Proposed ISS Contract Timeline
| Go/No-Go Form Due |
| July 10, 2015 |
| Go/No-Go Decision |
| July 17, 2015 |
| RFP Questions Due |
| July 24, 2015 |
| SEC Responses to Questions |
| August 7, 2015 |
| Proposals Due |
| August 28, 2015 |
| SEC Proposal Review and Preparation |
| August 28 – September 4, 2015 |
| Oral Presentations |
| September 8 – September 18, 2015 |
| Competitive Range |
| September 21 – September 25, 2015 |
| Oral Discussion (if required) |
| October 5 – October 9, 2015 |
| Final Selection |
| October 12 – October 23, 2015 |
| Selected Offeror Final Proposal/Negotiations |
| October 23 – November 6, 2015 |
| Contract Award |
| November 13, 2015 |
Page 3 of 93 SECHQ1-15-R0015