- Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington
About this file
This document is a Report of Inspection / Test for an Annual NFPA 25 and Annual NFPA 72 inspection conducted at the University of Washington Medical Center (UWMC) Montlake Tower building. The inspection was performed on the building's fire pump, which is a horizontal AC Fire Pump Systems model 393H8200 with a rated capacity of 750 GPM at 262 PSI. The inspection included testing of the fire pump, jockey pump, and associated electrical systems and controllers. All components were found to be functioning properly, and the pump performance met the manufacturer's certified curve within accepted tolerances.
The related state and local contract opportunity is for UW Medicine to establish a pool of qualified and experienced vendors to provide Automatic Fire Sprinkler System Testing & Inspection services at Harborview Medical Center (HMC), UWMC Montlake, and UWMC Northwest facilities and buildings. The contract will cover these fire sprinkler testing and inspection services on an as-needed basis across various jurisdictions in the state of Washington.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Report of Inspection / Test Annual NFPA 25, Annual NFPA 72
2024-01-06 Conducted by: Mike Sanders - Technician w Property Account
Medicine UWMC - Montlake Tower Unlversli of Washington Medi cal Center Built 2012
Building#: 3 1959 Ne aclflc Street 1959 NE Pacific St Seattle Washington 98195 LI IVF.R SI" Y ,,f WA II ING N.
Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
Report of Inspection/ Test for Asset - UWMC Fire Pump
Fire Pump Information EC02.03.05 EP 11
Property Owner UWMC
Owner's Address 1959 NE Pacific St
Property Name UWMC
Property Address 1959 NE Pacific St
Demand(s) of Fire protection systems supplied by pump: Hospital
Pump (Horizontal or Vertical): Horizontal
Pump Manufacturer A·C Fire Pump Systems
Shop/Serial Number 10058750101
Model 393H8200
Rated GPM 750
Rated Pressure 262
Rated 150 Pressure 225
Rated O Pressure 300
Rated RPM 3550
Suction Tank lfTank, size and height 33,000 gallons / 9' high
Driver, (electric or diesel engine) Eleq rlc
Engine Manufacturer WEG
Engine Shop/Serial Number 10021766
Engine Model 200360P3G4475
Rated Horsepower 200
Rated Speed 3550
Rated Voltage 460
Operating Voltage 380
Rated Amps 224
Phase Cycles 3
Service Factor 1.15
Controller Manufacturer Flrertrol
Copyright 2024 Inspect Point
2024-01~06 Conducted by: Mike Sanders - Technician w Property Account
Medicine UWMC • Montlake Tower Built 2012 Unlversli of Washington Medical Center Building#: 3 1959 Ne aciflc Street 1959 NE Pacific St Seattle Washington 98195 u IV ,RSITY uf WA SIII N(j O '• Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
Controller Shop/Serial Number 630832-01 RE
Controller Model FTA 1930AM200B
Jockey Pump Manufacturer Gould Pumps, ITT G&L Pumps
Jockey Pump Model 1 SSV Serles SHP
Jockey Punip Serial Number 2SVB1JSQ0
Jockey Controller Manufacturer Flrertrol
Jockey Controller Model FTA 1930-AM200B
Jockey Controller Serial Number 630832-01 RE
Transfer Switch Manufacturer Flrertrol
Transfer Switch Model FTA950-AM400B
Transfer Switch Serial Number 630832-01 RE
OWNER SECTION
Is there a Jockey Pump on system? 0 Yes Jockey Settings? (on/off) 0 Yes
D No D No
D NA D NA
Is the fire pump In service? 0 Yes Has the pump remained In service since the last 0 Yes
D No Inspection? D No
D NA D NA
Was the system (of which the pump Is a Pcart) free of 0 Yes actuation of devices or alarms since the ast Inspection? D No
D NA
FLUSH TEST
Suction plrlnfi was flushed at_ gpm? (see table 120
14.1.1 .1 o N PA20)
PEOPLE PRESENT
Was the pump UWMC representative present to witness 0 Yes Was the engine UWMC representative present to 0 Yes test? . D No witness test? D No
D NA D NA
Was the controller UWMC representative present to 0 Yes Was the transfers switch UWMC representative present 0 Yes witness test? D No to witness test? D No
D NA D NA
ELECTRIC WIRING
Were all electrical control panels ready for start-up? 0 Yes
D No
D NA
Page2 of21
2024-01-06 Conducted by: Mike Sanders·- Technician w Property Account
Medicine UWMC • Montlake Tower Built 2012 University of Washington Medical Center Building#: 3 1959 Ne Pacific Street 1959 NE Pacific St Seattle Washington 98195 U 1 IVEHS l 'fY uj' WA , II ING .
Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
FLOW TEST ·
Run the pump at no-load, rated load and peak load @ Yes Was the manufacturer's' certified pump test curve @ Yes (usually 150% of the rated load) conditions, For variable D No available for comparison to the acceptance test? D No speed drivers, run the test with pressure limiting control
D NA D NA "on" at 25, 50, 75, 100, 125, and 150% of rated load and then again rated speed w/ the pump Isolated from the fire protection system and the relle valve closed.
