This is a Standard Form 1442 Solicitation, Offer and Award document for construction services to rehabilitate operational buildings at Craters of the Moon National Monument and Preserve in Arco, ID. The solicitation (140P2025R0013) is being issued by the National Park Service DSC Contracting Services Division as a competitive total small business set-aside negotiated procurement under FAR Parts 15 and 36.

The project has an estimated construction magnitude between $1-5 million. Performance period is 550 calendar days after notice to proceed, with work to begin within 10 days of award. Proposals are due March 7, 2025 at 1200 local time. Performance and payment bonds are required within 10 calendar days of award. The government notes that funds are not currently available but there is high expectation of funding. Proposed substitutions for specified manufacturer items will be evaluated during the submittal process after award. A pre-proposal site visit will be conducted, with details provided in Section L.

View the file

Other files

File Type Posted
Sol_140P2025R0013_Amd_0005.pdf PDF
B09_Amd_4_CRMO323904_2-E101_0004.pdf PDF
B09__P2025R0013_Amd_4_CRMO_323904Clause_Updates_0004.pdf PDF
B09_Amd_4_Thermacore-door-systems-brochure_0004.pdf PDF
Sol_140P2025R0013_Amd_0004.pdf PDF
B09_Amd_4_EMON-DMON_Class5000-datasheet_0004.pdf PDF
B09_Amd_4_CRMO_323904_QA_4_1_25_Final_Questions_0004.pdf PDF
Sol_140P2025R0013_Amd_0003.pdf PDF
B09_Amd_2_CRMO_323904_QA_3_12_25_0002.xlsx XLSX spreadsheet
CRMO323904_232300-R1_Refrigerant_Piping_0002.pdf PDF
B09_Amd_2_02_CRMO_ACM_TCLP_Analysis_August_2022_0002.pdf PDF
CRMO323904_0-M001-R1_0002.pdf PDF
Sol_140P2025R0013_Amd_0002.pdf PDF
B09_Amd_2_SiteVisit_Registration2_25_0002.pdf PDF
B09_Amd_2_03_CRMO_Masonry_and_Paint_Analysis_December_2023_0002.pdf PDF
CRMO_323904_0-G000_R1_0001.pdf PDF
238126_-_Split-System_Air-Conditioners_0001.pdf PDF
CRMO_323904_ASI1_Refrigerant_Update_Cover_Sheet_0001.pdf PDF
Sol_140P2025R0013_Amd_0001.pdf PDF
B08_Atch_3_ButteCountyWD_1_3_2025.pdf PDF
B08_Atch_4_Solit_Vol1_PastPerfQ_-_CRMO.docx DOCX document
B08_Atch_7_Brand_Name_J_A_FAR_6_302_-_CRMO.pdf PDF
B08_Atch_1_Specifications_CRMO_323904_Final_UPDATED.pdf PDF
B08_Atch_6_Solit_Vol2__SubLimitations_-_CRMO.xlsx XLSX spreadsheet
B08_Atch_2_Drawings_CRMO_323904_Final_UPDATED.pdf PDF
B08_RFP_140P2025R0013_-_CRMO_323904_Feb2025Rev.pdf PDF
B08_Atch_5_Solit_Vol2_ContractPriceSchedule_-_CRMO.xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

NPS, DSC Contracting Services Div

12795 W. Alameda Pkwy

P.O. Box 25287 Denver CO 80225-0287

PDS

Refer to Section L

Amber Hughes 0000000000

CRMO 323904

x 02/07/2025

140P2025R0013

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

CRMO 323904 - "Rehabilitate Operational Buildings at Idaho Parks," at

Craters of the Moon National Monument and Preserve in Arco, ID.

This acquisition is being conducted in accordance with FAR Parts 15 and 36, in conjunction with FAR 6.203 and 19.502-2, as a Competitive Total Small Business

Set-Aside to be Negotiated for this Construction Services project.

The magnitude of construction is between $1,000,000.00 and $5,000,000.00.

The NAICS Code and associated Small Business Size Standard are noted within Section

K under FAR Provision 52.204-8 - "Annual Representations and Certifications."

Refer to Section L for information regarding a Pre-Proposal Site Visit as well as requirements for Proposal Submittals and Submissions, Questions, and Solicitation

Amendment Acknowledgements.

The information and requirements stated in Sections B thru J, to include all noted

Attachments, apply to this Solicitation and subsequent Contract.

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 550 calendar days and complete it within ________________ ________________ calendar days after receiving

Clause 52.211-10

03/07/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

NPS, DSC Contracting Services Div 12795 W. Alameda Pkwy

P.O. Box 25287 Denver CO 80225-0287

PDS

Paula Teague

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 76

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140P2025R0013

Offerors are advised that items within the

Drawings and Specifications for this project requirement, that identify a manufacturer, make and model, with reference to 'or equal (EQ)' are design items to be addressed under FAR Clause

52.236-5 - "Materials and Workmanship," in which proposed substitutions shall be evaluated during the submittal process, post-award.

Notice to Offerors: Funds are not presently available for this effort; however, there is a high expectation that funds will become available to make an award resulting from this

Solicitation. No award will be made under this

Solicitation until funds are available. The

Government reserves the right to cancel this

Solicitation, either before or after the closing date. In the event the Government cancels this

Solicitation, the Government has no obligation to reimburse an Offeror for any costs.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .