S02 VA813-028 IGNC Phase 5 Drawing_Sheets 292-302.pdf

PDF 5 MB Posted

Attached to
Indiantown Gap National Cemetery | Phase 5 Expansion Development
Solicitation number
36C10F22R0030
Issued by

View the file

Other files

File Type Posted
S06 A0003 RFI Updated Drawings.pdf PDF
S05 ALL A0003 RFIs Complete .docx DOCX document
S06 36C10F22R0030 A0003.pdf PDF
S04 Pre-Proposal Conference - IGAP Phase 5 Presentation.pdf PDF
S06 03 48 21 Precast Concrete Burial Crypts.pdf PDF
S04 Pre-Proposal Conference Attendance Sheet.pdf PDF
S06 PRICE-COST SCHEDULE Attachment.docx DOCX document
S06 A0002 RFI Updated Drawings.pdf PDF
S06 36C10F22R0030 A0002.pdf PDF
S06 23 42 00 Dust Collector.pdf PDF
S06 04 05 16 Masonry Grouting.pdf PDF
S06 05 12 00 Structural Steel Framing.pdf PDF
S06 23 36 00 Air Terminal Units.pdf PDF
S06 Past Performance Questionnaire 36C10F22R0030.docx DOCX document
S06 36C10F22R0030 A0001..pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 124-151.pdf PDF
S02 VA813-028 IGNC Phase 5 Specs_Divisions 00-33.pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 63-96.pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 152-291.pdf PDF
S02 VA813-028 IGNC Phase 5 Specs_Appendix D2.pdf PDF
S02 VA813-028 IGNC Phase 5 Specs_Appendix D5-H.pdf PDF
S02 VA813-028 IGNC Phase 5 Specs_Appendix A-D1.pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 16-23.pdf PDF
S02 VA813-028 IGNC Phase 5 Specs_Appendix D4.pdf PDF
S02 36C10F22R0030 F.pdf PDF
S02 Pre-Proposal Inquiry (PPI) Form 36C10F22R0030.docx DOCX document
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 24-39.pdf PDF
S02 VA813-028 IGNC Phase 5 Specs_Appendix D3.pdf PDF
S02 Wage Determination Davis-Bacon Act No. PA20220093.pdf PDF
S02 PAST PERFORMANCE QUESTIONNAIRE SAMPLE.docx DOCX document
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 40-62.pdf PDF
S02 VAAR 852.219-77 VA Notice of Limitations on Subcontracting - Certificate of Compliance.pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 97-123.pdf PDF
S02 Wage Determination Davis-Bacon Act No. PA20220006.pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 11-15.pdf PDF
S02 VA813-028 IGNC Phase 5 Drawing_Sheets 1-10.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CR

DC DC ES

72"

M

J

84"

J 84"

M D

XFMR-LPH

ABOVE

CONTINUED ON

ELECTRICAL

SITE PLAN

TELECOM

CABINET

PUMP HOUSE

P101

GROUND ROD

(TYPICAL)

#1/0 AWG BARE BURIED

24" BELOW GRADE.

EXTEND TO LIGHTING

RODS ON ROOF.

CONDUCTOR IS CONCEALED

IN BUILDING CONSTRUCTION.

SF-1

LPH-3

LPH-3

LPH-3

LPH-3

PHP

LPH-3

LPH-3 LPH

XFMR-LPH

PHP-7,9,11

LPH-3

LPH-3

LPH-2,4

AC-1

PHP-2,4,6

PCP

LPH-6

EF-1

LPH-5

CONTINUED ON

ELECTRICAL

SITE PLAN

30A/15A

LPH-3

LPH-3

XMFR-PH

2" CONDUIT FROM GNSS RADIO

CABINET TO GNSS ANTENNA

CONTINUED ON DRAWING G-E103.

PUMP HOUSE

P101

T

? C

CC

C? LPH-1

LPH-1

LPH-1

LPH-1

LIGHTING ROD

(TYPICAL), REFER TO

DRAWING E802 FOR

LIGHTNING PROTECTION

DETAILS

GROUND ROD

(TYPICAL), REFER TO

DRAWING E802 FOR

LIGHTNING PROTECTION

DETAILS

GROUND LOOP

REFER TO DRAWING E802

FOR LIGHTNING PROTECTION

DETAILS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

AE WORKS®

B

IM

/C F

M -0

I G

A P

/C F

M -0

I G

A P

M

E P

P u m p

H o u s e .r v t

/1

/2

:2

:2

A

M

P-E201

PUMPHOUSE - FLOOR PLANS INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA-813-028

2.18.2021 BK MPM

PHASE 5 DEVELOPMENT RFP

DOCUMENTS

1/4" = 1'-0"

PUMP HOUSE POWER PLAN

0 4' 8'2'0 4' 8'2'

1/4" = 1'-0"

PUMP HOUSE - LIGHTING PLAN

LIGHTING PLAN GENERAL NOTES

1 ALL EXIT SIGNS SHALL BE POWERED FROM THE CIRCUIT INDICATED AND UNSWITCHED.

2 EMERGENCY BATTERY BALLASTS AND EMERGENCY BATTERY PACK UNITS SHALL BE

CIRCUITED FROM THE UNSWITCHED LEG OF THE LOCAL LIGHTING CIRCUIT.

3 ALL LIGHTING FIXTURES POWERED FROM AN EMERGENCY GENERATOR CIRCUIT SHALL BE

PROVIDED WITH A UL924 LISTED AUTOMATIC LOAD CONTROL RELAY TO PERMIT LOCAL

CONTROL WITH ADJACENT FIXTURES AND BY-PASS OF LOCAL CONTROL (INCLUDING BUT

NOT LIMITED TO SWITCHES, OCCUPANCY SENSORS AND DIMMERS) IN THE ABSENCE OF

NORMAL POWER. UPON LOSS OF NORMAL POWER, THE LIGHTING CONTROL SHALL BE

BY-PASSED, AND DIMMED FIXTURES SHALL COME TO FULL ILLUMINATION AND SHALL NOT BE

ALLOWED TO TURN OFF. REFER TO TYPICAL DETAIL.

4 COORDINATE FINAL LOCATIONS OF FIXTURES WITH THE REFLECTED CEILING PLAN. ANY

CONFLICTS SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT AND ENGINEER.

5 COORDINATE ALL MOUNTING HEIGHTS WITH THE ARCHITECT AND ENGINEER PRIOR TO

ROUGH-IN.

6 WHERE MORE THAN ONE SWITCH OCCURS IN THE SAME LOCATION, THEY SHALL BE

INSTALLED IN GANG TYPE BOX UNDER THE COVERPLATE. MINIMUM CONDUIT SIZE IS 3/4",

AND MINIMUM WIRE SIZE SHALL BE #12 AWG. ALL WIRE TO BE STRANDED COPPER.

7 THE OCCUPANCY SENSORS INDICATED ON THE DRAWINGS ARE SHOWN FOR DESIGN INTENT

ONLY. THE EXACT QUANTITY OF SENSORS SHALL BE DETERMINED BY THE ELECTRICAL

CONTRACTOR PRIOR TO INSTALLING SENSORS BASED ON THE MANUFACTURER'S

RECOMMENDATION. PROVIDE 100% COVERAGE OF EACH INDIVIDUAL ROOM/SPACE SHOWN

ON THE DRAWINGS. DO NOT INSTALL SENSORS PRIOR TO SUBMITTING COVERAGE LAYOUTS

FOR EACH INDIVIDUAL ROOM/SPACE TO THE ENGINEER FOR APPROVAL. DO NOT INSTALL

SENSORS SUCH THAT THEY CAN POTENTIALLY "SEE" THROUGH OPEN DOORWAYS. INSTALL

ALL LOW VOLTAGE POWER PACKS DIRECTLY ABOVE LOCAL WALL SWITCHES IN THE AREA.

DO NOT INSTALL ULTRASONIC OR DUAL TECHNOLOGY SENSORS WITHIN 24" OF SUPPLY

DIFFUSERS.

8 ALL EMERGENCY EGRESS ILLUMINATION SHALL BE AVERAGE 1FC AND A MINIMUM OF 0.1FC

FOR PATH OF EGRESS.

9 PROVIDE CONDUIT AND WIRING AS REQUIRED TO MEET CIRCUITING SHOWN TO CONFORM

TO NEC REQUIREMENTS. PROVIDE EQUIPMENT GROUND CONDUCTOR IN ALL RACEWAYS.

REFER TO PANELBOARD SCHEDULES.

10 ROUTE CONDUIT HIGH AGAINST STRUCTURE AND OFFSET UP BETWEEN JOISTS WHERE

NECESSARY TO AVOID DUCT WORK AND HVAC SYSTEM.

11 LIGHTING CONTROL SWITCHES IN PATIENT BEDROOM BATHROOMS SHALL HAVE AMBER

PILOT LIGHT.

POWER PLAN GENERAL NOTES

1 FINAL LOCATION OF ALL EQUIPMENT SHALL BE DETERMINED IN THE FIELD AND SHALL BE INSTALLED

AS DIRECTED BY THE ARCHITECT OR OWNER'S REPRESENTATIVE. WHERE STRUCTURAL OPENINGS ARE NOT AVAILABLE, THE CONTRACTOR SHALL CORE DRILL WALLS AND FLOORS AS REQUIRED TO PERMIT PASSAGE OF CONDUITS. THE ELECTRICAL CONTRACTOR SHALL PROVIDE A MARKED-UP PLAN

WITH LOCATION PENETRATIONS FOR REVIEW AND APPROVAL OF THE STRUCTURAL ENGINEER

BEFORE ROUGH-IN BEGINS.

2 RECEPTACLES FOR ALL EQUIPMENT SHALL BE COMPLETE WITH PLUGS FOR THIS EQUIPMENT. THE ELECTRICAL CONTRACTOR SHALL VERIFY NEMA CONFIGURATIONS OF PLUGS AND RECEPTACLES FOR

EQUIPMENT IN THE SPACE.

