REQ_R001070_ICE.pdf
PDF 285 KB Posted
- Attached to
- Request for Quote (RFQ) - Bottled Water Delivery
- Solicitation number
- 250431
- Issued by
- Orange County, California
About this file
This is an Independent Cost Estimate (ICE) document prepared for the Orange County Transportation Authority's procurement of Bottled Drinking Water and Dispensers for the Santa Ana and Garden Grove Maintenance Departments. The procurement covers a two-year contract term from July 1, 2026 through June 30, 2028. The project scope includes eight water dispensers and monthly delivery of approximately 240 five-gallon water bottles, with all associated delivery, maintenance, bottle exchange, and related service costs included. The request for quote was issued with a deadline for written questions and clarifications by 4:00 p.m. on June 24, 2026, with responses to be provided via written addendum by June 25, 2026.
The independent cost estimate places the total contract value at $52,032.00, calculated as follows: eight coolers at $16 per month for 24 months equals $3,072, and water bottles at $8.50 each for 240 bottles per month for 24 months equals $48,960. The estimate was based on recent bid results for similar bottled drinking water service procurements and historical consumption levels at the respective maintenance departments. Award will be made to the lowest responsive and responsible firm on a lump-sum basis. Firms that do not bid on all line items in the pricing proposal shall be deemed non-responsive and ineligible for consideration. The successful firm must comply with all applicable Equal Employment Opportunity Laws and Regulations and certify non-subject status to Ukraine/Russia-related economic sanctions imposed by California or the United States Government.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEPENDENT COST ESTIMATE (ICE)
FA-CAMM-006.docm (09/25/15) Page 1 of 3
INSTRUCTIONS
Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.
PART I – GENERAL INFORMATION
Project Description: Bottled Drinking Water and Dispensers
SHADED AREA FOR PROCUREMENT USE ONLY
Assigned Buyer No.:
D/M/WBE%:
Purchase Requisition No.: R001070
New Contract / Procurement
Contract Amendment Current IFAS Printout Contract / PO No.:
(Required for Amendments)
Contract Task Order
Option Term
Date: 12/9/2025
Requestor: Christine Herrera Contracts Analyst Phone Ext.: 5485 Name Title
Signature:
Cost Estimate: $ 52,032.00 (include shipping, handling and taxes, if applicable)
PART II – ESTIMATE GUIDE
Please substantiate the estimate using the following information.
Estimate Type Items to Include Where to Find Supporting Information
Services (Other than A&E)
1. Tasks you want done
2. Types of people needed (i.e., supervisor, administrative assistant, other)
3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Prevailing wage rate category applied
7. Profit / applied fee
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Estimate Guide Continued
FA-CAMM-006.docm (09/25/15) Page 2 of 3
Estimate Type Items to Include Where to Find Supporting Information
Architects, Engineers, Designers
1. Tasks you want done
2. Types of people needed (i.e., engineers, administrative assistant, other)
3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Profit / applied fee
7. Overhead rate (%)
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Goods/Equipment 1. Product needed
2. Quantity
3. Unit price
4. Markups, overhead, profit
5. Delivery schedule desired
6. Warranty
1. Vendor survey / market survey
2. Current or past contracts for the same or similar product
3. Historical price and cost data
4. Various published indices
Construction 1. Product needed
2. Labor (at a minimum use Davis Bacon)
3. Materials
4. Bonds
5. Insurance
6. Mobilization
7. Equipment
8. Markups, fringes, overheads, profit
9. Completion schedule
1. “Means Book”
2. “Blue Book”
3. Davis Bacon wage rates / prevailing wages
4. Current or past contracts for the same project
5. Historical price and cost data
Additional Information: ICE for Bottled drinking water and dispensers for Santa Ana and Garden Grove Maintenance Departments is based on recent bid results for similar bottled drinking water service procurements and historical consumption levels at the Santa Ana and Garden Grove Maintenance Departments, the estimated cost for bottled drinking water and dispenser services is $52,032 for the two-year contract term.
The estimate is based on eight (8) water dispensers ($16 ea/mo) and an average usage of approximately 240 five-gallon water bottles per month ($8.50 ea) including all delivery, maintenance, bottle exchange, and related service costs.
Coolers: $16 x 8 = $128/mo x 24 months = $3,072, Water: $8.50 x 240 = $2,040 x 24 months = $48,960
TOTAL $52,032
FA-CAMM-006.docm (09/25/15) Page 3 of 3
PART III – INDEPENDENT COST ESTIMATE
Using the information provided in Part II, prepare the ICE for your procurement.
Use any or all of the categories listed below.
Prepared By: Christine Herrera Date: 12/9/2025
Signature:
DESCRIPTION OF COST ELEMENTS
1. DIRECT LABOR
(List of Labor Categories)
Estimated Hours
Rate Per Hour ($)
Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00
Total Direct Labor: $ 0.00
2. OVERHEAD
Rate (%)
(use decimal input)
Total Labor ($)
Estimated Cost ($)
Total Est.
Cost ($)
% $ 0.00 $ 0.00 $ 0.00
3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)
Total Est.
Cost ($)
Bottled drinking water and dispensers $ 52,032.00 $ 52,032.00
4. INFORMATION TECHNOLOGY SUPPORT Estimated Cost ($)
Total Est.
Cost ($)
Total IT Support: $ 0.00
5. TRAVEL Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
6. SUBCONTRACTOR(S) / CONSULTANT(S) Estimated Cost ($)
Total Est.
Cost ($)
Total Subcontractor(s) / Consultant(s): $ 0.00
7. OTHER DIRECT COSTS Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
8. TOTAL ESTIMATED COST: $ 52,032.00