Bid Tabulation and Responsive PW PI.xlsx
XLSX spreadsheet 3 MB Posted
- Solicitation number
- S-63400-00011896
- Issued by
- Benton County, Oregon
About this file
This is a bid tabulation document from the Oregon Parks and Recreation Department for the Fort Stevens State Park Campground Improvements Project (ITB #12279, OregonBuys #S-63400-00011896). The project involves comprehensive campground improvements including utility upgrades, electrical retrofitting, grading improvements, and restroom facility replacement. The scope encompasses civil improvements (including 118,297 SF of asphalt paving, 20,793 LF of trench excavation), landscape improvements, electrical upgrades for multiple camping loops, and construction of a new restroom building. The bid opening occurred on February 20, 2025, at 2:00 PM, with substantial completion for the restroom building required by June 30, 2025, and overall project completion by December 30, 2025.
Four contractors submitted bids for the project: Goodfellow Bros CA, LLC ($9,999,619 with $411,500 in alternates), Tapani Inc. ($11,398,932 with $990,000 in alternates), West Coast Contractors ($15,855,226.45 with $1,064,055.53 in alternates), and Fulcrum Construction ($15,994,394 with $1,195,500 in alternates). The bid included detailed line-item pricing for 56 base components and two alternates: a 2,000 LF sanitary sewer pressure main replacement and a manhole pump station replacement. All bidders except Fulcrum Construction submitted complete documentation including bidder information, residency information, public works bond, COBID certification, responsibility inquiry responses, and required forms.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Tabulation
BID TABULATION
| Oregon Parks and Recreation Department |
| 725 Summer St. NE, Ste C |
| PROJECT TITLE: | Fort Stevens State Park Campground Improvements Project | |
| OregonBuys #: | S-63400-00011896 | |
| ITB #: | 12279 | |
| BID OPENING: | Time: 2:00 PM | Date:2/20/2025 |
| Bidder Name | Total Bid | Alternates |
| Tapani Inc | $ 11,398,932.00 | 990,000.00 |
| Goodfellow Bros CA, LLC | $ 9,999,619.00 | 411,500.00 |
| West Coast Contractors | $ 15,855,226.45 | 1,064,055.53 |
| Fulcrum Construction | $ 15,994,394.00 | 1,195,500.00 |
Goodfellow
| Goodfellow | |||||
| # | Line Items | Quantity | Unit | Unit Cost | Total Cost |
| 1 | Permits & Mobilization | 1 | LS | $ 525,000.00 | $ 529,000.00 |
| 2 | Erosion Control | 1 | LS | $ 125,500.00 | $ 125,500.00 |
| 3 | Tree Salvage, Removal, Protection and Signage | 1 | LS | $ 325,000.00 | $ 325,000.00 |
| 4 | Traffic Control | 1 | LS | $ 54,500.00 | $ 54,500.00 |
| - Civil Improvements - | |||||
| 5 | General Survey, Excavation & Earthwork | 1 | LS | $ 425,000.00 | $ 425,000.00 |
| 6 | Clearing and Grubbing | 38,219 | SF | $ 2.00 | $ 76,438.00 |
| 7 | Asphalt Demolition | 1 | LS | $ 125,800.00 | $ 125,800.00 |
| 8 | Concrete Demolition | 1 | LS | $ 3,000.00 | $ 3,000.00 |