3 DURING THE BIDDING PROCESS, THE ELECTRICAL CONTRACTOR SHALL REVIEW DRAWINGS AND SPECIFICATIONS OF ALL OTHER TRADES (ARCHITECTURAL, SITE/LANDSCAPING, HVAC, PLUMBING AND

SPECIALTY TRADES). ALL ITEMS REQUIRING POWER INDICATED ON THESE DRAWINGS BUT NOT

INDICATED ON THE ELECTRICAL DRAWINGS SHALL BE CONSIDERED A PART OF THE ELECTRICAL

CONTRACTOR'S WORK. THIS WORK SHALL BE INSTALLED AS PER NEC REQUIREMENTS AT NO

ADDITIONAL COST TO THE OWNER.

4 THE CONTRACTOR SHALL MAKE EVERY EFFORT TO MAKE ALL FEEDER RUNS CONTINUOUS (NO CABLE BREAKS). IF SPLICING CABLES IN BOXES BECOMES NECESSARY, USE O.Z.G. TYPE "XW" CABLE TAPS, OR APPROVED EQUAL, AND TAPE EACH TAP IN APPROVED MANNER.

5 THE MECHANICAL CONTRACTOR SHALL PROVIDE DISCONNECT SWITCHES, VFD'S, OR COMBINATION STARTERS FOR ALL OF THEIR UNITS. THE ELECTRICAL CONTRACTOR SHALL RECEIVE THESE ITEMS

FROM THE MECHANICAL CONTRACTOR FOR INSTALLATION BY THE ELECTRICAL CONTRACTOR.

6 THE ELECTRICAL CONTRACTOR SHALL COORDINATE CONDUIT PENETRATIONS FOR ROOFTOP

EQUIPMENT WITH MECHANICAL AND ROOFING CONTRACTORS. IF PROVISIONS ARE NOT IN PLACE FOR

THESE PENETRATIONS THE ELECTRICAL CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING OWN

PENETRATIONS AND CONTRACTING THE ROOF CONTRACTOR FOR SEALING THE ROOF PENETRATIONS.

7 REFER TO MECHANICAL DRAWINGS FOR EXACT LOCATION OF ALL MECHANICAL EQUIPMENT.

8 PROVIDE CONDUIT AND WIRING AS REQUIRED TO MEET CIRCUITING SHOWN TO CONFORM TO NEC

REQUIREMENTS.

9 PROVIDE EQUIPMENT GROUND CONDUCTOR IN ALL RACEWAYS. REFER TO PANELBOARD SCHEDULES.

10 REFER TO EQUIPMENT CONNECTION SCHEDULE FOR ELECTRICAL REQUIREMENTS AND CIRCUIT

DESIGNATIONS.

11 ROUTE CONDUIT HIGH AGAINST STRUCTURE AND OFFSET UP BETWEEN JOISTS WHERE NECESSARY

TO AVOID DUCT WORK AND HVAC SYSTEM.

12 VERIFY AND COORDINATE EXACT ELECTRICAL REQUIREMENTS OF ALL EQUIPMENT WITH

MANUFACTURER'S RECOMMENDATIONS PRIOR TO INSTALLATION OF EQUIPMENT.

13 LOCATE SECURITY CAMERAS, MOTION DETECTORS, DOOR CONTACTS, CARD READERS, AND

ELECTRONIC STRIKES AS SHOWN. DRAWING SHOWS APPROXIMATE LOCATION - INSTALLER TO

COORDINATE OPTIMUM PLACEMENT.

1/4" = 1'-0"

PUMP HOUSE - ROOF PLAN

0 4' 8'2'

N

PROJECT

NORTH

# Revisions Date DWG 292 of 302February 18, 2022

NOTES:

1. LABEL SHALL BE DISPLAYED ON ALL SWITCHBOARDS,

PANELBOARDS, TRANSFER SWITCHES AND PULLBOXES

(MULTIPLE VOLTAGES)

2. NAMEPLATE SHALL BE WHITE LETTERING ON BLACK MICARTA

3. IF ONLY ONE VOLTAGE IS PRESENT, LABEL SHALL INDICATE

ONLY THAT RESPECTIVE VOLTAGE

2" H

IG

H

4" WIDE

VOLTAGE

208Y / 120V

PHASE A BLACK

PHASE B RED

PHASE C BLUE

NEUTRAL WHITE

VOLTAGE

480Y / 277V

PHASE A BROWN

PHASE B ORANGE

PHASE C YELLOW

NEUTRAL GRAY

3 1A

A

SECTION A-A

FLOOR OR WALL ASSEMBLY -- MIN 4-1/2 IN. THICK REINFORCED LIGHTWEIGHT OR NORMAL WEIGHT (100-150 PCF) CONCRETE. WALL MAY ALSO BE CONSTRUCTED OF ANY UL CLASSIFIED CONCRETE BLOCKS *. MAX DIAM OF OPENING IS 12 IN. SEE CONCRETE BLOCKS (CAZT) CATEGORY IN THE FIRE RESISTANCE DIRECTORY FOR NAMES OF

MANUFACTURERS.

THROUGH PENETRANTS -- ONE METALLIC PIPE, CONDUIT OR TUBING TO BE INSTALLED WITHIN THE FIRESTOP SYSTEM. PIPE, CONDUIT OR TUBING TO BE RIGIDLY SUPPORTED ON BOTH SIDES OF FLOOR OR WALL ASSEMBLY.

THE ANNULAR SPACE SHALL BE 0 IN. (POINT CONTACT) TO MAX 1-1/4 IN. THE FOLLOWING TYPES AND SIZES OF

METALLIC PIPES, CONDUITS OR TUBING MAY BE USED:

A. STEEL PIPE -- NOM 10 IN. DIAM (OR SMALLER) SCHEDULE 10 (OR HEAVIER) STEEL PIPE.

B. IRON PIPE -- NOM 10 IN. DIAM (OR SMALLER) CAST OR DUCTILE IRON PIPE.

C. CONDUIT -- NOM 4 IN. DIAM (OR SMALLER) STEEL ELECTRICAL METALLIC TUBING OR STEEL CONDUIT.

D. COPPER TUBING -- NOM 4 IN. DIAM (OR SMALLER) TYPE L (OR HEAVIER) COPPER TUBING.

E. COPPER PIPE -- NOM 4 IN. DIAM (OR SMALLER) REGULAR (OR HEAVIER) COPPER PIPE.

PACKING MATERIAL -- MIN 3 IN. THICKNESS OF MIN 4 PCF MINERAL WOOL BATT INSULATION FOR NOM 4 IN. DIAM (AND SMALLER) PIPES, CONDUITS OR TUBINGS AND A MIN 4 IN. THICKNESS OF MIN 4 PCF MINERAL WOOL BATT INSULATION FOR PIPE GREATER THAN NOM 4 IN. DIAM, FIRMLY PACKED INTO OPENING AS A PERMANENT FORM.

PACKING MATERIAL TO BE RECESSED FROM TOP SURFACE OF FLOOR OR FROM BOTH SURFACES OF WALL AS

REQUIRED TO ACCOMMODATE THE REQUIRED THICKNESS OF FILL MATERIAL.

FILL, VOID OR CAVITY MATERIAL* -- SEALANT -- MIN 1/2 IN. THICKNESS OF FILL MATERIAL APPLIED WITHIN THE ANNULUS, FLUSH WITH THE TOP SURFACE OF FLOOR OR BOTH SURFACES OF WALL. AT THE POINT OF CONTACT LOCATION BETWEEN PIPE AND CONCRETE, A MIN 1/2 IN. DIAM. BEAD OF FILL MATERIAL SHALL BE APPLIED AT THE CONCRETE/PIPE INTERFACE ON THE TOP SURFACE OF FLOOR AND ON BOTH SURFACES OF WALL. W RATING

APPLIES ONLY WHEN CP601S OR CP604 SEALANT IS USED.

HILTI CONSTRUCTION CHEMICALS, DIV OF HILTI INC -- CP601S, CP604, CP606 OR FS-ONE SEALANT

*BEARING THE UL CLASSIFICATION MARK

SECURED SIDE OF THE DOOR UNSECURED SIDE OF THE DOOR

J-BOX(RECESSED)

4"x4"x2 1/8"

MOUNTED ABOVE CEILING

(VERIFY IN FIELD w/ EC)

1/2" FLEX CO 1/2" FLEX CO

DOOR CONTACT

3/4" CO

3' -6

3' -4

DOUBLE

MAGNETIC

LOCK

1/2" FLEX CO

REQUEST TO

EXIT (MOTION)

SINGLE GANG BB

3/4" CO w/ BELDON

#CMP638AFS CABLE

TO CARD

READER

CONTROLLER

TO CARD

READER

CONTROLLER

3/4" CO w/ BELDON

#CMP638AFS CABLE

1/2" FLEX CO

CARD READER /

KEYPAD / BIOMETRIC

READER COMBO

DOUBLE GANG BB

(VERTICAL)

LENGTH AS REQUIRED

CONDUIT CLAMP.

SIZE AS REQUIRED

INTEGRAL

GALVANIZED

LIPPED STEEL

MOUNTING

CHANNEL

REFER TO PLANS FOR

QUANTITY & SIZE OF

CONDUITS

NOTES

1. METAL CHANNEL STRUT SUPPORT LONGER THAN THAN

36" SHALL BE INSTALLED WITH A CENTER SUPPORT

ROD.

2. FASTEN THREADED ROD TO STRUCTURE BY APPROVED

METHOD PER SPECIFICATION 260533, RACEWAYS AND

BOXES FOR ELECTRICAL SYSTEMS. FIELD VERIFY

EXACT CONDITIONS.

3. FOR TRAPEZE INSTALLATIONS IN SEISMIC AREAS ENGAGE

THE SERVICES OF A STRUCTURAL ENGINEER TO PROVIDE

INSTALLATION DETAILS AND SPECIFICATIONS FOR

SEISMIC RESTRAINT REQUIREMENTS.

LOCKING SQUARE

WASHER & LOCKNUT

3/8" MIN GALVANIZED

THREADED ROD, TYP.

