13R0393_Awd_Term_Plan_12_05_2013.docx
DOCX document 51 KB Posted
- Attached to
- INL/A GLOBAL AVIATION INFORMATION TECHNOLOGY SERVICES Federal contract opportunity
- Solicitation number
- SAQMMA13R0393
About this file
Award Term Plan
View the file
Other files for this federal contract opportunity
Show all 42
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation SAQMMA13R0393 Attachment J.2
AWARD TERM PLAN
FOR
US DEPARTMENT OF STATE
BUREAU FOR INTERNATIONAL NARCOTICS
AND LAW ENFORCEMENT AFFAIRS (INL)
AVIATION SUPPORT SERVICES
INFORMATION TECHNOLOGY
(Approval date)
REVIEWED: APPROVED:
| ________________________ | ______________________ | |
| Contracting Officer | Term Determining Official | |
| Reaver Clements | Ralph Frank |
Contents
| 1.0 Introduction | 3 |
| 2.0 Organization | 3 |
| 3.0 Responsibilities | 3 |
| 4.0 Award Term Process | 4 |
| 5. 0 Award Term Incentive | 5 |
| 6.0 Award Term Determination | 6 |
| 7.0 Award Term Plan Change Procedure | 6 |
| 8. 0 Award Term Extensions | 7 |
| 9.0 Award Term Periods and Available Points | 7 |
| 10.0 Evaluation Criteria | 8 |
| 11.0 Sample Award Point Conversion | 11 |
1.0 Introduction
This award term plan is the basis for INL Office of Aviation’s evaluation of the contractor’s performance and for presenting an evaluation of that performance to the Term Determining Official (TDO). The adjustment to the performance period will result in a contract of at least three (3) years but not greater than ten (10) years.
All TDO decisions regarding the award term points shall not be subject to the provisions of FAR 52.233-1, disputes, or reviewed by any Board of Contract appeal (BCA), court, or other judicial entity. This includes but is not limited to; the amount of the award term points, the methodology used to calculate the award term points, the final calculation of the award term points.
The award term will be provided to the contractor through a unilateral contract modification based upon points earned as determined by the TDO.
2.0 Organization
The award term organization consists of the TDO and an Award Term Review Board (ATRB). The ATRB consists of a chairperson, the Contracting Officer (CO), a recorder, functional area experts, advisors, and the performance monitors. The ATRB will have no less than three (3) voting members.
3.0 Responsibilities
a. Term Determining Official. The TDO approves the award term plan and any significant changes. The TDO also reviews the recommendations of the ATRB, considers all pertinent data, determines the performance rating for each evaluation period, and determines if an award term option is approved. The award term determination will be made by the TDO based upon the criteria outlined in paragraph 10.0 Evaluation Criteria. The TDO also appoints the ATRB Chairperson.
b. Contracting Officer. The CO is the liaison between the Contractor and the Government Personnel. Subsequent to TDO approval, the CO modifies the contract period of performance to reflect the decision as appropriate.
c. Award Term Review Board Chairperson. The ATRB Chairperson chairs board meetings, and appoints the remaining ATRB members. The ATRB Chairperson briefs the TDO on recommended performance ratings and recommends award term plan changes to the TDO. The Chairperson also coordinates the administrative actions during the award term process includes: 1) receipt, processing and distribution of evaluation reports from all required sources, 2) scheduling board meetings and briefings, and 3) accomplishing other actions required to ensure the smooth operation of the award term process.
d. Award Term Review Board Members. ATRB members review performance monitor evaluations, consider all information from pertinent sources, prepare interim performance evaluations every four (4) months, and will recommend an overall performance evaluation rating to the TDO on an annual basis. The ATRB will also evaluate and recommend changes to the award term plan.
e. Performance Monitors. Government Technical Monitors (GTMs) maintain written records of the contractor’s performance in their assigned evaluation area(s) to ensure that a fair and accurate evaluation is obtained. GTMs utilize the Quality Assurance Survallence Plan (QASP), internal and external audits, and verified customer service reports. Monitors prepare interim and end-of-period evaluation reports as directed by the ATRB.
f. Award Term Review Board Recorder. The ATRB recorder assists the Chairperson in his administrative duties which include internal evaluation milestones, scheduling of meetings and briefings and processing reports. The recorder is a non-voting member.