Was equipment and gauges calibrated? @ Yes Date of last calibration 1/6/2024 D No
D NA
If dry charge batteries were supplied, was electrolyte D Yes For each test record the following for each load @ Yes added a minimum of 24 hours before entne"Start and D No condition D No were the batteries given a conditioning c arge?
@ NA D NA
For electric motors operating at the rated voltage and . @ Yes For electric motors operating under varying voltage, was @ Yes frequency, Is the ampere demand on each dhase less D No the product of the actual voltage and current demand D No than or equal to the product of the full loa ampere
D NA on each ~hase less than or e~ual to the product of the D NA rating times the allowable service factor as stamped on rated ful load current times t e rated voltage times the the motor nameplate? allowable service factor?
For electric motors orreratlng under vatng voltage, did @ Yes Did engine-drive unit show no signs of overload or @ Yes the voltage sti with n the range of 95 to 110% of the D No stress? D No rated voltage urlng the test?
D NA D NA
Was the governor set to prof erly regulate the engine @ Yes Did the gear drive assembly operate without excessive @ Yes speed at rated pump speed D No objectionable noise, vibration, or heating? D No
D NA D NA
Was the unit started and brought up to rated speed @ Yes Did the ~ump perform equal to the manufacturer's @ Yes without Interruption under discharge conditions equal D No curve w thin the accuracy limits of the test equipment? D No to peak load? D NA D NA
Did the unadjusted performance discharge curve meet @ Yes Were there no vibrations that could damage any fire @ Yes .
or exceed the fire protection system demands? D No pump component? D No
D NA D NA
Did the pump perform at all conditions without @ Yes Have electric motor pumps pass the phase reversal test @ Yes objectionable overheating of any component? D No on normal and alternate (If provided) power? D No
D NA D NA
If a break tank Is provided, was the refill mechanism D Yes Record refill rate: N/A tested 5 times and did It operate correctly? D No
@ NA
For vertical turbine pumps taking the suction from wells, D Yes Record the pump system suction pressure. (psi) N/A Is the water level capable of being recorded? D No
@ NA
Record the pump system discharge pressure. (psi) N/A
TESTING
Electric pump started automatically? @ Yes Record pump starting pressure at the transfer switch. 265 D No (psi)
D NA
2024-01-06 Conducted by: Mike Sanders - Technician w Property Account
Medicine UWMC - Montlake Tower Built 2012 Un Ivers Ii of Washington Medical Center Building#: 3 · 1959 Ne aclflc Street 1959 NE Pacific St Seattle Washington 98195 u IVF.R SITY of W Sii lNGT 1 .
Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
Record the time the controller Is on the flrst step. 2 Record the time the motor accelerates to full speed. 4 (seconds) · (seconds)
Packing gland showing slight discharge? @ Yes Electric motor driven pump ran for 1 O mln7 @ Yes
D No D No
D NA D NA
Are all times and pressures and results acceptable? @ . Yes At the end of the 1 O minute test the Inboard Bearings 80 0 No temperature was
0 NA
At the end of the 1 O minute test the Inboard Packing Box 80 At the end of the 10 minute test the Outboard Bearings 92 temperature was: temperature was:
At the end of the 1 O minute test the Outboard Packing 112 Circulation and pressure relief valves operated properly @ Yes Box temperature was: during all flow tests? D No
D NA
No alarm Indicators or other visible abnormalities @ Yes Were Suction screens cleaned after flow7 @ Yes observed during no-flow test? D No D No
D NA D NA
Automatic transfer switch test: Power failure slnililated @ Yes Automatic transfer switch test: Connection made to @ Yes during peak now7 D No alternate source? D No
D NA D NA
Automatic transfer switch test: After termination of @ Yes All alarm conditions simulated? @ Yes simulated power failure did motor reconnect to source? D No D No
D NA D NA
All alarms operated? @ Yes
D No
D NA
INSPECTION
Pump house/room proper temperature? @ Yes Are suction, discharge and bypass valves open7 @ Yes
D No D No
D NA D NA
Is Piping free from leaks? @ Yes Suction and system pressure gauges normal? @ Yes
D No D No
D NA D NA
Suction reservoir, If provided, full7 @ Yes Waterflow test valves In closed position? @ Yes
D No D No
D NA D NA
Controller Indicating power on7 @ Yes Transfer switch Indicating normal situation? @ Yes
D No D No
D NA D NA
Isolation switch closed? @ Yes Pump In correct phase? @ Yes
D No D No
D NA D NA
Page 4of 21
2024-01-06 Conducted by: Mike Sanders - Technician w Property Account
Medicine UWMC - Montlake Tower Built 2012 University of Washington Medical Center · Building#: 3 1959 Ne Pacific Street 1959 NE Pacific St Seattle Washington 98195 U , IVF.R SITY 11f WA 11 INGTON.
Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
Circulation relief valve flowing water? 0 Yes
D No
D NA
MAINTENANCE
Cleaned or replacecl crank case breather In lubrication 0 Yes Cleaned water strainer In coolant system? 0 Yes systems? D No D No
D NA D NA
Insulation acceptable and fire hazards eliminated from 0 Yes Battery terminals clean and tight? D Yes exhaust system? D No D No
D NA 0 NA
Electrical systems free of wire chafing? 0 Yes Manual starting means on electrical systems operated @ Yes
D No and boxes, panels and cabinets cleaned? D No
D NA D NA
Antifreeze tested In coolant system? D Yes Flexible exhaust section acceptable? 0 Yes
D No D No
0 NA D NA
Changed pump bearing lubrication? D Yes Shaft end play acceptable? 0 Yes
D No D No
D NA D NA
Pressure gauges and sensors accurate? 0 Yes Coupling alignment acceptable? 0 Yes
D No D No
D NA D NA
Transmission coupling, rl1ht angle 3ear drive and 0 Yes Circuit breakers passed trip test? 0 Yes mechanical moving parts ubrlcate 7 D No D No
D NA D NA
Emergency manual starting means operated without D Yes Electrical connections secure? 0 Yes power? D No D No
0 NA D NA
Is the volt meter and ammeter accurate? 0 Yes Pressure switch settings calibrated? 0 Yes
D No D No
D NA D NA
Motor bearing greased? 0 Yes Fuel tank free of water and foreign material? 0 Yes
D No D No
D NA D NA
Fuel tank vents and overflow pipes free of obstructions? 0 Yes Fuel piping acceptable? 0 Yes
D No D No
D NA D NA
Antifreeze changed In coolant system? D Yes Heater exchange cleaned out? D Yes
D No D No
0 NA 0 NA
Ducts and louvers for combust.lon air okay? D Yes Exhaust system hanged In suf ports acceptable and D Yes
D No system free of back pressure D No
0 NA 0 NA
Page 5of 21
2024-01-06 Conducted by: Mike Sanders. Technician w Property Account ·
Medicine UWMC • Montlake Tower Built 2012 University of Washington Medical Center Building#: 3 1959 Ne Pacific Street 1959 NE Pacific St Seattle Washington 98195 U: IVF.R SITY il{ Wt\ SII ING N.
Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
Control and power wiring tight? 0 Yes No corrosion on circuit b_oards? 0 Yes
D No D No
D NA D NA
No cracked cable wire Insulation? 0 Yes No leaks In plumbing parts? 0 Yes
D No D No
D NA D NA
No sign or water on electrical parts? 0 Yes
D No
D NA
Report of Inspection/ Test
2024-01-06 Conducted by: Mike Sanders• Technician w Property Account
Medicine UWMC - Montlake Tower Built 2012 l,Jnlversli of Washington Medi cal Center Building#: 3 1959 Ne aclflc Street 1959 NE Pacific St .. Seattle Washington 98195 IVF. RS ITY II}' WA SII INGTO N Seattle WA 98195 206-598-6247 Print Date: 2024-03-19 sandem3@uw.edu
PERFORMANCE EC.02.03,05 EP 11
Rated% Driver speed: Total Flow Net Pressure: Discharge Pressure: Suction Pressure:
RPM PSI PSI PSI
0% 3586 0 294.0 297.0 3.0
50% o.o 0.0 0.0
100% 3551 750 250.0 252.0 2.0
150% 3547 1125 211.0 213.0 2.0
ELECTRIC MOTOR EC.02.03.05 EP 6 EP 11
L1 Voltage L1 Amperes L2 Voltage L2Amperes L3 Voltage L3Amperes
0% 472 166 472 176 473 168
50%
100% 470 207 471 211 472 200
150% 470 228 470 236 472 224
Pump Flow Detail Coefficient (same for all): N/A Nozzle/Orifice Size:· N/ A (Inches)
PITOT
1 2 ' 3 4 5 6
0% NIA NIA. NIA NIA NIA NIA
50% NIA NIA NIA NIA NIA NIA
100% NIA NIA NIA NIA NIA NIA
150% NIA NIA NIA NIA NIA NIA
FLOW
0% 0 NIA NIA NIA NIA NIA
50% NIA NIA NIA NIA NIA NIA
100% NIA NIA NIA NIA NIA NIA
150% NIA NIA NIA NIA NIA NIA
Page7 of21
~ 175 i 1so oi <?: 125
Report of Inspection /Test Annual NFPA 25, Annual NFPA 72
2024-01-06 Property UWMC - Montlake Tower Built 2012 Building#: 3 1959 NE Pacific St Seattle WA 98195 Print Date: 2024-03-19
Conducted by: Mike Sanders - Technician Account
University of Washington Medi cal Center 1959 Ne Pacific Street Seattle Washington 98195 206-598-6247 sandem3@uw.edu
-W Medicine
U IIVERS ITY ,,[ W \ 11 INGTO •
0L------------------------------------------- 0 10-0 200 300 400 500 600 ·
Flow(aPMJ
700 800
+ Curren! Performance Curve + Manufaclurlng Curve -+-- Allowable Min Pressure Curve
Copyright 2024 Inspect Point
900 1,000 1,100