WASHER &

LOCKNUT

INTEGRAL

GALVANIZED

LIPPED STEEL

MOUNTING

CHANNEL

GROUND

PHASE

CONDUCTOR

CONDUITBREAKER SIZE

NOTE:

1. PROVIDE A CONDUCTOR PER BREAKER POLE. THESE ARE THE MINIMUM SIZES REQUIRED

FOR EACH CIRCUIT. CONTRACTOR TO MAKE ALL THE NECESSARY FIELD ADJUSTMENTS TO

COMPENSATE FOR VOLTAGE DROP.

2. IN GENERAL, VOLTAGE DROP FOR ANY BRANCH CIRCUIT SHALL NOT EXCEED 3%. VOLTAGE

DROP FOR ANY FEEDER SHALL NOT EXCEED 2%. WHERE VOLTAGE DROP EXCEEDS THESE

REQUIREMENTS, THE CONTRACTOR SHALL INCREASE THE SIZE OF THE CONDUCTORS AND

RACEWAY AS REQUIRED.

BRANCH CIRCUIT WIRING SCHEDULE (THHN)

NEUTRAL

CONDUCTOR

3/4"

3/4"

3/4"

1"

1"

1"

1"

1-1/4"

1-1/4"

1-1/2"

15A

20A

30A

35A

40A

45A

50A

60A

70A

80A

DRY-TYPE

TRANSFORMER

WALL

MINIMUM 6" CLEAR

(BOTH SIDES)

COMPRESSION

VIBRATION

ISOLATOR

4" X 2" STEEL

CHANNEL

1/2" DIAMETER

COLD ROLLED

STEEL ROD

MINIMUM 6" CLEAR

SIDE VIEWFRONT VIEW

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

AE WORKS®

B

IM

/C F

M -0

I G

A P

/C F

M -0

I G

A P

M

E P

P u m p

H o u s e .r v t

/1

/2

:2

:3

A

M

P-E701

PUMPHOUSE - ELECTRICAL SCHEDULES &

DETAILS

INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA-813-028

2.18.2021 BK MM

PHASE 5 DEVELOPMENT RFP

DOCUMENTS

12.5 :TOTAL DEMAND LOAD (A)

4.5 :TOTAL DEMAND LOAD (KVA)

100.91% :TOTAL DEMAND FACTOR

12.3 :TOTAL CONNECTED LOAD (A)

4.4 :TOTAL CONNECTED LOAD (KVA)

NOTES: 15.3 20.5 4.4 :CONNECTED LOAD/PHASE (A)

1.7 2.3 0.5 :CONNECTED LOAD/PHASE (KVA)

23 SPACE -- -- 0.00 0.00 -- -- SPACE 24

21 SPACE -- -- 0.00 0.00 -- -- SPACE 22

19 SPACE -- -- 0.00 0.00 -- -- SPACE 20

17 SPACE -- -- 0.00 0.00 -- -- SPACE 18

15 SPACE -- -- 0.00 0.00 -- -- SPACE 16

13 SPACE -- -- 0.00 0.00 -- -- SPACE 14

11 SPARE 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 12

9 SPARE 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 10

7 IRRIGATION CONTROLLER 1 15.0 A 0.60 0.00 20.0 A 1 SPARE 8

5 RCPT 1 20.0 A 0.18 0.36 20.0 A 1 EF-1 (SUPPLIED WITH IRRIGATION EQUIP) 6

3 RCPT 1 20.0 A 1.44 0.90 4

1 LIGHTING 1 20.0 A 0.16 0.90

20.0 A 2 SF-1

NO DESCRIPTION P TRIP A B C TRIP P DESCRIPTION NO

CKT CIRCUIT BREAKER LOAD (KVA) BREAKER CIRCUIT CKT

A.I.C. RATING 10,000 AMPS SYMMETRICAL MOUNTING: SURFACE

BUS RATING: 100 AMPS MCB RATING: 50.0 A FED FROM: XFMR-LPH

RATINGS: 208Y/120 MAINS TYPE: MCB LOCATION: PUMP HOUSE P101

PANEL LPH

182.9 :TOTAL DEMAND LOAD (A)

152.1 :TOTAL DEMAND LOAD (KVA)

100.03% :TOTAL DEMAND FACTOR

182.9 :TOTAL CONNECTED LOAD (A)

152.0 :TOTAL CONNECTED LOAD (KVA)

NOTES: 184.3 186.3 179.6 :CONNECTED LOAD/PHASE (A)

50.9 51.4 49.7 :CONNECTED LOAD/PHASE (KVA)

29 SPACE -- -- 0.00 0.00 -- -- SPACE 30

27 SPACE -- -- 0.00 0.00 -- -- SPACE 28

25 SPACE -- -- 0.00 0.00 -- -- SPACE 26

23 SPACE -- -- 0.00 0.00 -- -- SPACE 24

21 SPACE -- -- 0.00 0.00 -- -- SPACE 22

19 SPACE -- -- 0.00 0.00 -- -- SPACE 20

17 SPACE -- -- 0.00 0.00 -- -- SPACE 18

15 SPACE -- -- 0.00 0.00 -- -- SPACE 16

13 SPACE -- -- 0.00 0.00 -- -- SPACE 14

11 46.30 2.34 12

9 46.30 2.34 10

PUMP CONTROL PANEL 3 225.0 A

46.30 2.34

15.0 A 3 IRRIGATION WELL PUMP

5 0.53 0.58 6

3 2.29 0.58 4

XFMR-LPH 3 30.0 A

1.66 0.58

15.0 A 3 AC-1

NO DESCRIPTION P TRIP A B C TRIP P DESCRIPTION NO

CKT CIRCUIT BREAKER LOAD (KVA) BREAKER CIRCUIT CKT

A.I.C. RATING 14,000 AMPS SYMMETRICAL MOUNTING: SURFACE

BUS RATING: 400 AMPS MCB RATING: 400.0 A FED FROM:

RATINGS: 480Y/277 MAINS TYPE: MCB LOCATION:

PANEL PHP

LIGHTING FIXTURE SCHEDULE

TYPE DESCRIPTION MANUFACTURER MODEL NUMBER LAMP VOLT VA NOTE

C PENDANT INDUSTRIAL LITHONIA CLX-L48-4000LM-SEF-FDL-WD-MVOLT-GZ10-THCLX-WH LED 120 V 41 VA

EQUIPMENT CONNECTION SCHEDULE

TAG IDENTIFICATION HP

DISC / POLES /

FUSE FEEDER SIZE

CONDUIT

SIZE

AC-1 AIR COMPRESSOR 1 30A / 15A 3 - #12 AWG & #12 AWG G 3/4"

SF-1 SUPPLY FAN 0.5 20A 3 - #12 AWG & #12 AWG G 3/4"

NOT TO SCALE

BRANCH WIRING IDENTIFICATION

NOT TO SCALE

CONDUIT THROUGH CONCRETE WALL - FLOOR ASSEMBLY

NOT TO SCALE

DOOR ASSEMBLY - DOUBLE DOOR

NOT TO SCALE

CONDUIT TRAPEZE MOUNTING DETAIL

NOT TO SCALE

SUSPENDED MOUNTING OF DRY-TYPE TRANSFORMER

# Revisions Date DWG 293 of 302February 18, 2022

GFI

48"

GFI

48"

GFI

48"

GFI

48"

GFI

EWC

GFI

48"

GFI

GFI

GFI GFI

48"

48"

GFI

WP

J

J

J

J

GFI

GFI

J

J

CR

CR

CR

CR

DC

DC

DC

DC

DCDC

CR

DC

ES

ES

ES

ES

ES

ES

F P

F P

F P

60"

F

CR

F

F

F F

F

F

F F

F F

M D

MD

MD

GB

G B

G B

M D

VS VS

VS

VS

OS

OS OS

OS

OS OS

OS

OS

OS

DC

J

J J

J

J J J

J

A

XFRM-MB

TELECOM

RACK

2 - 3" CONDUITS

CONTINUED ON SITE PLAN

CONTINUED ON SITE PLAN

TRAINING ROOM

S112

FOREMAN'S

OFFICE

S110

OFFICE

S111

COVERED

OUTDOOR BREAK

AREA

S103

BREAKROOM

S101

TELECOM

S113

MECHANICAL

S114

ELECTRICAL

S102

WOMENS

S108

MENS

S106

JANITOR

S105

VESTIBULE

S100

CORRIDOR

S104

FACP

WALKIE-TALKIE

CHARGING (TYPICAL)

HP-1B HP-1A

EWH-3

EWH-2

TF-1

SBP

TF-3

SBP-18

SBP-18

SBP-18

SBP-19

SBP-16

SBP-43

SBP-41

SBP-33

SBP-23

SBP-21

SBP-44

SBP-20

SBP-25

SBP-26

SBP-25

SBP-26

SBP-25SBP-25

SBP-25

SBP-26

SBP-29

SBP-26

SBP-7,9,11SBP-8,10,12

SBP-15 SBP-14

SBP-22

SBP-26

SBP-24 SBP-24

SBP-24

SBP-24 SBP-24

SBP-35

SBP-35 SBP-35

SBP-35

SBP-27

SBP-27

SBP-27

SBP-27

SBP-26

SBP-36,38

SBP-13

SBP-26

SBP-29

SBP-15

SBP-24

SBP-42 SBP-40

SBP-52,54

SEWAGE EJECTOR

BURIED FEEDER

SBP-51

DAMPER

CONTROLS

SBP-20

DAMPER

CONTROLS

SBP-24

SBP-2

GFI

WP

+30"

EF-1

SBP-53

+7'-6"

+7'-6"

+7'-6"

+7'-6"

+7'-6"