4.0 Award Term Process
a. Performance Evaluations. The contractor is expected to meet all requirements of the contract from the first date of performance; however, only the ratings received for each evaluation period will be considered in the award term determinations under this contract.
b. Interim Evaluation Process. Interim evaluations will occur on a trimester basis. The ATRB Chairperson will notify the ATRB members fifteen (15) calendar days before each interim evaluation period ends. ATRB members will complete the interim evaluation reports within fifteen (15) calendar days after the interim period ends. The ATRB will determine the preliminary interim evaluation results. The ATRB Chairperson will then brief the Contractor on the interim results to include strengths, weaknesses, and the preliminary estimation of the Contractor’s interim rating.
The ATRB will review any Contractor self-evaluations, the Contractor’s performance, and consider information from any pertinent sources in determining an overall rating recommendation which will then be presented to the TDO. The ATRB will prepare and submit a formal interim evaluation report to the TDO within thirty (30) calendar days after the end of each interim evaluation period. The report will include a recommendation as to the overall rating and include a narrative of each element evaluated that supports the recommended rating assigned. If the ATRB is unable to reach a unanimous agreement on the content of a report, the Chairperson shall forward minority reports prepared by the dissenting ATRB member(s).
c. End-of-Period Evaluations. A final evaluation will occur at the end of each evaluation period. The ATRB Chairperson will notify the ATRB members fifteen (15) calendar days before the final evaluation period is complete. ATRB members will complete their final evaluation reports within fifteen (15) calendar days after the evaluation period ends.
The ATRB will review any Contractor self-evaluations, the final interim evaluation reports approved by the TDO, the Contractor’s performance, and consider information from any applicable sources in determining an overall rating recommendation to be presented to the TDO. The ATRB will prepare and submit a final evaluation report to the TDO within thirty (30) calendar days after the end of each evaluation period. The report will include a recommendation as to the overall rating and include a narrative of each element evaluated that supports the recommended rating assigned. If the ATRB is unable to reach unanimous agreement on the content of a report, the ATRB Chairperson shall forward minority reports prepared by the dissenting ATRB member(s).
d. Contractor’s Self-Evaluation. At their discretion, the Contractor may submit to the CO within ten (10) calendar days after the end of each interim and final evaluation period, a brief written self-evaluation of its performance for that period. This self-evaluation shall not exceed five (5) pages. This self-evaluation will be considered in the ATRB’s evaluation of the Contractor’s performance during this period.
e. TDO Evaluation. The TDO is required to make a final evaluation of the interim and final evaluation rating within fifteen (15) days upon receipt of the ATRB evaluation report. Accordingly, the TDO has the flexibility to change the recommended rating as a result of any relevant factor to include, but not limited to the following:
(1) the rating assigned to an individual function due to extraordinary input from the activity or other sources;
(2) the overall rating based on trends in performance in all functions or any general economic or business trends which may affect performance capability; or
(3) any other information the TDO determines is applicable to the Contractor’s performance evaluation.
Any changes to the ratings recommended by the ATRB must be documented and the documentation shall include the rationale for the change.
f. Duration of Evaluation. The estimated time for the completion of the government’s evaluation is approximately forty-five (45) days after the conclusion of the evaluation period.
5. 0 Award Term Incentive
The primary intent of the award term is to provide incentive for the Contractor to perform the required services in such a manner as to warrant the highest possible rating during each evaluation period. If during an evaluation period the Contractor receives an “Unsatisfactory” rating under any of the evaluation criteria, the operation of the award term plan for future evaluation periods will cease. The duration of the contract at the time the award term plan ceases will not exceed the one (1)-year base period, the two (2)-option year periods, and any previously approved one (1)-year award term option periods.
6.0 Award Term Determination
a. Award Term Determination Criteria. The TDO may only approve the use of an award term option year if the Contractor for the applicable evaluation period earns the following: a minimum score of eighty-three points out of one hundred and five available points points based upon an overall performance rating, five points discretionary points.
b. Award Term Determination Process. The first award term determinations will be made no later than two months into the first option period of the contract and at one-year intervals thereafter, if applicable. The first award term determination will consider the Contractor’s performance ratings received during the twelve months of the base period and six month transition period. Each of the remaining seven award term determinations will be based upon one-year performance periods. The determination and process for approving an award term option is a unilateral decision made solely at the discretion of the Government.
