This is an Independent Cost Estimate (ICE) document prepared by the Orange County Transportation Authority (LOSSAN Agency) for a Digital Asset Management (DAM) System procurement. The project involves the acquisition of a DAM system to support the agency's marketing program. The cost estimate was prepared by Marcus Garcia, Senior Business Unit Analyst, on May 29, 2025, with a contract option term date of May 29, 2025. The procurement is based on a Request for Proposals (RFP) process, with the related purchase requisition number REQR000447.
The total independent cost estimate is $24,150.00 for the one-year initial term. The cost breakdown includes a base annual license fee of $15,750.00 and implementation and onboarding services of $8,400.00. These figures are derived from quotes received through RFQ 4-2706 conducted in December 2024 and incorporate a five percent inflation rate adjustment to ensure realistic, risk-adjusted costs that align with current market pricing. The estimate encompasses all direct costs including licensing, implementation services, and system setup required to deploy the DAM system for the authority's marketing program operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP_250151_PS.pdf | ||
| RFP_250151__Exhibit_B_General_Provisions.pdf | ||
| RFP_250151_Exhibit_A_SOW.pdf | ||
| RFP_250151_PP.pdf | ||
| RFP_250151_Insurance_requirements.pdf | ||
| RFP_250151_PS.doc | DOC document | |
| RFP_250151_PP.docx | DOCX document | |
| RFP_250151_PS_idedits.doc | DOC document | |
| RFP_250151_REQR000447_idedits.pdf | ||
| RFP_250151_PP_idedits.docx | DOCX document | |
| RFP_250151_SOW_idedits.docx | DOCX document | |
| RFP_250151_SOWV.pdf | ||
| RFP_250151_REQR000447.pdf | ||
| RFP_250151_FORM_700_Review.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEPENDENT COST ESTIMATE (ICE)
FA-CAMM-006.docm (09/25/15) Page 1 of 3
INSTRUCTIONS
Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.
PART I – GENERAL INFORMATION
SHADED AREA FOR PROCUREMENT USE ONLY
Assigned Buyer No.:
D/M/WBE%:
Project Description: Request for Proposals for a Digital Asset Management (DAM) System for the LOSSAN Agency's Marketing Program
Purchase Requisition No.: REQR000447
New Contract / Procurement
Contract Amendment Current IFAS Printout Contract / PO No.:
(Required for Amendments)
Contract Task Order
Option Term
Date: 5/29/2025
Requestor: Marcus Garcia Senior Business Unit Analyst Phone Ext.: 5090 Name Title
Signature:
Cost Estimate: $ 24,150.00 (include shipping, handling and taxes, if applicable)
PART II – ESTIMATE GUIDE
Please substantiate the estimate using the following information.
Estimate Type Items to Include Where to Find Supporting Information
Services (Other than A&E)
1. Tasks you want done
2. Types of people needed (i.e., supervisor, administrative assistant, other)
3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Prevailing wage rate category applied
7. Profit / applied fee
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Estimate Guide Continued
FA-CAMM-006.docm (09/25/15) Page 2 of 3
Estimate Type Items to Include Where to Find Supporting Information
Architects, Engineers, Designers
1. Tasks you want done
2. Types of people needed (i.e., engineers, administrative assistant, other)
3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Profit / applied fee
7. Overhead rate (%)
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Goods/Equipment 1. Product needed
2. Quantity
3. Unit price
4. Markups, overhead, profit
5. Delivery schedule desired
6. Warranty
1. Vendor survey / market survey
2. Current or past contracts for the same or similar product
3. Historical price and cost data
4. Various published indices
Construction 1. Product needed
2. Labor (at a minimum use Davis Bacon)
3. Materials
4. Bonds
5. Insurance
6. Mobilization
7. Equipment
8. Markups, fringes, overheads, profit
9. Completion schedule
1. “Means Book”
2. “Blue Book”
3. Davis Bacon wage rates / prevailing wages
4. Current or past contracts for the same project
5. Historical price and cost data
Additional Information: The Independent Cost Estimate (ICE) for the Digital Asset Management (DAM) system includes a base annual license cost of $15,000, and implementation services of $8,000, based on quotes received through RFQ 4-2706 conducted in December 2024. The cost elements provided for a five percent inflation rate. Using these rates as the basis for the ICE ensures that realistic, risk-adjusted costs are proposed for a system that meets current and future needs while aligning with recent market pricing.
FA-CAMM-006.docm (09/25/15) Page 3 of 3
PART III – INDEPENDENT COST ESTIMATE
Using the information provided in Part II, prepare the ICE for your procurement.
Use any or all of the categories listed below.
Prepared By: Marcus Garcia, Senior Business Unit Analyst Date: 5/29/2025
Signature:
DESCRIPTION OF COST ELEMENTS
1. DIRECT LABOR
(List of Labor Categories)
Estimated Hours
Rate Per Hour ($)
Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00
Total Direct Labor: $ 0.00
2. OVERHEAD
Rate (%)
(use decimal input)
Total Labor ($)
Estimated Cost ($)
Total Est.
Cost ($)
% $ 0.00 $ 0.00 $ 0.00
3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
4. INFORMATION TECHNOLOGY SUPPORT Estimated Cost ($)
Total Est.
Cost ($)
Base Annual License $ 15,750.00
Total IT Support: $ 15,750.00
5. TRAVEL Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
6. SUBCONTRACTOR(S) / CONSULTANT(S) Estimated Cost ($)
Total Est.
Cost ($)
Total Subcontractor(s) / Consultant(s): $ 0.00
7. OTHER DIRECT COSTS Estimated Cost ($)
Total Est.
Cost ($)
Implementation and Onboarding Fee $ 8,400.00 $ 8,400.00
8. TOTAL ESTIMATED COST: $ 24,150.00