S-E201

M

M M

A

TRAINING ROOM

S112

FOREMAN'S

OFFICE

S110

OFFICE

S111

COVERED

OUTDOOR BREAK

AREA

S103

BREAKROOM

S101

TELECOM

S113

MECHANICAL

S114

ELECTRICAL

S102

WOMENS

S108

MENS

S106

JANITOR

S105

VESTIBULE

S100

CORRIDOR

S104

FACP

B

B

A

A

B

B

COMMUNICATIONS

RACK

A

TRAINING ROOM

S112

FOREMAN'S

OFFICE

S110

OFFICE

S111

COVERED

OUTDOOR BREAK

AREA

S103

BREAKROOM

S101

TELECOM

S113

MECHANICAL

S114

ELECTRICAL

S102

WOMENS

S108

MENS

S106

JANITOR

S105

VESTIBULE

S100

CORRIDOR

S104

T

T

T

OS OS

T

V S

B2 B2

B2E B2

B2 B2

B2E B2 FAE FA FAE FA

B2 B2

B2 B2

FAE

FA

D2D1D2

C

SAE

FAE

FA

B2

B2

B2 B2

B2 B2

FAE

FA

FA

FA

FACC

D2

FA

FAE

FA

B2E

FA

FA

WC

SA SA

SA SA

SAE

WC

E1

E1

E1

E1

D1

SBP-31

SBP-31 SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31SBP-31SBP-31

SBP-31 SBP-31

SBP-31 SBP-31

SBP-31

SBP-31 SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31SBP-31

SBP-31 SBP-31

SBP-31SBP-31SBP-31SBP-31

SBP-31

SBP-31 SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31SBP-31SBP-31

SBP-31

SBP-31 SBP-31

SBP-31 SBP-31

SBP-31 SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

SBP-31

M C

M C

MC

M C

V S

V S

AHU-1B AHU-1A

SBP-17

SBP-17

SBP-17

SBP-17 SBP-17

TF-2

WH-2

SBP-22 SBP-22

SBP-28,30

SBP-29

SBP-17

SBP-29

TRAP

PRIMER

TRAP

PRIMER

CONTROL

VALVE

SBP-22

SBP-1,3,5SBP-1,3,5

CP-1

CONTROL

PANEL

MECHANICAL

S114

WELL PUMP CONTROLLER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

A

LT

E R

N A

T E

AE WORKS®

B

IM

/C

F M

-0

I G

A P

/C F

M

-0

I G

A P

M

E P

M a in te n a n c e

S ta ff .r v t

/1

/2

:5

:0

P

M

S-E201

STAFF BUILDING - FLOOR PLANS INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

2.18.2022 BK MPM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

1/8" = 1'-0"

STAFF BUILDING POWER PLAN

8' 16'4'0

1/8" = 1'-0"

STAFF BUILDING - SYSTEMS PLAN

8' 16'4'0

1/8" = 1'-0"

STAFF BUILDING - LIGHTING PLAN

8' 16'4'0

LIGHTING PLAN GENERAL NOTES

1 ALL EXIT SIGNS SHALL BE POWERED FROM THE CIRCUIT INDICATED AND UNSWITCHED.

2 EMERGENCY BATTERY BALLASTS AND EMERGENCY BATTERY PACK UNITS SHALL BE

CIRCUITED FROM THE UNSWITCHED LEG OF THE LOCAL LIGHTING CIRCUIT.

3 COORDINATE FINAL LOCATIONS OF FIXTURES WITH THE REFLECTED CEILING PLAN. ANY

CONFLICTS SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT AND ENGINEER.

4 COORDINATE ALL MOUNTING HEIGHTS WITH THE ARCHITECT AND ENGINEER PRIOR TO

ROUGH-IN.

5 WHERE MORE THAN ONE SWITCH OCCURS IN THE SAME LOCATION, THEY SHALL BE

INSTALLED IN GANG TYPE BOX UNDER THE COVERPLATE. MINIMUM CONDUIT SIZE IS 3/4",

AND MINIMUM WIRE SIZE SHALL BE #12 AWG. ALL WIRE TO BE STRANDED COPPER.

6 THE OCCUPANCY SENSORS INDICATED ON THE DRAWINGS ARE SHOWN FOR DESIGN INTENT

ONLY. THE EXACT QUANTITY OF SENSORS SHALL BE DETERMINED BY THE ELECTRICAL

CONTRACTOR PRIOR TO INSTALLING SENSORS BASED ON THE MANUFACTURER'S

RECOMMENDATION. PROVIDE 100% COVERAGE OF EACH INDIVIDUAL ROOM/SPACE SHOWN

ON THE DRAWINGS. DO NOT INSTALL SENSORS PRIOR TO SUBMITTING COVERAGE LAYOUTS

FOR EACH INDIVIDUAL ROOM/SPACE TO THE ENGINEER FOR APPROVAL. DO NOT INSTALL

SENSORS SUCH THAT THEY CAN POTENTIALLY "SEE" THROUGH OPEN DOORWAYS. INSTALL

ALL LOW VOLTAGE POWER PACKS DIRECTLY ABOVE LOCAL WALL SWITCHES IN THE AREA.

DO NOT INSTALL ULTRASONIC OR DUAL TECHNOLOGY SENSORS WITHIN 24" OF SUPPLY

DIFFUSERS.

7 ALL EMERGENCY EGRESS ILLUMINATION SHALL BE AVERAGE 1FC AND A MINIMUM OF 0.1FC

FOR PATH OF EGRESS.

8 PROVIDE CONDUIT AND WIRING AS REQUIRED TO MEET CIRCUITING SHOWN TO CONFORM

TO NEC REQUIREMENTS. PROVIDE EQUIPMENT GROUND CONDUCTOR IN ALL RACEWAYS.

REFER TO PANELBOARD SCHEDULES.

POWER PLAN GENERAL NOTES

1 FINAL LOCATION OF ALL EQUIPMENT SHALL BE DETERMINED IN THE FIELD AND SHALL BE INSTALLED AS DIRECTED BY THE ARCHITECT OR

OWNER'S REPRESENTATIVE. WHERE STRUCTURAL OPENINGS ARE NOT AVAILABLE, THE CONTRACTOR SHALL CORE DRILL WALLS AND FLOORS AS REQUIRED TO PERMIT PASSAGE OF CONDUITS. THE ELECTRICAL CONTRACTOR SHALL PROVIDE A MARKED-UP PLAN WITH LOCATION PENETRATIONS FOR REVIEW AND APPROVAL OF THE STRUCTURAL ENGINEER BEFORE ROUGH-IN BEGINS.

2 RECEPTACLES FOR ALL EQUIPMENT SHALL BE COMPLETE WITH PLUGS FOR THIS EQUIPMENT. THE ELECTRICAL CONTRACTOR SHALL VERIFY

NEMA CONFIGURATIONS OF PLUGS AND RECEPTACLES FOR EQUIPMENT IN THE SPACE.

3 DURING THE BIDDING PROCESS, THE ELECTRICAL CONTRACTOR SHALL REVIEW DRAWINGS AND SPECIFICATIONS OF ALL OTHER TRADES (ARCHITECTURAL, SITE/LANDSCAPING, HVAC, PLUMBING AND SPECIALTY TRADES). ALL ITEMS REQUIRING POWER INDICATED ON THESE DRAWINGS BUT NOT INDICATED ON THE ELECTRICAL DRAWINGS SHALL BE CONSIDERED A PART OF THE ELECTRICAL CONTRACTOR'S WORK.

THIS WORK SHALL BE INSTALLED AS PER NEC REQUIREMENTS AT NO ADDITIONAL COST TO THE OWNER.

4 THE CONTRACTOR SHALL MAKE EVERY EFFORT TO MAKE ALL FEEDER RUNS CONTINUOUS (NO CABLE BREAKS). IF SPLICING CABLES IN BOXES BECOMES NECESSARY, USE O.Z.G. TYPE "XW" CABLE TAPS, OR APPROVED EQUAL, AND TAPE EACH TAP IN APPROVED MANNER.

5 THE MECHANICAL CONTRACTOR SHALL PROVIDE DISCONNECT SWITCHES, VFD'S, OR COMBINATION STARTERS FOR ALL OF THEIR UNITS. THE ELECTRICAL CONTRACTOR SHALL RECEIVE THESE ITEMS FROM THE MECHANICAL CONTRACTOR FOR INSTALLATION BY THE ELECTRICAL

CONTRACTOR.

6 THE ELECTRICAL CONTRACTOR SHALL COORDINATE CONDUIT PENETRATIONS FOR ROOFTOP EQUIPMENT WITH MECHANICAL AND ROOFING CONTRACTORS. IF PROVISIONS ARE NOT IN PLACE FOR THESE PENETRATIONS THE ELECTRICAL CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING OWN PENETRATIONS AND CONTRACTING THE ROOF CONTRACTOR FOR SEALING THE ROOF PENETRATIONS.

7 REFER TO MECHANICAL DRAWINGS FOR EXACT LOCATION OF ALL MECHANICAL EQUIPMENT.

8 PROVIDE CONDUIT AND WIRING AS REQUIRED TO MEET CIRCUITING SHOWN TO CONFORM TO NEC REQUIREMENTS.

9 PROVIDE EQUIPMENT GROUND CONDUCTOR IN ALL RACEWAYS. REFER TO PANELBOARD SCHEDULES.

10 REFER TO EQUIPMENT CONNECTION SCHEDULE FOR ELECTRICAL REQUIREMENTS AND CIRCUIT DESIGNATIONS.

11 ROUTE CONDUIT HIGH AGAINST STRUCTURE AND OFFSET UP BETWEEN JOISTS WHERE NECESSARY TO AVOID DUCT WORK AND HVAC

SYSTEM.

12 VERIFY AND COORDINATE EXACT ELECTRICAL REQUIREMENTS OF ALL EQUIPMENT WITH MANUFACTURER'S RECOMMENDATIONS PRIOR TO

INSTALLATION OF EQUIPMENT.

FA & TECH SYSTEMS PLAN GENERAL NOTES

1 ALL FIRE ALARM WIRING & DEVICES SHALL BE IN ACCORDANCE WITH THE EXISTING FACILITY FIRE ALARM SYSTEM

MANUFACTURER VENDOR'S POINT BY POINT WIRING DIAGRAM. THE FLOOR PLAN SHOWS THE PROPOSED QUANTITY OF FIRE ALARM SYSTEM COMPONENTS. CONTRACTOR SHALL PROVIDE ADDITIONAL DEVICES AND MODULES AS REQUIRED TO PROVIDE A FULLY FUNCTIONAL AND LOCAL/NATIONAL CODE AND VA STANDARD COMPLIANT SYSTEM.

2 CONTRACTOR / VENDOR SHALL PREPARE PENNSYLVANIA LICENSED P.E. WORKING FIRE ALARM SYSTEM DRAWINGS INCORPORATING THE FIRE ALARM CRITERIA DESIGN AND CONFORMING TO VA AND AHJ REQUIREMENTS.