| Rating |
| Consequence |
| Numerical |
| Adjectival |
| 95–100 |
| Superior |
| Earn two award term periods. |
| 89–94 |
| Excellent |
| Earn one award term period and any lost award term period. |
| 83–88 |
| Good |
| Earn one award term period. |
| 77–82 |
| Marginal |
| Loss of award term period. Failure to earn the required evaluation rating of eighty-three points in two successive evaluation periods will bar the ATRB from conducting future evaluations under the Award Term Plan. |
| < 77 |
| Unsatisfactory |
| Failure to earn the required evaluation rating of seventy-seven points in an evaluation period will bar the ATRB from conducting future evaluations under the Award Term Plan. |
c. TDO Determination. Unless the Award Term Plan ceases pursuant to its own terms, the TDO is required to make the award term determinations identified under this plan. If an award term option period is approved by the TDO, the exercise of the award term option is at the discretion of the Government. Favorable determinations by the TDO do not obligate the Government to exercise an award term option but only provide the CO with the authority and discretion to exercise the option in accordance with FAR 52.217-9.
d. Notification to the Contractor. The TDO will advise the Contractor and the CO of the results of the award term determination and will provide both with a copy of the final evaluation report.
7.0 Award Term Plan Change Procedure
Contractor requested changes to the Award Term Plan shall be forwarded to the CO, who as a mandatory member of the ATRB, will forward the request to the ATRB chair and board members for coordination. Upon review, the ATRB will forward a recommendation to accept or reject the changes to the TDO. Proposed changes to the Award Term Plan will be negotiated with the Contractor. If a mutual agreement cannot be reached within sixty (60) days prior to the start of the next award term period, the Government has the unilateral right to implement the changes.
Government proposed changes to the Award Term Plan will be made unilaterally if the proposed changes are prior to the start of the award term period. If proposed changes occur during the award term period the changes will be bilaterally negotiated with the Contractor.
8. 0 Award Term Extensions
If the contract term ends prior to the TDO approving the use of an award term option year or prior to the CO exercising an award term option period, the Government will incur no costs associated with the award term provision of this contract.
9.0 Award Term Periods and Available Points
The award term points earned by the Contractor will be determined at the completion of evaluation periods shown below.
Evaluation Periods
Period 1: Transition and Base Period for Award Term Year 1 (Performance Year 4) Period 2: Option Year 1 for Award Term Year 2 (Performance Year 5) Period 3: Option Year 2 for Award Term Year 3 (Performance Year 6) Period 4: Award Term Year 1 for Award Term Year 4 (Performance Year 7) Period 5: Award Term Year 2 for Award Term Year 5 (Performance Year 8) Period 6: Award Term Year 3 for Award Term Year 6 (Performance Year 9) Period 7: Award Term Year 4 for Award Term Year 7 (Performance Year 10)
The TDO will only make an award term determination for Periods 1 and 2 if the CO exercises the two (2) one (1)-year option periods in accordance with FAR 52.217-9. Any additional award term determination made by the TDO will only be made if the CO exercises additional one (1)-year award term options in accordance with FAR 52-217-9.
Maximum Available Points
The maximum available award term points that can be earned during a particular evaluation period are one hundred and five (105) points. The Contractor can earn up to a total of one hundred (100) points for each evaluation period based upon performance, plus five (5) additional discretionary points. All combined, a total of eighty-three (83) points are needed per evaluation period to approve an additional award term option period. (NOTE: All standards will be rounded to a single decimal place.)
10.0 Evaluation Criteria
a. Performance Areas and Weight
| Performance Area |
| Maximum |
Possible
| 1. |
| IT Operations |
| 30 |
| 2. |
| IT Security |
| 25 |
| 3. |
| Systems/ Network/ MIS Administration |
| 20 |
| 4. |
| Asset Management |
| 10 |
| 5. |
| Monitor, Analyze and Report on Projects |
| 15 |
| Technical Total |
| 100 |
| 6. |
| Discretionary |
| 5 |
| Award Term Period Total |
| 105 |
b. Performance Areas and Evaluation Criteria
1. IT Operations Accomplished all related related SOR requirements to the acceptable quality levels (AQL). As a total body of work the contractor accomplished DOSAW objectives to include, but not limited to the following: provide IT Operational support for the INL/A enterprise to assure network, system, and application availability. Complied with established INL/A policies and DOS network and system configuration templates. Provide weekly reports to include all IT Operations related events.
2. IT Security Accomplished all related SOR requirements to the acceptable quality levels (AQL). As a total body of work the contractor accomplished DOSAW objectives to include, but not limited to the following: provide IT Security Support for the INL/A enterprise to assure the confidentiality, integrity, availability, and reliability of all systems, services, information, and data. Complied with procedures and standards required by FIPS, National Institute of Standards and Technologies (NIST), and applicable sections of FAM/FAH. Delivery of updated C&A packages annually or upon significant change or upon expiration of ATO. Provide weekly reports to include all IT Security related events and incidents.
