RFP_250151_PS_idedits.doc

DOC document 52 KB Posted

Attached to
Digital Asset Management System
Solicitation number
250151
Issued by
Orange County, California

About this file

This is a time schedule memorandum for RFP 250151, "Digital Asset Management System," issued by the California Department of Transportation's LOSSAN (Los Angeles-San Diego-San Luis Obispo Rail Corridor) office in coordination with the Orange County Transportation Authority (OCTA). The RFP solicits proposals from qualified firms to provide a Digital Asset Management System for OCTA. The RFP was issued on December 15, 2025, with written questions from proposers due by December 17, 2025, and written responses to proposers due by December 22, 2025. Offers must be submitted by 2:00 p.m. on December 29, 2025, followed by a pre-evaluation meeting at 3:00 p.m. that same day. The evaluation committee will review proposals beginning January 6, 2025, with contract execution targeted for January 15, 2025. The contract term is one (1) year initial term.

The budget allocated for this effort is $24,150 for the one-year initial term. No information regarding set asides, incumbent contractors, renewal options, funding sources, or additional pricing terms is provided in the time schedule document.

View the file

Other files

File Type Posted
RFP_250151_PS.pdf PDF
RFP_250151__Exhibit_B_General_Provisions.pdf PDF
RFP_250151_Exhibit_A_SOW.pdf PDF
RFP_250151_PP.pdf PDF
RFP_250151_PS.doc DOC document
RFP_250151_PP.docx DOCX document
RFP_250151_Insurance_requirements.pdf PDF
RFP_250151_REQR000447_idedits.pdf PDF
RFP_250151_PP_idedits.docx DOCX document
RFP_250151_SOW_idedits.docx DOCX document
RFP_250151_ICE.pdf PDF
RFP_250151_REQR000447.pdf PDF
RFP_250151_FORM_700_Review.pdf PDF
RFP_250151_SOWV.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

December 15, 2025 To:

Marcus Garcia, Business Unit Analyst Senior, LOSSAN From:

Michael Cardozo, Senior Contract Administrator, CAMM Subject:

Time Schedule for Release, Selection and Award

RFP 250151, “Digital Asset Management System” Please review the time schedule for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.

December 15, 2025

Issue RFP

December 17, 2025

Written Questions Due From Proposers

December 22, 2025

Responses Due to Proposers

December 29, 2025

Offers Submitted 2:00 p.m.

December 29, 2025

Pre-Evaluation Meeting 3:00 p.m.

January 6, 2025

Evaluation Committee Reviews Proposals

January 15, 2025 Contract Executed

Project Manager Concurrence:

Marcus Garcia, Business Unit Analyst Senior, LOSSAN

Date Revised: 03/03/2010