This document is a Statement of Work (SOW) for the Project Management Information System (PMIS) required for use on a GSA Region 10 construction project. The SOW specifies that the contractor must use GSA's web-based PMIS, currently the Kahua Project Management Software, to manage all project-related documentation, collaboration, and workflow. The contractor must attend mandatory training, maintain adequate staffing, and continuously monitor and update the PMIS throughout the project lifecycle. The PMIS will serve as the electronic filing cabinet for all submittals, correspondence, and project data. Personnel without an HSPD-12 security clearance will have limited PMIS access initially. GSA retains ownership of all data entered into the system and will provide PMIS administration and user support.

The related federal contract opportunity is for a Design-Build project to replace electrical generators at the Dalton Cache Land Port of Entry in Haines, Alaska and the Fairbanks Federal Building in Fairbanks, Alaska. The solicitation also includes options for design-build projects at the Skagway Land Port of Entry and the Alcan Land Port of Entry. The contracting agency is the General Services Administration (GSA) Public Buildings Service Region 10.

View the file

Other files for this federal contract opportunity

Other files attached to Haines / Fairbanks Generators, newest first.
File Type Posted
Sol_SBSA_GC_April 2024 amend 05.pdf PDF
Solicitation Amendment 47PL0124R0032_0005.pdf PDF
Copy of Fairbanks Original MCC Drawings.pdf PDF
Copy of Fairbanks002.PDF PDF
Copy of Fairbanks Original Safety Switches.pdf PDF
R10 SOW for Dispose Replace Electrical Generators REV 1 8_2_2024.docx DOCX document
Solicitation Amendment 47PL0124R0032_0004.pdf PDF
Copy of Fairbanks Original Panelboard Drawings.pdf PDF
Copy of AK0029ZZ 1979-07-10 FEDERAL BUILDING - ELECTRICAL - POWER ONE LINE AND RISER DIAGRAM.pdf PDF
Copy of 2016-11-11 FBKS HVACR - Updated Electrical As-Builts E3-2.pdf PDF
2017-10-10 Fairbanks One Line (2).pdf PDF
Copy of Fairbanks Original Dist Panel Drawings.pdf PDF
Copy of Fairbanks001.PDF PDF
Generator PPI Log- Questions and Responses.xlsx XLSX spreadsheet
2017-12-18 Fairbanks Arc Flash Hazard Analysis Report.pdf PDF
Solicitation Amendment 47PL0124R0032_0003.pdf PDF
Sol_SBSA_GC_April 2024 amend 03.pdf PDF
Sol_SBSA_GC_April 2024 amend 02.pdf PDF
Solicitation Amendment 47PL0124R0032_0002.pdf PDF
Solicitation Amendment 47PL0124R0032_0001.pdf PDF
Sol_SBSA_GC_April 2024 amend 01.pdf PDF
FFB GEN DB SOW 2024-07-08.docx DOCX document
Att 4_CD_Waste_Mgmt_Plan_Report_Temp.xlsx XLSX spreadsheet
Att 6_P-120.pdf PDF
Att 5_R10 NCMMS Asset ImpExp Template.xlsx XLSX spreadsheet
7_2_Vendor Security Training_6_2021.pptx PPTX presentation
7_5 R10 NCMMS Asset Equipment In-Place Template .xlsx XLSX spreadsheet
Sol_SBSA_GC_April 2024.pdf PDF
Att 1_Vendor Security Training_6_2021.pptx PPTX presentation
Att 8_GSA Func requirements.pdf PDF
7_3_Controlled Unclassified Information CUI 3490_3.pdf PDF
WD AK20240001 06142024.pdf PDF
Exhibit 3 Past Performance Questionnaire.docx DOCX document
Exhibit 00 - Read Me First - CUI Document.docx DOCX document
47PL0124R0032 Form.pdf PDF
Att 9_Exhib 5a - Fire Alarm Design-Install-Test Policy.pdf PDF
Att 2_Controlled Unclassified Information.pdf PDF
Att 10_Exhib 5b - Policy for Fire Watch-Suppression.pdf PDF
FFB GEN DB SOW 2024-04-25.docx DOCX document
Att 11_GSA FFB Project location.pdf PDF
7_4 External Users Access To Kahua .pptx PPTX presentation
7_6_ PBS 120 .pdf PDF
7_7_LPOE_Replace Day tank SOW Rv2.pdf PDF
Reps and Certs GC May 2024.pdf PDF
Agr_SBSA_GC_May 2024.pdf PDF
Att 7_R10 - Electrical and Telecom DC Reqs.pdf PDF
7_8 Haines LPOE Replace ATS SOW.pdf PDF
R10 SOW for Dispose Replace Electrical Generators 4_26_2024.docx DOCX document
Exhibit 1 - Key Personnel Resume Format.pdf PDF
Exhibit 2 - Project Experience Form.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R10 Statement of Work (SOW) - Project Management Information System (PMIS)