| 9 | Utilities Salvage, Demolition and Site Protection | 1 | LS | $ 275,775.00 | $ 275,775.00 |
| 10 | Salvage Site Markers, Fire Pits, and Tables | 32 | Each | $ 900.00 | $ 28,800.00 |
| 11 | Trench Excavation and Backfill - Water, Electrical and Joint Trenching | 20,793 | LF | $ 35.00 | $ 727,755.00 |
| 12 | NOT USED | - | - | $ - 0 | |
| 13 | NOT USED | - | - | $ - 0 | |
| 14 | Base or Shoulder Rock | 1 | LS | $ 385,950.00 | $ 385,950.00 |
| 15 | Asphalt Paving | 118,297 | SF | $ 4.50 | $ 532,336.50 |
| 16 | Pavement Markings | 1,764 | SF | $ 5.00 | $ 8,820.00 |
| 17 | Wheelstops (OFCI) | 39 | Each | $ 160.00 | $ 6,240.00 |
| 18 | Signage | 4 | Each | $ 1,500.00 | $ 6,000.00 |
| 19 | Concrete Sidewalk Paving | 564 | SF | $ 30.00 | $ 16,920.00 |
| 20 | Concrete Vehicular Paving | 1,764 | SF | $ 60.00 | $ 105,840.00 |
| 21 | Concrete Pads for Utilities | 657 | SF | $ 40.00 | $ 26,280.00 |
| 22 | Aggregate Paving | 32,524 | SF | $ 8.00 | $ 260,192.00 |
| 23 | Site Drainage System | 1 | LS | $ 7,250.00 | $ 7,250.00 |
| 24 | Site Sewer System | 1 | LS | $ 140,525.00 | $ 140,525.00 |
| 25 | Gravity Sewerline - 4" | 6,260 | LF | $ 105.00 | $ 657,300.00 |
| 26 | Gravity Sewerline - 6" | 2,334 | LF | $ 115.00 | $ 268,410.00 |
| 27 | Gravity Sewerline - 8" | 2,854 | LF | $ 200.00 | $ 570,800.00 |
| 28 | Gravity Sewerline - 10" | 462 | LF | $ 285.00 | $ 131,670.00 |
| 29 | 48" Manhole | 33 | Each | $ 7,500.00 | $ 247,500.00 |
| 30 | Lift Station Retrofit | 1 | LS | $ 604,500.00 | $ 604,500.00 |
| 31 | Site Water System | 1 | LS | $ 268,500.00 | $ 268,500.00 |
| 32 | Waterline - 3/4" | 5,315 | LF | $ 15.00 | $ 79,725.00 |
| 33 | Waterline - 3" | 4,510 | LF | $ 28.00 | $ 126,280.00 |
| 34 | Propane Site Work | 1 | LS | $ 5,500.00 | $ 5,500.00 |
| - Landscape Improvements - | |||||
| 35 | Landscape - Soil Preparation | 1 | LS | $ 48,000.00 | $ 48,000.00 |
| 36 | Landscape - Seeding | 12,128 | SF | $ 0.25 | $ 3,032.00 |
| 37 | Landscape - Plants and Planting | 1 | LS | $ 75,000.00 | $ 75,000.00 |
| 38 | Landscape - Warranty and Maintenance | 1 | LS | $ 155,000.00 | $ 155,000.00 |
| 39 | Removable Bollards and Fire Pits (OFCI) | 1 | LS | $ 20,000.00 | $ 20,000.00 |
| 40 | Grading Monuments | 95 | Each | $ 300.00 | $ 28,500.00 |
| 41 | Site Bicycle Racks | 1 | Each | $ 4,000.00 | $ 4,000.00 |
| 42 | Wattle Screen | 158 | LF | $ 100.00 | $ 15,800.00 |
| 43 | Chain Link Fencing and Gates | 1 | LS | $ 11,000.00 | $ 11,000.00 |
| 44 | Boulder Retaining Wall | 140 | LF | $ 285.00 | $ 39,900.00 |
| 45 | Kiosk for Electrical Switchgear | 1 | LS | $ 10,000.00 | $ 10,000.00 |
| - Electrical Improvements - | |||||
| 46 | Loop C Electrical | 1 | LS | $ 19,000.00 | $ 19,000.00 |
| 47 | Loops L & M Electrical | 1 | LS | $ 1,200,000.00 | $ 1,200,000.00 |
| 48 | Loops N & O Electrical | 1 | LS | $ 78,000.00 | $ 78,000.00 |
| 49 | South Camp Lift Station Electrical | 1 | LS | $ 94,000.00 | $ 94,000.00 |
