This document provides answers to questions regarding solicitation number RFPN62742-21-R-1318 for the construction of sixteen munitions storage igloos, roadway reconstruction/resurfacing, associated utilities and security features, and incidental related work at Andersen Air Force Base in Guam. Specifically, the answers clarify that note 2 on drawing E-611 will be revised to remove the neutral wire from panel MDP to ECB-MSI inside the igloo building. Additionally, note 6 on drawing E-611 will be revised to specify three number four wires and one number four ground wire in three-inch rigid galvanized conduit between relevant structures. The revised drawings will be provided in a forthcoming amendment to the solicitation.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC
258 MAKALAPA DR STE 100
PEARL HARBOR HI 96860-3134
RFP N62742-21-R-1318
Notice No. 6
Notice No. 6 14 Dec 2021
PRE-PROPOSAL QUESTIONS & ANSWERS
RFP N62742-21-R-1318
WON 1640581, FY22 MCAF PROJECT P-31054/AJJY073105P4, PDI: MUNITIONS
STORAGE IGLOOS IV,
ANDERSEN AIR FORCE BASE, GUAM
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
9. Electrical Works, Drawing E-611 and E-612, Note #2 and Note #6
a. Note #2 of secondary one line diagram on Dwg E-611 calls for 3-phase wires and 1-ground wire without a neutral wire (3#1/0, 1#1/0GND) from panel MDP through EHHs whereas the grounding diagram on Dwg E-612 indicates neutral wire from Panel MDP through Panel ECB-MSI inside the Igloo Bldg. Please clarify.
b. Note #2 of secondary one line diagram on Dwg E-611 calls for 3-phase wires and 1-ground wire without a neutral wire (3#1/0, 1#1/0GND) whereas Note #6 calls for 4-wire and 1-ground wire (4#4, 1#4 GND) Please clarify.
ANSWER:
a. The neutral wire from Panel MDP to ECB-MSI inside the Igloo Bldg will be removed.
Revised drawing will be provided in a forthcoming amendment.
b. Note #6 will be revised to read as 3” RGS Conduit, 3#4, 1#4GND. Revised drawing will be provided in a forthcoming amendment.