CONTRACTOR SHALL PROVIDE ALL MATERIAL REQUIRED PER AHJ AND VA DESIGN CRITERIA FOR A FULLY FUNCTIONING FIRE ALARM SYSTEM. SUBMIT SIGNED AND SEALED DOCUMENTS TO THE VA AND DESIGN

PROFESSIONAL AS A SHOP DRAWING FOR REVIEW.

3 THE INTENT IS FOR THE CONTRACTOR TO INSTALL ALL REQUIRED COMPONENTS FOR A FULLY FUNCTIONING FIRE

ALARM SYSTEM AS AN EXTENSION THE EXISTING FIRE ALARM SYSTEM IN THE FACILITY.

4 REFER TO POWER PLAN FOR FLOOR DATA OUTLET LOCATIONS. COORDINATE WITH OWNER AND ARCHITECT FOR FINAL LOCATIONS. COORDINATE WITH FURNITURE PLANS FOR ROUGH-IN OF ALL COMMUNICATION DEVICES.

5 LOCATE SECURITY CAMERAS, MOTION DETECTORS, DOOR CONTACTS, CARD READERS, AND ELECTRONIC STRIKES AS SHOWN. DRAWING SHOWS APPROXIMATE LOCATION - INSTALLER TO COORDINATE OPTIMUM PLACEMENT.

6 SECURITY CAMERA INSTALLER TO ENSURE CAMERA COVERAGE FROM THIS BUILDING INCLUDES BULK STORAGE

N

PROJECT

NORTH

1/4" = 1'-0"

MECHANICAL ROOM - POWER PLAN

0 4' 8'2'

1. ELECTRICAL BRANCH CIRCUIT FOR POTABLE WELL IS WIRED THRU

WELL PUMP CONTROLLER. CONTROLLER SUPPLIED WITH WELL PUMP.

REFER TO DETAIL S-E701:2

KEYNOTES

# Revisions Date DWG 294 of 302February 18, 2022

T T

C C

SBP-31SBP-31

1 1

ATTIC

S201

A

ATTIC

S201

ERV-1B ERV-1A

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

A

LT

E R

N A

T E

AE WORKS®

B

IM

/C

F M

-0

I G

A P

/C F

M

-0

I G

A P

M

E P

M a in te n a n c e

S ta ff .r v t

/1

/2

:1

:5

A

M

S-E202

STAFF BUILDING - ATTIC PLANS INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

2.18.2022 BK MM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS 4

1/8" = 1'-0"

STAFF BUILDING ATTIC - LIGHTING

1/8" = 1'-0"

STAFF BUILDING ATTIC - POWER PLAN

LIGHTING PLAN KEYNOTES

1. LOCATE LIGHT FIXTURE ABOVE ERV UNIT.

2. LOCATE LIGHT SWITCH AT ENTRANCE TO ATTIC.

8' 16'4'0 8' 16'4'0

N

PROJECT

NORTH

# Revisions Date DWG 295 of 302February 18, 2022

TYPE: COMBINATION 1-DATA, 1-TELEPHONE PORTS

CAT 6 CABLE

CAT 6 CABLE

MOUNT JACK AT I8" A.F.F. (UNLESS NOTED OTHERWISE)

TO IT. RM. DATA

PATCH PANEL

TO IT. RM. TELE.

PATCH PANEL

TYPE: 2-DATA JACKS FOR WIRELESS ACCESS POINT

15' PATCH CORD

PROVIDED BY CONTRACTOR

TO WIRELESS

ACCESS

TRANSCEIVER

D A

T A

D A

T A

P H

O N

E

D A

T A

CAT 6A CABLE

TO IT. RM. DATA

PATCH PANEL

D A

T A

D A

T A

CAT 6A CABLE

TO IT. RM. DATA

PATCH PANEL

TYPE: COMBINATION 2-DATA PORTS

MOUNT JACK AT 18" A.F.F. (UNLESS NOTED OTHERWISE)

BA

D A

T A

D A

T A

CAT 6A CABLE

TO IT. RM. DATA

PATCH PANEL

TYPE: SECURITY CAMERA - COMBINATION 2-DATA PORTS

MOUNT JACKS ON CEILING OR WALL FOR SECURITY CAMERA

DUCT SMOKE DETECTOR

AREA SMOKE DETECTOR

MANUAL PULL STATION

NOTIFY

NECESSARY

STAFF FOR

RESPONSE

NOTIFY

FIRE

DEPARTMENT

INITIATE

SUPERVISORY

SIGNAL

TO A 24-HOUR

MANNED POINT

FOR IMMEDIATE

RESPONSE.

CLOSE

ASSOCIATE

SMOKE

BARRIER

DOORS ON THE

FLOOR

CLOSE

DAMPERS

ON FAN

PROXIMATE TO

DETECTOR.

SHUT DOWN

AIR HANDLER

SERVED

BY THE

DETECTOR

RECALL

ELEVATOR

INITIATE

ELEVATOR

SHUTDOWN

AND

DISCONNECT

ELEVATOR

POWER

OPEN LOCKED

EGRESS

DOORS ON

FLOOR OF

FIRE ORIGIN

FIRE ALARM SYSTEM INPUT/OUTPUT MATRIX

INPUT DEVICE

X

OUTPUT

X

X

X

X

X

X X

X

X

TO NEXT

DEVICE

F

S

F

TO NEXT

DEVICE

F P

FACP

TYPICAL PARTIAL FIRE ALARM RISER DIAGRAM

NOTES:

1. LABEL SHALL BE DISPLAYED ON ALL SWITCHBOARDS,

PANELBOARDS, TRANSFER SWITCHES AND PULLBOXES

(MULTIPLE VOLTAGES)

2. NAMEPLATE SHALL BE WHITE LETTERING ON BLACK MICARTA

3. IF ONLY ONE VOLTAGE IS PRESENT, LABEL SHALL INDICATE

ONLY THAT RESPECTIVE VOLTAGE

2" H

IG

H

4" WIDE

VOLTAGE

208Y / 120V

PHASE A BLACK

PHASE B RED

PHASE C BLUE

NEUTRAL WHITE

VOLTAGE

480Y / 277V

PHASE A BROWN

PHASE B ORANGE

PHASE C YELLOW

NEUTRAL GRAY

UNSECURED SURFACE STRIKESECURED SURFACE STRIKE

RIGHT HAND REVERSE(RHRB) DOOR

PANIC

EXITING DEVICE

DOOR STRIKE

SURFACE MTD.

DOOR STRIKE

(BEYOND)

1/2" FLEX CO

DOOR CONTACT

3/4" CO

CARD READER

SINGLE GANG BB

(VERTICAL)

1/2" FLEX CO

REQUEST TO EXIT(REX)

SINGLE GANG BB

(HORIZONTAL)

4" TO 8"

6"

3' -6

3' -4

VELCRO TIE WRAPS

DATA CATEGORY 6

CABLING ONLY

VELCRO TIE WRAPS

TELEPHONE

CATEGORY 6

CABLING ONLY

MAX 5'

NYLON BUSHING

1 1/4" EMT CONDUIT

SUSPENDED CEILING

1 1/4" EMT CONDUIT

EMT COMPRESSION FITTING

4" x 4" x 2.25"

JUNCTION BOX

MUD RING

COVER PLATE

8" M

IN

A .F

.F . O

R A

S N

O T

E D

GROUND

PHASE

CONDUCTOR

CONDUITBREAKER SIZE

NOTE:

1. PROVIDE A CONDUCTOR PER BREAKER POLE. THESE ARE THE MINIMUM SIZES REQUIRED

FOR EACH CIRCUIT. CONTRACTOR TO MAKE ALL THE NECESSARY FIELD ADJUSTMENTS TO

COMPENSATE FOR VOLTAGE DROP.

2. IN GENERAL, VOLTAGE DROP FOR ANY BRANCH CIRCUIT SHALL NOT EXCEED 3%. VOLTAGE

DROP FOR ANY FEEDER SHALL NOT EXCEED 2%. WHERE VOLTAGE DROP EXCEEDS THESE

REQUIREMENTS, THE CONTRACTOR SHALL INCREASE THE SIZE OF THE CONDUCTORS AND

RACEWAY AS REQUIRED.

BRANCH CIRCUIT WIRING SCHEDULE (THHN)

NEUTRAL

CONDUCTOR

3/4"

3/4"

3/4"

1"

1"

1"

1"

1-1/4"

1-1/4"

1-1/2"

15A

20A

30A

35A

40A

45A

50A

60A

70A

80A

TO BREAKER PANEL

GROUND

GROUND

L1

M1

M2

L2

L3

PRESSURE

SWITCH

CONTROL

BOX

L1 L2 R Y B L3

GROUND

SUBMERSIBLE

PUMP

WELL CASING

NEMA 3R

DISCONNECT

SWITCH

ALL WIRING IN #8 AWG

WIRING IN CONDUIT, EXCEPT IN WELL CASING.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

A

LT

E R

N A

T E

AE WORKS®

B

IM

/C

F M

-0

I G

A P

/C F

M

-0

I G

A P

M

E P

M a in te n a n c e

S ta ff .r v t

/1

/2

:5

:0

P

M

S-E701

STAFF BUILDING - ELECTRICAL SCHEDULES

& DETAILS

INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

2.18.2022 Checker Author

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

186.5 :TOTAL DEMAND LOAD (A)

67.2 :TOTAL DEMAND LOAD (KVA)

99.56% :TOTAL DEMAND FACTOR

187.3 :TOTAL CONNECTED LOAD (A)

67.5 :TOTAL CONNECTED LOAD (KVA)

NOTES: 175.3 194.1 198.1 :CONNECTED LOAD/PHASE (A)

21.0 23.0 23.5 :CONNECTED LOAD/PHASE (KVA)

