.
5. Field Verification: All work dimensions, quantities, and locations shall be field verified by the contractor.
6. Contractor Use of Premises: The Contractor shall coordinate with the GSA PM to arrange a schedule for site access during construction. Construction processes disruptive to normal facility operations shall be coordinated with the GSA PM in writing at least 5 business days in advance. The Contractor shall be authorized to use building restrooms.
7. Utilities: Contractor shall be authorized to use utilities during the course of this project. The contractor is responsible for making connections to the existing utility systems. Temporary electrical work shall meet the requirements of NFPA 70.
When temporary connections are removed, the Contractor is responsible for restoring existing utility services to their original condition.
8. Utility Outages and Locates: No utility outages will be approved without the written consent and approval of the GSA PM. Requests for utility outages shall be coordinated in writing at least 5 business days in advance with the GSA PM.
9. Protection of Public: The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
10. Housekeeping: The project site shall be kept in a neat, orderly, and safe condition at all times and all work areas shall be cleaned at the end of each work day. A final cleaning of the entire construction area will be required at substantial completion of the project. Final Cleaning to include (1) Removal of all tools, equipment, surplus material, and rubbish/debris; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Removal of grease, dirt, stains, foreign materials, and labels from finished surfaces; and (4) thoroughly clean building interiors.
11. Disposal: Ensure all waste materials and debris is disposed at an Alaska
Department of Environmental Conservation (DEC) approved disposal site, in accordance with applicable environmental regulations. Unless otherwise specified, all material(s) removed becomes the property of the Contractor.
12. Painting/Staining: If necessary, all painting, staining, or other activity which may cause noxious or undesirable fumes must be performed outside of the normal working hours of 8AM-5PM. Painting/Staining shall be coordinated in writing with the GSA Project Manager at least 5 business days in advance. The Contractor is responsible for using “low or no VOC” paints and stains.
13. Communications: Contractor project designee must be available to provide project status updates to GSA each workday.
Section 6:
Description
Section 7:
Submittals
As indicated, execute the project as follows:
1. The Contractor is responsible for maintaining electricity to the building during the demolition and installation of the new automatic transfer switch (ATS). It is estimated that the work will require 2 electricians for 5 days to accomplish this task.
Contractor shall stage work to minimize interruption to power as much as possible to accomplish this task. Contractor shall coordinate with on-site O&M staff, COR, and tenant occupant for all power interruptions.
2. The Contractor shall remove and replace the existing non-functional ATS with a similar code compliant 400A ATS.
3. The ATS shall have, but not limited to, the following minimum features.
a. Automatic Open Transition Transfer Switch
b. 208V, 3-phase, 400 Amp capacity, 3-Pole
c. Controller with
i. RS-485 MODBUS controller
ii. Multi-schedule Engine Exerciser
iii. A 300 Entry Event Log
iv. A common alarm output function when applied on 3-phase systems it also enables the following:
1. 3-Phase emergency source VLL sensing
2. Phase Rotation Monitoring
3. Emergency Source VLL unbalance monitoring
d. 125A Seismic rating
e. Type 1 Enclosure
4. As much as possible use existing conduit raceway and conductors.
5. The Contractor must label all new equipment and update labeling on any impacted electrical panels. Labels must include equipment name & upstream source/equipment name, voltage, amperage, short circuit current ratings, etc.
6. All work must comply with all applicable codes to include but not limited to NFPA 110, NEC 408, GSA PBS100, etc.
7. The Contractor shall perform a functional test of all repaired/replaced items and ensure normal operation under normal and emergency power.
8. The Contractor is responsible for proper disposal of all construction waste.
The following submittals shall be provided with this project.
Contractor proposed new equipment spec sheets and drawings.
Contractor to provide all testing reports to COR upon completion.
END OF SCOPE