| - C Loop Restroom Building Site Improvements - | |||||
| 50 | Building Demolition | 1 | LS | $ 20,000.00 | $ 20,000.00 |
| 51 | Building Electrical Connection | 1 | LS | $ 3,000.00 | $ 3,000.00 |
| 52 | Restroom Building Foundation and Slab | 1 | LS | $ 295,035.00 | $ 295,035.00 |
| 53 | Restroom Building Construction | 1 | LS | $ 560,000.00 | $ 560,000.00 |
| 54 | Restroom Building Plumbing | 1 | LS | $ 44,685.00 | $ 44,685.00 |
| 55 | Restroom Building Electrical | 1 | LS | $ 42,560.00 | $ 42,560.00 |
| 56 | Restroom Building Mechanical | 1 | LS | $ 80,000.00 | $ 80,000.00 |
| TOTAL BID, BEFORE MARKUPS (Lines 1-56) | $ 9,999,619 | ||||
| 57 | N/A | ||||
| 58 | N/A |
| Bid Alternates | |||||
| 59 | Sanitary Sewer Pressure Main Replacement | 2,000 | LF | ERROR:#REF! | $ 290,000.00 |
| 60 | Manhole Pump Station Replacement | 1 | LS | ERROR:#REF! | $ 121,500.00 |
| TOTAL BID ALTERNATES, BEFORE MARKUPS (Lines 59-60) | $ 411,500 | ||||
| Attach. A | BIDDERS INFORMATION AND CERTIFICATIONS FORM | ||||
| Bidder Information | Yes | ||||
| Residency Information | Yes | ||||
| Public Works Bond | Yes | ||||
| Certified COBID FIRMS | Yes | ||||
| Responsibility Inquiry (Questions 1-8) | Yes | ||||
| Pay Equity Certificate | Yes | ||||
| Record of Satisfactory Performance | Yes | ||||
| Addenda Acknowledgement | Yes | ||||
| Bidder Signature | Yes | ||||
| Form A-2 | Pricing Form | Yes | |||
| Form A-3 | Bid Security Form | Yes | |||
| Form A-4 | First Tier Subcontractor Disclosure Form | Yes |
Tapani
| TAPANI Inc. | |||||
| # | Line Items | Quantity | Unit | Unit Cost | Total Cost |
| 1 | Permits & Mobilization | 1 | LS | $ 1,100,000.00 | $ 1,100,000.00 |
| 2 | Erosion Control | 1 | LS | $ 125,000.00 | $ 125,000.00 |
| 3 | Tree Salvage, Removal, Protection and Signage | 1 | LS | $ 300,000.00 | $ 300,000.00 |
| 4 | Traffic Control | 1 | LS | $ 20,000.00 | $ 20,000.00 |
| - Civil Improvements - | |||||
| 5 | General Survey, Excavation & Earthwork | 1 | LS | $ 200,000.00 | $ 200,000.00 |
| 6 | Clearing and Grubbing | 38,219 | SF | $ 5.00 | $ 191,095.00 |
| 7 | Asphalt Demolition | 1 | LS | $ 125,000.00 | $ 125,000.00 |
| 8 | Concrete Demolition | 1 | LS | $ 20,000.00 | $ 20,000.00 |
| 9 | Utilities Salvage, Demolition and Site Protection | 1 | LS | $ 300,000.00 | $ 300,000.00 |
| 10 | Salvage Site Markers, Fire Pits, and Tables | 32 | Each | $ 1,500.00 | $ 48,000.00 |
| 11 | Trench Excavation and Backfill - Water, Electrical and Joint Trenching | 20,793 | LF | 35 | $ 727,755.00 |
| 12 | NOT USED | - | - | - 0 | $ - 0 |
| 13 | NOT USED | - | - | - 0 | $ - 0 |
| 14 | Base or Shoulder Rock | 1 | LS | $ 700,000.00 | $ 700,000.00 |
| 15 | Asphalt Paving | 118,297 | SF | $ 6.00 | $ 709,782.00 |
| 16 | Pavement Markings | 1,764 | SF | $ 18.00 | $ 31,752.00 |
| 17 | Wheelstops (OFCI) | 39 | Each | $ 250.00 | $ 9,750.00 |
| 18 | Signage | 4 | Each | $ 1,500.00 | $ 6,000.00 |