71 SPARE 1 20.0 A 0.00 0.00 -- -- SPACE 72

69 SPARE 1 20.0 A 0.00 0.00 -- -- SPACE 70

67 SPARE 1 20.0 A 0.00 0.00 -- -- SPACE 68

65 SPARE 1 20.0 A 0.00 0.00 -- -- SPACE 66

63 SPARE 1 20.0 A 0.00 0.00 -- -- SPACE 64

61 SPARE 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 62

59 SPACE -- -- 0.00 0.00 -- -- SPACE 60

57 SPACE -- -- 0.00 0.00 -- -- SPACE 58

55 SPACE -- -- 0.00 0.00 -- -- SPACE 56

53 SPEC 1 20.0 A 0.70 2.00 54

51 RADIO EQUIPMENT 1 20.0 A 0.18 2.00

40.0 A 2 SEWAGE EJECTOR PUMP

49 0.00 2.10 50

47 0.00 2.10 48

SPARE 3 125.0 A

0.00 2.10

35.0 A 3 POTABLE WELL PUMP

43 RECEP - S101 VENDING MACHINE 1 20.0 A 0.72 0.72 20.0 A 1 RECEP - S101 EWC 44

41 RECEP - S101 VENDING MACHINE 1 20.0 A 0.72 0.18 20.0 A 1 RCPT 42

39 0.85 0.18 20.0 A 1 RCPT 40

ERV-1B 2 20.0 A

0.85 1.00 38

35 RECEP - S111 1 20.0 A 0.72 1.00

20.0 A 2 EWH-2

33 RECEP - S101 REFRIGERATOR 1 20.0 A 0.72 0.85 34

31 LIGHTING 1 20.0 A 1.53 0.85

20.0 A 2 ERV-1A

29 EWH-1 & EWH-3 1 20.0 A 1.00 3.00 30

27 RECEP - S110 1 20.0 A 0.72 3.00

40.0 A 2 WH-2

25 RECEP - S105, S106 & S108 1 20.0 A 0.90 1.06 20.0 A 1 RECEP - S102, S104 & S114 26

23 RECEP - S101 COUNTERTOP 1 20.0 A 0.72 0.90 20.0 A 1 RECEP - S112 24

21 RECEP - S101 COUNTERTOP 1 20.0 A 0.72 1.39 20.0 A 1 TF-2 & TF-3 22

19 RECEP - S101 WALKIE-TALKIE 1 20.0 A 0.48 0.70 20.0 A 1 TF-1 20

17 RECEP - S114 & CP-1 1 20.0 A 0.36 0.54 20.0 A 1 RECEP - S101 18

15 RECEP - S113 1 20.0 A 0.18 0.48 20.0 A 1 RECEP - S101 WALKIE-TALKIE 16

13 FIRE ALARM CONTROL PANEL 1 20.0 A 0.00 0.18 20.0 A 1 RECEP - S113 14

11 4.32 4.32 12

9 4.32 4.32 10

HP-1A 3 60.0 A

4.32 4.32

60.0 A 3 HP-1B

5 1.36 0.00 20.0 A 1 SPARE 6

3 1.36 0.00 -- -- SPACE 4

AHU-1A & AHU-1B 3 15.0 A

1.36 0.18 20.0 A 1 RCPT 2

NO DESCRIPTION P TRIP A B C TRIP P DESCRIPTION NO

CKT CIRCUIT BREAKER LOAD (KVA) BREAKER CIRCUIT CKT

A.I.C. RATING 10,000 AMPS SYMMETRICAL MOUNTING: SURFACE

BUS RATING: 400 AMPS MCB RATING: 400.0 A FED FROM: XFRM-MB

RATINGS: 208Y/120 MAINS TYPE: MCB LOCATION: ELECTRICAL S102

PANEL SBP

LIGHTING FIXTURE SCHEDULE

TYPE DESCRIPTION MOUNTING MANUFACTURER MODEL NUMBER LAMP VOLT VA NOTE

B2 2X2 FIXTURE LAY-IN LITHONIA 2BLT2 33LM ADP EZ1 LP835 LED 120 V 31 VA

B2E 2X2 FIXTURE WITH BATTERY BACKUP LAY-IN LITHONIA 2BLT2 33LM ADP EZ1 LP835 EL14LSD LED 120 V 31 VA

C SURFACE WRAPAROUND PENDANT LITHONIA THCLX L48 3000 LM HEF FDL WD MVOLT 40K WH LED 120 V 39 VA

D1 RECESSED DOWNLIGHT RECESSED LITHONIA EVO4 35K 05 AR MD LSS MVOLT GZ10 SF120 LED 120 V 11 VA

D2 RECESSED DOWNLIGHT - WITH BATTERY BACKUP RECESSED LITHONIA EVO4 35K 05 AR MD LSS MVOLT GZ10 SF120 ELSD LED 120 V 11 VA

E1 EXIT SIGN WITH BATTERY BACKUP UNIVERSAL LITHONIA LES 1 R 120/277 EL N SD LED 120 V 5 VA

FA 2X2 FIXTURE LAY-IN LITHONIA EPANL 2X2 2000LMHE 80 CRI 35K EZT 120 LED 120 V 22 VA

FAE 2X2 FIXTURE WITH BATTERY BACKUP LAY-IN LITHONIA EPANL 2X2 2000LMHE 80 CRI 35K EZT 120 E10WCP LED 120 V 22 VA

SA 1X4 FIXTURE SURFACE LITHONIA BWLP 40LHE ADSMT 120V EZ1 LP830 LED 120 V 41 VA

SAE 1X4 FIXTURE WITH BATTERY BACKUP SURFACE LITHONIA BWLP 40LHE ADSMT 120V EZ1 LP830 E10WLCP LED 120 V 41 VA

WC EXTERIOR WALL PACK WITH BATTERY BACKUP LITHONIA DWSW1LED 10C 350 40K TFTM 120 PE E20WC SF120 LED 120 V 13 VA

EQUIPMENT CONNECTION SCHEDULE

TAG HP

FLA /

MCA DISC / POLES / FUSE FEEDER SIZE CONDUIT SIZE

AHU-1A 4.5 / 5.6 3 - #12 AWG & #12 AWG G 3/4"

AHU-1B 4.5 / 5.6 3 - #12 AWG & #12 AWG G 3/4"

HP-1A 60A 3 - #6 AWG & #10 AWG G 1.25"

HP-1B 60A 3 - #6 AWG & #10 AWG G 1.25"

SEWAGE EJECTOR 1 NEMA 3R - 60A NON FUSED 2 - #8 AWG & #10 AWG G 1"

WH-2 60A NON FUSED 2 - #10 AWG & #10 AWG G 3/4"

NOT TO SCALE

DATA/TELE FACEPLATE DETAILS

1/8" = 1'-0"

FIRE ALARM MATRIX

NOT TO SCALE

BRANCH WIRING IDENTIFICATION

NOT TO SCALE

EGRESS DOOR ASSEMBLY

NOT TO SCALE

J HOOK DETAIL

NOT TO SCALE

ROUGH-IN DETAIL

NOT TO SCALE

WELL PUMP CONTROL DETAIL

# Revisions Date DWG 296 of 302February 18, 2022

WP

GFI

WP

J

K

J

WBP

MAU-1

WASH BAY

WBP-4

WBP-6,8,10

WBP-1

WBP-13

WH-3

EF-1

WBP-9,11

WBP-13

WP

ELECTRONIC

TRAP

PRIMER

10' - 0"

XFMR-WB

CONTINUED

ON SITE PLAN

+36"

GFI,WP

WBP-13

WBP-3,5,7

NEMA 3R

NEMA 3R

HB

HB

HB

HB

HB

HB

WP

WBP-2WBP-2

WBP-2 WBP-2

WBP-2WBP-2

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

AE WORKS®

B

IM

/C

F M

-0

I G

A P

/C F

M

-0

I G

A P

M

E P

E x is ti n g S to ra g e .r v t

/1

/2

:5

:0

A

M

W-E201

NEW WASH BAY - ELECTRICAL PLANS INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

02.18.2022 BK MM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

1/4" = 1'-0"

NEW WASH BAY POWER PLAN

0 4' 8'2'

POWER PLAN KEYNOTES1/4" = 1'-0"

NEW WASH BAY LIGHTING PLAN

0 4' 8'2'

LIGHTING PLAN GENERAL NOTES

1 ALL EXIT SIGNS SHALL BE POWERED FROM THE CIRCUIT INDICATED AND UNSWITCHED.

2 COORDINATE FINAL LOCATIONS OF FIXTURES WITH THE REFLECTED CEILING PLAN. ANY

CONFLICTS SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT AND ENGINEER.

3 COORDINATE ALL MOUNTING HEIGHTS WITH THE ARCHITECT AND ENGINEER PRIOR TO

ROUGH-IN.

4 WHERE MORE THAN ONE SWITCH OCCURS IN THE SAME LOCATION, THEY SHALL BE

INSTALLED IN GANG TYPE BOX UNDER THE COVERPLATE. MINIMUM CONDUIT SIZE IS 3/4",

AND MINIMUM WIRE SIZE SHALL BE #12 AWG. ALL WIRE TO BE STRANDED COPPER.

5 PROVIDE CONDUIT AND WIRING AS REQUIRED TO MEET CIRCUITING SHOWN TO CONFORM

TO NEC REQUIREMENTS. PROVIDE EQUIPMENT GROUND CONDUCTOR IN ALL RACEWAYS.

REFER TO PANELBOARD SCHEDULES.

6 ROUTE CONDUIT HIGH AGAINST STRUCTURE AND OFFSET UP BETWEEN JOISTS WHERE

NECESSARY TO AVOID DUCT WORK AND HVAC SYSTEM.

POWER PLAN GENERAL NOTES

1 FINAL LOCATION OF ALL EQUIPMENT SHALL BE DETERMINED IN THE FIELD AND SHALL BE INSTALLED

AS DIRECTED BY THE ARCHITECT OR OWNER'S REPRESENTATIVE. WHERE STRUCTURAL OPENINGS ARE NOT AVAILABLE, THE CONTRACTOR SHALL CORE DRILL WALLS AND FLOORS AS REQUIRED TO PERMIT PASSAGE OF CONDUITS. THE ELECTRICAL CONTRACTOR SHALL PROVIDE A MARKED-UP PLAN

WITH LOCATION PENETRATIONS FOR REVIEW AND APPROVAL OF THE STRUCTURAL ENGINEER

BEFORE ROUGH-IN BEGINS.