Updated April 2022 GSA R10 Project Management Information System - 1

1.1 PURPOSE

A. Project Management Information System (PMIS)

The Contractor is required to use GSA’s web-based electronic Project Management

Information System (PMIS). PMIS is a web-based project management tool which provides GSA with an automated workflow, collaboration, document management and project management solution to assist GSA in the management of design and construction projects.

GSA uses PMIS throughout the design and construction phases as a repository for all project information and as a tool to manage and monitor progress and modifications.

Unless as otherwise provided, the Contractor will rely exclusively on PMIS to post, review, access, comment on, collaborate, or otherwise submit all project information.

The current PMIS system in use by GSA is Kahua Project Management Software.

1.2 PROJECT COLLABORATION AND DOCUMENTATION

A. General

1. The Contractor is required to effectively manage the GSA Project Management

Information System including maintaining adequate staffing levels and ensuring that personnel attend the mandatory GSA-provided training sessions.

2. The Contractor is required to use the GSA Project Management Information

System to upload, store, capture, preserve, record, maintain, update, and route all project-related documentation to comply with GSA's Document Security

Requirements. Classified material is not permitted to be stored in this system.

Properly marked Controlled Unclassified (CUI) material is permitted to be stored in this system.

3. The Contractor is required to use the workflow processes contained within the

GSA Project Management Information System to submit and receive approval for all project deliverables.

Updated April 2022 GSA R10 Project Management Information System - 2

4. The Contractor is required to continuously monitor and review the GSA Project

Management Information System to ensure the Contractor data is current through completion of the Close-out Phase of Construction.

5. The Contractor is required to store documents from their subcontractors and vendors in the GSA Project Management Information System.

B. Contents of the GSA Project Management Information System

1. Refer to the Statement of Work for all required submittals

2. The Contractor is required to use the GSA Project Management Information

System as the electronic filing cabinet for all project-related documentation, correspondence and submittals.

1.3 SCHEDULING REQUIREMENTS

1.3.1 The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule.

Contractor provided schedules should be uploaded or imported to the GSA Project

Management Information System on a recurring basis.

1.4 EQUIPMENT AND TRAINING

A. Equipment

1. GSA will not furnish any equipment related to accessing the GSA Project

Management Information System. The GSA Project Management Information

System is web-accessible, and can therefore be accessed via any computer with an Internet connection.

B. GSA Project Management Information System Training

1. GSA will provide no cost training to familiarize team members with the GSA

Project Management Information System. The GSA Project Manager will ensure that appropriate personnel should attend training and what roles will be set up within the system based on their project responsibilities.

C. GSA Project Management Information System Support

Updated April 2022 GSA R10 Project Management Information System - 3

1. GSA will provide GSA Project Management Information System administration and end user support, for the duration of the project.

1.5 PERSONNEL REQUIREMENTS

An HSPD-12 (Homeland Security Presidential Directive 12) security clearance is required for full access to the PMIS.

Project team members without an HSPD-12 clearance will be given limited access to the

PMIS system at contract award to allow initial document submissions while clearances are in process.

1.6 DATA OWNERSHIP

A. GSA will retain ownership of all data entered into the system and will administer all information contained therein. Distribution of any system data will be made upon request.

1.7 DOCUMENT SECURITY

A. GSA Project Management Information System security access levels ensure that sensitive documents can only be accessed by the appropriate personnel. It is the contractor’s responsibility to ensure their employees, subcontractors and vendors have the appropriate level of security to ensure document security.