| 19 | Concrete Sidewalk Paving | 564 | SF | $ 16.00 | $ 9,024.00 |
| 20 | Concrete Vehicular Paving | 1,764 | SF | $ 20.00 | $ 35,280.00 |
| 21 | Concrete Pads for Utilities | 657 | SF | $ 70.00 | $ 45,990.00 |
| 22 | Aggregate Paving | 32,524 | SF | $ 5.00 | $ 162,620.00 |
| 23 | Site Drainage System | 1 | LS | $ 20,000.00 | $ 20,000.00 |
| 24 | Site Sewer System | 1 | LS | $ 250,000.00 | $ 250,000.00 |
| 25 | Gravity Sewerline - 4" | 6,260 | LF | $ 100.00 | $ 626,000.00 |
| 26 | Gravity Sewerline - 6" | 2,334 | LF | $ 115.00 | $ 268,410.00 |
| 27 | Gravity Sewerline - 8" | 2,854 | LF | $ 265.00 | $ 756,310.00 |
| 28 | Gravity Sewerline - 10" | 462 | LF | $ 575.00 | $ 265,650.00 |
| 29 | 48" Manhole | 33 | Each | $ 10,500.00 | $ 346,500.00 |
| 30 | Lift Station Retrofit | 1 | LS | $ 500,000.00 | $ 500,000.00 |
| 31 | Site Water System | 1 | LS | $ 200,000.00 | $ 200,000.00 |
| 32 | Waterline - 3/4" | 5,315 | LF | $ 2.00 | $ 10,630.00 |
| 33 | Waterline - 3" | 4,510 | LF | $ 14.00 | $ 63,140.00 |
| 34 | Propane Site Work | 1 | LS | $ 7,500.00 | $ 7,500.00 |
| - Landscape Improvements - | |||||
| 35 | Landscape - Soil Preparation | 1 | LS | $ 7,000.00 | $ 7,000.00 |
| 36 | Landscape - Seeding | 12,128 | SF | $ 0.50 | $ 6,064.00 |
| 37 | Landscape - Plants and Planting | 1 | LS | $ 35,000.00 | $ 35,000.00 |
| 38 | Landscape - Warranty and Maintenance | 1 | LS | $ 25,000.00 | $ 25,000.00 |
| 39 | Removable Bollards and Fire Pits (OFCI) | 1 | LS | $ 45,000.00 | $ 45,000.00 |
| 40 | Grading Monuments | 95 | Each | $ 750.00 | $ 71,250.00 |
| 41 | Site Bicycle Racks | 1 | Each | $ 3,000.00 | $ 3,000.00 |
| 42 | Wattle Screen | 158 | LF | $ 85.00 | $ 13,430.00 |
| 43 | Chain Link Fencing and Gates | 1 | LS | $ 25,000.00 | $ 25,000.00 |
| 44 | Boulder Retaining Wall | 140 | LF | $ 300.00 | $ 42,000.00 |
| 45 | Kiosk for Electrical Switchgear | 1 | LS | $ 75,000.00 | $ 75,000.00 |
| - Electrical Improvements - | |||||
| 46 | Loop C Electrical | 1 | LS | $ 25,000.00 | $ 25,000.00 |
| 47 | Loops L & M Electrical | 1 | LS | $ 1,400,000.00 | $ 1,400,000.00 |
| 48 | Loops N & O Electrical | 1 | LS | $ 90,000.00 | $ 90,000.00 |
| 49 | South Camp Lift Station Electrical | 1 | LS | $ 100,000.00 | $ 100,000.00 |
| - C Loop Restroom Building Site Improvements - | |||||
| 50 | Building Demolition | 1 | LS | $ 50,000.00 | $ 50,000.00 |
| 51 | Building Electrical Connection | 1 | LS | $ 5,000.00 | $ 5,000.00 |
| 52 | Restroom Building Foundation and Slab | 1 | LS | $ 100,000.00 | $ 100,000.00 |
| 53 | Restroom Building Construction | 1 | LS | $ 750,000.00 | $ 750,000.00 |
| 54 | Restroom Building Plumbing | 1 | LS | $ 200,000.00 | $ 200,000.00 |
| 55 | Restroom Building Electrical | 1 | LS | $ 50,000.00 | $ 50,000.00 |
| 56 | Restroom Building Mechanical | 1 | LS | $ 100,000.00 | $ 100,000.00 |
| TOTAL BID, BEFORE MARKUPS (Lines 1-56) | $ 11,398,932 | ||||
| 57 | N/A | ||||
| 58 | N/A |
| Bid Alternates | |||||