2 RECEPTACLES FOR ALL EQUIPMENT SHALL BE COMPLETE WITH PLUGS FOR THIS EQUIPMENT. THE ELECTRICAL CONTRACTOR SHALL VERIFY NEMA CONFIGURATIONS OF PLUGS AND RECEPTACLES FOR

EQUIPMENT IN THE SPACE.

3 DURING THE BIDDING PROCESS, THE ELECTRICAL CONTRACTOR SHALL REVIEW DRAWINGS AND SPECIFICATIONS OF ALL OTHER TRADES (ARCHITECTURAL, SITE/LANDSCAPING, HVAC, PLUMBING AND

SPECIALTY TRADES). ALL ITEMS REQUIRING POWER INDICATED ON THESE DRAWINGS BUT NOT

INDICATED ON THE ELECTRICAL DRAWINGS SHALL BE CONSIDERED A PART OF THE ELECTRICAL

CONTRACTOR'S WORK. THIS WORK SHALL BE INSTALLED AS PER NEC REQUIREMENTS AT NO

ADDITIONAL COST TO THE OWNER.

4 THE CONTRACTOR SHALL MAKE EVERY EFFORT TO MAKE ALL FEEDER RUNS CONTINUOUS (NO CABLE BREAKS). IF SPLICING CABLES IN BOXES BECOMES NECESSARY, USE O.Z.G. TYPE "XW" CABLE TAPS, OR APPROVED EQUAL, AND TAPE EACH TAP IN APPROVED MANNER.

5 THE MECHANICAL CONTRACTOR SHALL PROVIDE DISCONNECT SWITCHES, VFD'S, OR COMBINATION STARTERS FOR ALL OF THEIR UNITS. THE ELECTRICAL CONTRACTOR SHALL RECEIVE THESE ITEMS

FROM THE MECHANICAL CONTRACTOR FOR INSTALLATION BY THE ELECTRICAL CONTRACTOR.

6 REFER TO MECHANICAL DRAWINGS FOR EXACT LOCATION OF ALL MECHANICAL EQUIPMENT.

7 PROVIDE CONDUIT AND WIRING AS REQUIRED TO MEET CIRCUITING SHOWN TO CONFORM TO NEC

REQUIREMENTS.

8 PROVIDE EQUIPMENT GROUND CONDUCTOR IN ALL RACEWAYS. REFER TO PANELBOARD SCHEDULES.

9 REFER TO EQUIPMENT CONNECTION SCHEDULE FOR ELECTRICAL REQUIREMENTS AND CIRCUIT

DESIGNATIONS.

10 ROUTE CONDUIT HIGH AGAINST STRUCTURE AND OFFSET UP BETWEEN JOISTS WHERE NECESSARY

TO AVOID DUCT WORK AND HVAC SYSTEM.

11 VERIFY AND COORDINATE EXACT ELECTRICAL REQUIREMENTS OF ALL EQUIPMENT WITH

MANUFACTURER'S RECOMMENDATIONS PRIOR TO INSTALLATION OF EQUIPMENT.

12 REFER TO DRAWINGS E-800 FOR ELECTRICAL SERVICE TO THIS BUILDING. ALL WORK IS NEW

CONSTRUCTION.

N

PROJECT

NORTH

1 KEY OPERATED SWITCH FOR OVERHEAD DOOR.

# Revisions Date DWG 297 of 302February 18, 2022

GROUND

PHASE

CONDUCTOR

CONDUITBREAKER SIZE

NOTE:

1. PROVIDE A CONDUCTOR PER BREAKER POLE. THESE ARE THE MINIMUM SIZES REQUIRED

FOR EACH CIRCUIT. CONTRACTOR TO MAKE ALL THE NECESSARY FIELD ADJUSTMENTS TO

COMPENSATE FOR VOLTAGE DROP.

2. IN GENERAL, VOLTAGE DROP FOR ANY BRANCH CIRCUIT SHALL NOT EXCEED 3%. VOLTAGE

DROP FOR ANY FEEDER SHALL NOT EXCEED 2%. WHERE VOLTAGE DROP EXCEEDS THESE

REQUIREMENTS, THE CONTRACTOR SHALL INCREASE THE SIZE OF THE CONDUCTORS AND

RACEWAY AS REQUIRED.

BRANCH CIRCUIT WIRING SCHEDULE (THHN)

NEUTRAL

CONDUCTOR

3/4"

3/4"

3/4"

1"

1"

1"

1"

1-1/4"

1-1/4"

1-1/2"

15A

20A

30A

35A

40A

45A

50A

60A

70A

80A

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 725-8456

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works, LTD.

418 Beaver Street

Sewickley, PA

Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100

AE WORKS®

B

IM

/C

F M

-0

I G

A P

/C F

M

-0

I G

A P

M

E P

E x is ti n g S to ra g e .r v t

/1

/2

:5

:0

A

M

W-E701

NEW WASH BAY - ELECTRICAL SCHEDULES INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

02.18.2022 BK MM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

LIGHTING FIXTURE SCHEDULE

TYPE DESCRIPTION MANUFACTURER MODEL NUMBER LAMP VOLT VA NOTE

HB 1X4 FIXTURE LITHONIA CSVT L48 4000LM MVOLT 40K 80CRI STSL LED 120 V 38 VA 10.5' AFF

115.5 :TOTAL DEMAND LOAD (A)

41.6 :TOTAL DEMAND LOAD (KVA)

100.14% :TOTAL DEMAND FACTOR

NEMA 3R ENCLOSURE 115.3 :TOTAL CONNECTED LOAD (A)

41.6 :TOTAL CONNECTED LOAD (KVA)

NOTES: 98.1 130.6 124.7 :CONNECTED LOAD/PHASE (A)

11.8 15.2 14.5 :CONNECTED LOAD/PHASE (KVA)

41 SPACE -- -- 0.00 0.00 -- -- SPACE 42

39 SPACE -- -- 0.00 0.00 -- -- SPACE 40

37 SPACE -- -- 0.00 0.00 -- -- SPACE 38

35 SPACE -- -- 0.00 0.00 -- -- SPACE 36

33 SPACE -- -- 0.00 0.00 -- -- SPACE 34

31 SPACE -- -- 0.00 0.00 -- -- SPACE 32

29 SPACE -- -- 0.00 0.00 -- -- SPACE 30

27 SPACE -- -- 0.00 0.00 -- -- SPACE 28

25 SPACE -- -- 0.00 0.00 -- -- SPACE 26

23 SPACE -- -- 0.00 0.00 -- -- SPACE 24

21 SPACE -- -- 0.00 0.00 -- -- SPACE 22

19 SPARE 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 20

17 SPARE 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 18

15 SPARE 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 16

13 RCPT 1 20.0 A 0.00 0.00 20.0 A 1 SPARE 14

11 3.00 0.00 20.0 A 1 SPARE 12

WH-3 2 40.0 A

3.00 0.92 10

7 10.63 0.92 8

5 10.63 0.92

20.0 A 3 GARAGE DOOR

MAU-1 3 125.0 A

10.63 0.70 20.0 A 1 EF-1 4

1 RCPT 1 20.0 A 0.00 0.23 20.0 A 1 LITES 2

NO DESCRIPTION P TRIP A B C TRIP P DESCRIPTION NO

CKT CIRCUIT BREAKER LOAD (KVA) BREAKER CIRCUIT CKT

A.I.C. RATING 10,000 AMPS SYMMETRICAL MOUNTING: SURFACE

BUS RATING: 225 AMPS MCB RATING: 225.0 A FED FROM:

RATINGS: 208Y/120 MAINS TYPE: MCB LOCATION: WASHBAY 101

PANEL WBP

EQUIPMENT CONNECTION SCHEDULE

TAG NEMA TYPE

DISC / POLES /

FUSE FEEDER SIZE

CONDUIT

SIZE

GARAGE DOOR 30A 3 - #12 AWG & #12 AWAG G 3/4"

MAU-1 3 - #1 AWG & #6 AWG G 1.5"

WH-3 60A 2 - #8 AWG & #10 AWG G 3/4"

# Revisions Date DWG 298 of 302February 18, 2022

LP

LP

EM

TR

INDIANTOWN GAP

ROAD

24" CMP

4" PVC 10" TCP

" T

CP

15"

12"

METAL

GARAGE

METAL

GARAGE

METAL

GARAGE

OLD CUMBERLAND STREET

MATCHLINE G-E104

MATCHLINE G-E101

ADMINISTRATION

BUILDING -1001

1 2

TYPICAL

TYPICAL

TYPICAL

TYPICAL

EXISTING

MAINTENANCE - 3001

STORAGE - 3002 STORAGE

MATCHLINE G-E101MATCHLINE G-E102

MA

TC

HL

IN

E G-

E1

MA

TC

HL

IN

E G-

E1

TYPICAL

14TYPICAL

TYPICAL

WASH

BAY

RESTROOM - PR

COMMITTAL

SHELTER

SCALE:

PARTIAL ELECTRICAL SITE PLAN

1" = 50'

G-E102

G-E101

00 50' 100'

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 930-5779

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works LTD.

418 Beaver Street Sewickley, PA Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100 AE WORKS®

BI

M

C

FM

0-

IG

AP

/C

FM

0-

8/

2/

0:

:2

AM

INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

2.15.2022 BK MM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

# Revisions Date

PARTIAL ELECTRICAL SITE PLAN

DRAWING KEYNOTES

1. NEW 15 KV DUAL FUSED SWITCH. REFER TO DRAWING E801-1 FOR DETAILS.

2. NEW MEDIUM VOLTAGE FEEDER: 3 - #2 AWG (15KV) AND #6 AWG (600V)

IN 4" PVC CONDUIT AND SPARE 4" CONDUIT.

3. (2) NEW BURIED SINGLE MODE FIBER OPTIC CABLES IN (2) - 4" PVC CONDUIT.

FIBER OPTIC CABLE TO BE ADJACENT TO MEDIUM VOLTAGE POWER

ALONG OLD CUMBERLAND ROAD TO REACH NEW CONSTRUCTION.

