21R1318_Notice7-Issued.pdf

PDF 381 KB Posted

Attached to
FY22 MCAF P-31054, PDI: MUNITIONS STORAGE IGLOOS IV, ANDERSEN AIR FORCE BASE, GUAM
Solicitation number
RFPN62742-21-R-1318
Issued by

About this file

This document contains questions and answers regarding solicitation number RFPN62742-21-R-1318 for the construction of sixteen munitions storage igloos, roadway reconstruction/resurfacing, associated utilities and security features, and incidental related work at Andersen Air Force Base, Guam. The Naval Facilities Engineering Command Pacific issued Notice No. 7 providing revisions to the solicitation, including removing the requirement for a neutral wire in the electrical design and specifying that the cost for backfilling any over-excavated areas shall be included under the line items for the base work and option items. Revised drawings will be forthcoming via amendment.

View the file

Other files

File Type Posted
21R1318_Notice11-Issued.pdf PDF
21R1318_Notice10-Issued.pdf PDF
21R1318_Amend0009-Issued.pdf PDF
21R1318_Notice9-Issued.pdf PDF
21R1318_Amend0007-Dwgs.pdf PDF
21R1318_Amend0008-Issued.pdf PDF
21R1318_Notice8-Issued.pdf PDF
21R1318_Amend0007-Issued.pdf PDF
21R1318_Amend0006-Issued.pdf PDF
21R1318_Notice6-Issued.pdf PDF
21R1318_Amend0005-Issued.pdf PDF
21R1318_Notice5-Issued.pdf PDF
21R1318_Notice4-Issued.pdf PDF
21R1318_Notice3-Issued.pdf PDF
P31054_SV-Sign-In_Completed_211117.pdf PDF
21R1318_Amend0004.pdf PDF
21R1318_Notice2-Issued.pdf PDF
21R1318_Notice1-Issued.pdf PDF
21R1318_Amend0003-Issued.pdf PDF
21R1318_Amend0002-Issued.pdf PDF
1_P31054_Specs-Signed-Rev1.pdf PDF
P31054_Amd0001-Attchs.pdf PDF
2_P31054_Dwgs-Signed.pdf PDF
RFPN6274221R1318.pdf PDF
21R1318_Amend0001-Issued.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC

258 MAKALAPA DR STE 100

PEARL HARBOR HI 96860-3134

RFP N62742-21-R-1318

Notice No. 7

20 Dec 2021

PRE-PROPOSAL QUESTIONS & ANSWERS

WON 1640581, FY22 MCAF PROJECT P-31054/AJJY073105P4, PDI: MUNITIONS

STORAGE IGLOOS IV,

ANDERSEN AIR FORCE BASE, GUAM

NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

RESPONSE REVISED FROM NOTICE NO. 6 DATED 14 DECEMBER 2021

9. Electrical Works, Drawing E-611 and E-612, Note #2 and Note #6

a. Note #2 of secondary one line diagram on Dwg E-611 calls for 3-phase wires and 1-ground wire without a neutral wire (3#1/0, 1#1/0GND) from panel MDP through EHHs whereas the grounding diagram on Dwg E-612 indicates neutral wire from Panel MDP through Panel ECB-MSI inside the Igloo Bldg. Please clarify.

b. Note #2 of secondary one line diagram on Dwg E-611 calls for 3-phase wires and 1-ground wire without a neutral wire (3#1/0, 1#1/0GND) whereas Note #6 calls for 4-wire and 1-ground wire (4#4, 1#4 GND) Please clarify.

ANSWER:

a. The neutral wire from Panel MDP to ECB-MSI inside the Igloo Bldg will be removed.

Revised drawing will be provided in a forthcoming amendment.

b. Note #6 will be revised to read as 1 1/2” RGS Conduit, 3#4, 1#4GND. Revised drawing will be provided in a forthcoming amendment.

RESPONSE FOR NOTICE NO. 7:

10. RFP –Price Proposal Schedule SF1442, page 3 of 5 SLIN 0001AB and SLIN 0001AC

These unit price line items were provided for costing the work related to over excavating into soil or limestone based upon the conditions provided on drawing S-011. Please indicate where cost for the material, labor, and equipment used to backfill these over excavated areas should be placed. The description of the item clearly directs proposers to price the over excavation, but no guidance is provided for the backfill of the over excavation. We suggest including the backfill in the referenced line items as well since any material removed will need to be replaced with select granular and the quantity to be backfilled will depend on the amount of over excavation completed.

ANSWER: Cost for the material, labor, and equipment used to backfill shall be placed under

SLIN 0001AA, CLIN 0002, and CLIN 0003 of the Price Proposal Schedule for work under CLIN 0001 (Base Item), CLIN 0002 (Option Item No. 1), and CLIN 0003 (Option Item No. 2), respectively.