| 59 | Sanitary Sewer Pressure Main Replacement | 2,000 | LF | $ 95.00 | $ 190,000.00 |
| 60 | Manhole Pump Station Replacement | 1 | LS | $ 800,000.00 | $ 800,000.00 |
| TOTAL BID ALTERNATES, BEFORE MARKUPS (Lines 59-60) | $ 990,000 | ||||
| Attach. A | BIDDERS INFORMATION AND CERTIFICATIONS FORM | ||||
| Bidder Information | Yes | ||||
| Residency Information | Yes | ||||
| Public Works Bond | Yes | ||||
| Certified COBID FIRMS | Yes | ||||
| Responsibility Inquiry (Questions 1-8) | Yes | ||||
| Pay Equity Certificate | Yes | ||||
| Record of Satisfactory Performance | Yes | ||||
| Addenda Acknowledgement | Yes | ||||
| Bidder Signature | Yes | ||||
| Form A-2 | Pricing Form | Yes | |||
| Form A-3 | Bid Security Form | Yes | |||
| Form A-4 | First Tier Subcontractor Disclosure Form | Yes |
West Coast West Coast Contractors
| Attach. A | BIDDERS INFORMATION AND CERTIFICATIONS FORM |
| Bidder Information | |
| Residency Information | |
| Public Works Bond | |
| Certified COBID FIRMS | |
| Responsibility Inquiry (Questions 1-8) | |
| Pay Equity Certificate | |
| Record of Satisfactory Performance | |
| Addenda Acknowledgement | |
| Bidder Signature | |
| Form A-2 | Pricing Form |
| Form A-3 | Bid Security Form |
| Form A-4 | First Tier Subcontractor Disclosure Form |
| TOTAL BID, BEFORE MARKUPS (Lines 1-56) | $15,855,226.45 | |
| 57 | N/A | |
| 58 | N/A |
| Bid Alternates | |||||
| 59 | Sanitarv Sewer Pressure Main Replacement | 2,000 | LF | $184.99 | $369,980.00 |
| 60 | IManhole Pump Station Replacement | 1 | LS | $694,075.53 | 694,075.53 |
| TOTAL BID ALTERNATES, BEFORE MARKUPS (Lines 59-60) | $1,064,055.53 | ||||
| Attach. A | BIDDERS INFORMATION AND CERTIFICATIONS FORM | ||||
| Bidder Information | Yes | ||||
| Residency Information | Yes | ||||
| Public Works Bond | Yes | ||||
| Certified COBID FIRMS | Yes | ||||
| Responsibility Inquiry (Questions 1-8) | Yes | ||||
| Pay Equity Certificate | Yes | ||||
| Record of Satisfactory Performance | Yes | ||||
| Addenda Acknowledgement | Yes | ||||
| Bidder Signature | Yes | ||||
| Form A-2 | Pricing Form | Yes | |||
| Form A-3 | Bid Security Form | Yes | |||
| Form A-4 | First Tier Subcontractor Disclosure Form | Yes |
Fulcrum Fulcrum Construction and Building Services LLC
| Attach. A | BIDDERS INFORMATION AND CERTIFICATIONS FORM | |
| Bidder Information | Yes | |
| Residency Information | Yes | |
| Public Works Bond | Yes | |
| Certified COBID FIRMS | Yes | |
| Responsibility Inquiry (Questions 1-8) | Yes | |
| Pay Equity Certificate | N/A | |
| Record of Satisfactory Performance | Yes | |
| Addenda Acknowledgement | Yes | |
| Bidder Signature | Yes | |
| Form A-2 | Pricing Form | Yes |
| Form A-3 | Bid Security Form | Yes |
| Form A-4 | First Tier Subcontractor Disclosure Form | No |
Sheet1
Sheet3 image1.jpeg image2.emf image3.png image4.png image5.png
File details come from the government source that posted it. Updated .