This is a Question and Answer document from the Oregon Parks and Recreation Department (OPRD) regarding ITB #12279 for the Fort Stevens State Park Campground Improvements Project, addressing questions 76 through 82 as part of Addendum 4. The document clarifies that Bid Item #15 will be paid per square foot, not per ton. It references a utility responsibility matrix found in sheet E3.601-Schedules-Electrical within Attachment C Plans and Drawings Part A. The document also clarifies details about bus gutter installations at RV sites in Loops L and M, with specific reference to detail 1/E3.00 and drawings E3.001 and E3.002.
The document confirms that plumbers must be licensed for this project. The Q&A was prepared by Winona Butler, who serves as the Single Point of Contact Procurement and Contract Specialist. This addendum is dated February 18, 2025, and is associated with OregonBuys #S-63400-00011896.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLARIFICATIONS AND RESPONSE(S) TO QUESTIONS 76 through 82 OregonBuys # S-63400-00011896
ITB #12279
FORT STEVENS STATE PARK
CAMPGROUND IMPROVEMENTS PROJECT
FROM ADDENDUM 4 QUESTION AND ANSWER
76. QUESTION: Bid Item #15 Would we be getting payed by the square foot or Per Ton? The description seems to contradict?
OPRD RESPONSE: Winning Bidder will be paid Per square foot.
ADDITIONAL QUESTIONS RECEIVED
80. QUESTION: In response to questions 71 a utility responsibility matrix was supposed to be provided, however, it was not in addendum 4, is another addendum coming out with this matrix?
OPRD RESPONSE: This sheet E3.601-Schedules-Electrical is provided in “Attachment C Plans and Drawings Part A 2-6-2025 Addendum 3” (pdf 161 of 180).
81. QUESTION: The answer to question 60 contradicts the answer to question 58, can you please clarify?
OPRD RESPONSE: Refer to detail 1/E3.00 for buss gutter detail. The buss gutters will be installed at every RV site at the exterior portion of each Loop in L and M. There is a detail reference on drawings E3.001 and E3.002 and noted as “typical of all RV hookups”.
82. QUESTION: Does the Plumber need be licensed?
OPRD RESPONSE: Yes
Question and Answer document is prepared by:
Winona Butler, Single Point of Contact Procurement and Contract Specialist Winona.Butler@oprd.oregon.gov
| Question and Answer 02/18/2025 | ITB #12279 | |
| OregonBuys #S-63400-00011896 | Fort Stevens State Park Campground Improvements Project |