HORIZONTAL SEPARATION OF 24" BETWEEN POWER AND FIBER OPTIC CABLES.

4. NEW CONCRETE MANHOLE FOR POWER DISTRIBUTION.

5. NEW NON-METALLIC HAND HOLE FOR FIBER OPTIC CABLES. 30" X 18".

6. EXTEND FIBER OPTIC CABLE TO ADMINISTRATION BUILDING.

7. DISCONNECT AND REMOVE EXISTING 112.5KVA 13.2 KV TO 208/120-VOLT, THREE

PHASE TRANSFORMER AND CONCRETE BASE FEEDING MAINTENANCE BUILDING.

PROVIDE AND INSTALL NEW 112.5KVA, 13.2KV TO 208/120-VOLT, THREE PHASE

TRANSFORMER ON NEW CONCRETE BASE. RECONNECT ALL WIRING.

8. DISCONNECT AND REMOVE EXISTING 75KVA 13.2 KV TO 208/120-VOLT, THREE

PHASE TRANSFORMER AND CONCRETE BASE FEEDING ADMINISTRATION BUILDING.

PROVIDE AND INSTALL NEW 75KVA, 13.2KV TO 208/120-VOLT, THREE PHASE

TRANSFORMER ON NEW CONCRETE BASE. RECONNECT ALL WIRING.

9. NEW 75KVA TRANSFORMER 13.2KV DELTA PRIMARY TO 208/120-VOLT WYE SECONDARY

10. NEW SERVICE ENTRANCE RATED PANEL BOARD - MPB.

11. 2 - GROUND RODS, 6' APART AT NEW GNSS RADIO ANTENNA. CONNECT GROUND

RODS WITH #6 AWG BARE COPPER AND MAKE GROUND CONNECTION

TO REINFORCING STEEL IN CONCRETE BASE, AND POLE.

12. 1 - 2" CONDUITS FROM GNSS TOWER TO ELECTRICAL PANEL 'S'.

13. NEW SECURITY CAMERA ON EXISTING BUILDING.

14. NEW LIGHT FIXTURES ON EXISTING BUILDING. CONTROL NEW FIXTURES WITH

ASTRONOMICAL TIME CLOCK. POWER FOR LIGHT FIXTURES AND TIME CLOCK FROM

SPARE CIRCUIT BREAKER IN CIRCUIT BREAKER PANEL. TIME CLOCK TO BE LOCATED

LIGHT FIXTURE - LITHONIA CATALOG NUMBER - ARC2LED P2 40K DDBXD

15. REFER TO SPECIFICATION SECTION 11 83 00 FOR GNSS EQUIPMENT REQUIREMENTS.

16. LOCATE SECURITY CAMERAS ON BUILDING EXTERIOR AS SHOWN. DRAWING SHOWS

APPROXIMATE LOCATION - INSTALLER TO COORDINATE OPTIMUM PLACEMENT.

DRAWING GENERAL NOTES

EXISTING MAINTENANCE BUILDING - REFER TO M-ED201 FOR DEMOLITION WORK IN THIS BUILDING.

NEW WASH BAY BUILDING - REFER TO W-E201 & W-E701 FOR WORK IN THIS BUILDING.

EXISTING MAINTENANCE BUILDING - REFER TO E-800, M-E201 & M-E701 FOR NEW WORK IN THIS BUILDING.

17. DISCONNECT BRANCH CIRCUIT AND CONTROL WIRING TO OVERHEAD DOOR MOTOR.

RECONNECT BRANCH CIRCUIT AND CONTROL WIRING TO NEW OVERHEAD DOOR MOTOR.

IN ELECTRICAL ROOM OF EXISTING ADMINISTRATION BUILDING.

18. EXISTING UTILITY POLE TO REMAIN.

19. PROPOSED OVERHEAD ELECTRIC AND TELECOMMUNICATIONS SERVICES.

20. PROPOSED WOODEN UTILITY POLE.

21. PROPOSED UNDERGROUND ELECTRIC SERVICE.

22. PROPOSED POWER DISTRIBUTION PANEL.

23. PROPOSED TELECOMMUNICATIONS DISTRIBUTION CABINET.

24. PROPOSED UNDERGROUND COMMUNICATIONS CABLE. REFER TO CONTRACT DRAWING E800 & E801 FOR SITE WORK CONSTRUCTION DETAILS.

25. 3/4" x 10' GROUND ROD AND #6 AWG GROUND WIRE IN CONDUIT. CADWELD AT BOTH CONNECTIONS.

CONCEAL CONDUIT IN FINISHED SPACES.

DWG 299 of 302February 18, 2022

AE WORKS®

EM

OLD CUMBERLAND

STREET

OLD CUMBERLAND

STREET

TYPICAL

TYPICAL

TYPICAL

TYPICAL

OLD CUMBERLAND STREET

MATCHLINE G-E101

MATCHLINE G-E102

MA

TC

HL

IN

E G-

E1

MA

TC

HL

IN

E G-

E1

02 MATCHLINE G-E101

MATCHLINE G-E102

MA

TC

HL

IN

E G-

E1

MA

TC

HL

IN

E G-

E1

SCALE:

PARTIAL ELECTRICAL SITE PLAN

1" = 50'

G-E103

G-E102

00 50' 100'

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 930-5779

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works LTD.

418 Beaver Street Sewickley, PA Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100 AE WORKS®

BI

M

C

FM

0-

IG

AP

/C

FM

0-

8/

2/

0:

:2

AM

INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

2.15.2022 BK MM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

# Revisions Date

PARTIAL ELECTRICAL SITE PLAN

DRAWING KEYNOTES

1. NEW CONCRETE MANHOLE FOR POWER DISTRIBUTION.

2. NEW MEDIUM VOLTAGE FEEDER: 3 - #2 AWG (15KV) AND #6 AWG (600V)

IN 4" PVC CONDUIT AND SPARE 4" CONDUIT.

3. (2) NEW BURIED SINGLE MODE FIBER OPTIC CABLE IN (2) - 4" PVC CONDUIT.

FIBER OPTIC CABLE TO BE ADJACENT TO MEDIUM VOLTAGE POWER

ALONG OLD CUMBERLAND ROAD TO REACH NEW CONSTRUCTION.

HORIZONTAL SEPARATION OF 24" BETWEEN POWER AND FIBER OPTIC CABLES.

4. NEW BURIED NON-METALLIC HANDHOLE - 18" X 30", FOR FIBER OPTIC CABLES.

REFER TO CONTRACT DRAWING E802 FOR SITE WORK CONSTRUCTION DETAILS.

DRAWING GENERAL NOTES

DWG 300 of 302 February 18, 2022

PUMP HOUSE

TYPICAL

TYPICAL

TYPICAL

TYPICAL

NEW ENTRANCE ROAD

NEW ROAD 'A'

NE

W

S

ER

VI

CE

E

NT

RA

NC

E

NEW LOOP ROAD

MAINTENANCEBUILDING ROAD

J

OP

EN

ST

OR

AG

E

BU

ILD

IN

G

EN

CL

OS

ED

S

TO

RA

GE

BU

ILD

IN

G

FUEL

ISLAND

MAINTENANCE

M

ALTERNATE NO. 4

CR DC

SPB-48,50

SPB-48,50

SPB-46,48,50

REFER TO DRAWING E800,

DETAIL-4 FOR ONE-LINE DRAWING.

REFER TO DRAWING E800,

DETAIL-2 & 3 FOR ONE-LINE DRAWINGS.

REFER TO DRAWING E801,

DETAIL-2 FOR ONE-LINE DRAWINGS.

STAFF

FUTURE

TYPICAL

SCALE:

PARTIAL ELECTRICAL SITE PLAN

1" = 50'

G-E104

G-E103

00 50' 100'

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseStampConsultants

321 4 5 6 7 8 9 10

Sprinkler Status

INTEGRITY FEDERAL SERVICES

MARTINSBURG, WV

(304) 930-5779

HONOR ENGINEER COMPANY

HARRISBURG, PA

(717) 533-9077

MABBETT & ASSOCIATES, INC.

STONEHAM, MA

(781) 275-6050

PENNONI ASSOCIATES INC.

MECHANICSBURG, PA

(717) 620-5925

COMMANDER'S CONCEPTS COMMISSIONING

FOREST, VA

(713) 492-1922

AQUA ENGINEERING, INC

FORT COLLINS, CO

(970) 372-6104

BARBER & HOFFMAN, INC.

CRANBERRY TOWNSHIP, PA

(724) 741-0848

Architect/Engineer of Record

AE Works LTD.

418 Beaver Street Sewickley, PA Phone: 412-287-7333 www.aeworks.com

THE LA GROUP

SARATOGA SPRINGS, NY

(518) 587-8100 AE WORKS®

BI

M

C

FM

0-

IG

AP

/C

FM

0-

8/

2/

0:

:2

AM

INDIANTOWN GAP NATIONAL

CEMETERY

LEBANON COUNTY, PA

VA 813-028

2.15.2022 BK MM

PHASE 5 DEVELOPMENT

RFP DOCUMENTS

# Revisions Date

PARTIAL ELECTRICAL SITE PLAN

DRAWING KEYNOTES

1. NEW CONCRETE MANHOLE FOR POWER DISTRIBUTION.

2. NEW MEDIUM VOLTAGE FEEDER: 3 - #2 AWG (15KV) AND #6 AWG (600V)

IN 4" PVC CONDUIT AND SPARE 4" CONDUIT.

3. (2) - NEW BURIED SINGLE MODE FIBER OPTIC CABLES IN (2) - 4" PVC CONDUIT.

FIBER OPTIC CABLE TO BE ADJACENT TO MEDIUM VOLTAGE POWER

ALONG OLD CUMBERLAND ROAD TO REACH NEW CONSTRUCTION.

HORIZONTAL SEPARATION OF 24" BETWEEN POWER AND FIBER OPTIC CABLES.

4. NEW BURIED NON-METALLIC HANDHOLE - 18" X 30", FOR FIBER OPTIC CABLES.

5. BUILDING TRANSFORMER

6. BURIED 2" CONDUIT FOR SECURITY.

7. SECONDARY…