Continuously monitor, review, and adjust the electronic security posture of INL/A enterprise. Review and implement DOS security policy/procedure/guidelines, configure and update hardware and software, and mitigate vulnerabilities identified by security appliances and sensors placed across the enterprise. Safeguard sensitive but unclassified (SBU) and program information. Deviations from DOS policies affecting the security posture of INL/A enterprise shall be brought to the attention of the ISSO. Average vulnerability score of all INL/A systems less than (< 4) on the CVSS scale. Notify the ISSO within two (2) working days of non-compliance or deviation from policy.
3. Systems/ Network/ MIS Administration:
Accomplished all related related SOR requirements to the acceptable quality levels (AQL). As a total body of work the contractor accomplished DOSAW objectives to include, but not limited to the following: established and maintained all IT applications and hardware to ensure at a 100% operations at all times as well as Intranet and Internet-based web pages. Continuously monitor, review, and adjust the MIS posture to ensure availability and operability to all personnel.
4. Asset Management:
Accomplished all related related SOR requirements to the acceptable quality levels (AQL). As a total body of work the contractor accomplished DOSAW objectives to include, but not limited to the following: maintaining sufficient accountability (quantity and location) of all IT related property.
5. Monitor, Analyze and Report on Projects:
Accomplished all related related SOR requirements to the acceptable quality levels (AQL). As a total body of work the contractor accomplished DOSAW objectives to include, but not limited to the following: consistently applied the defined business processes to collect, synthesize, analyze and present to USG IT all requisite data, reports, metrics, and deliverables from associate contracts for USG IT consideration and action. Successfully extended related services to OCONUS operational sites.
6. Discretionary The Government will reserve five (5) points of the award term evaluation criteria and will use it to evaluate the Contractor’s overall performance, responsiveness to changing program requirements, managing workload, initiative to solve problems, quality and timeliness of reports, etc. At the discretion of the TDO, the contractor may earn anywhere from zero to five (0-5) points.
c. Scoring the Performance Areas
Types of Rating Methods
| Numerical |
| Adjectival |
| Rating Descriptors |
| 95–100 |
| Superior |
| Contractor’s performance of virtually all SOR tasks is consistently noteworthy and provides numerous significant, tangible or intangible, benefits to the Government. The few areas for improvement are all minor. There are no recurring problems. Contractor’s management initiates effective corrective action whenever needed. |
| 89–94 |
| Excellent |
| Contractor's performance of most contract tasks is consistently above standard and provides numerous significant tangible and intangible benefits to the Government (e.g., improved quality, responsiveness, increased timeliness, or generally enhanced effectiveness of operations). Although some areas may require improvement; these areas are minor and are more than offset by better performance in other areas. Few, if any, recurring problems have been noted, and contractor takes satisfactory corrective action. |
83–88
| Good |
| Contractor's performance of most contract tasks is better than adequate and provides some tangible benefits to the Government in several significant areas. While the remainder of the contractor's effort generally meets the contract requirements, areas requiring improvement are more than offset by better performance in other areas. |
| 77–82 |
| Marginal |
| Contractor’s performance of most contract tasks only marginally meets performance or capability standards necessary for acceptable contract performance, with several moderate-range risk elements identified. There are few tangible benefits to the Government due to contractor’s effort or initiative. Although there are areas of good or better performance, these are more or less offset by lower-rated performance in other areas. |
| < 77 |
| Unsatisfactory |
| Contractor’s performance of most contract tasks is inadequate and inconsistent. Quality, responsiveness, and timeliness in many areas require attention and action. Corrective actions have not been taken or are ineffective. Overall unsatisfactory performance fails to meet performance or capability standards. |
11.0 Sample Award Point Conversion
| Performance Area |
| Rated |
| Weight |
| Points |
Available Points Earned
| IT Operations |
| Superior |
| 96% |
| 30 |
| 28.8 |
| IT Security |
| Excellent |
| 92% |
| 25 |
| 23 |
| Systems/ Network/ MIS Admin |
| Excellent |
| 90% |
| 20 |
| 13.5 |
| Asset Management |
| Good |
| 88% |
| 10 |
| 13.2 |
| Monitor, Analyze and Report on Projects |
| Good |
| 84% |
| 15 |
| 12.6 |
| Technical Points |
| 91 |
| Discretionary |
| 1 |
| Overall Period Rating |
| Excellent |
Award Term Plan
File details come from the government source that posted it. Updated .