Pre-Proposal Design Meeting Summary for Veterans Memorial Boulevard Phase II
This document is a presentation from the Transportation Engineering Division of Collier County, Florida's Department of Transportation, detailing the pre-proposal design meeting for Veterans Memorial Boulevard Phase II (RPS Solicitation 26-8668). The project involves design services for a 1.23-mile roadway extension in Naples, Florida, connecting Livingston Road to U.S. 41 (Tamiami Trail). The project is divided into two phases: Phase 2A (approximately 0.5 miles from Aubrey Rogers High School to Railroad Property), which is being developed by Pulte Homes under an Imperial Lakes Developer Agreement with design underway and construction scheduled to start in 2027; and Phase 2B (approximately 0.8 miles from the Railroad Property to U.S. 41), which requires County-contracted design and permitting services. The pre-proposal meeting was conducted to discuss project scope, updated project limits, and permitting requirements. Proposals for design services are due August 7, 2026 at 3:00 p.m., with a pre-proposal conference scheduled for July 17, 2026 at 1:30 p.m. The anticipated design phase duration is 550 calendar days from Notice to Proceed, with a total contract schedule of 1,490 calendar days.
Phase 2B permitting is currently being obtained by County consultant Kimley-Horn and includes Environmental Resource Permit (ERP) applications to the South Florida Water Management District and Army Corps of Engineers for the entire project limits. Additional permit modifications are required for the Mercedes Benz site and Triangle Parcel, along with mitigation for Conservation Easement impacts requiring an alternative mitigation site. An Intersection Control Evaluation is being performed by Collier County at the U.S. 41/VMB intersection, with an interim emergency signal planned at North Collier Fire Station #49. The project schedule shows permitting running from July 2026 through July 2027, with the procurement phase from July 2026 through March 2027, and the combined design, permitting, and construction phase from April 2027 through November 2030. Evaluation criteria for proposals include Ability of Professional Personnel (20 points), Certified Woman/Minority Business Enterprise status (5 points), Past Performance (25 points), Project Approach and Willingness to Meet Time and Budget Requirements (20 points), Location (10 points), and Recent, Current, and Projected Workloads (20 points).
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Meeting
Design Services for Veterans Memorial Blvd. Phase II
RPS Solicitation 26-8668
VMB Phase II Transportation Engineering Division
Transportation Management Services Department Transportation Engineering Division
Agenda VMB Phase II Project Overview and Updated Project Limits Permitting/Mitigation/Right of Way (ROW) Schedule update Questions
Project Limits
PHASE 2A
PHASE 2B
Aubrey Rogers HS RR Property
VMB Phase II Transportation Engineering Division
Updated Project Limits VMB Phase II
Phase 1 Livingston Road to Aubrey Rogers High School (East Entrance) Completed in 2023 Phase 2A Aubrey Rogers High School (terminus of Phase 1) to Railroad Property Approximately 0.5 miles Imperial Lakes Developer Agreement (Pulte Homes) – Developer will complete design, permitting, mitigation, and construction.
Schedule – Design is underway, Construction to start in 2027.
Phase 2B East end of Railroad Property to US 41 (Tamiami Trail) Approximately 0.8 miles Permitting currently being obtained by County Consultant (Kimley-Horn) Intersection Control Evaluation (ICE) currently being performed by Collier County at US 41/VMB Intersection North Collier Fire Station #49 – Interim Emergency Signal at US41/VMB
Permitting/ROW VMB Phase II
Permitting:
Environmental impacts will require permits from:
the South Florida Water Management District (SFWMD) - Submitted Army Corps of Engineers (or FDEP) - Submitted The County has contracted Kimley-Horn to obtain these permits and provide mitigation-related services for Phase 2B (Kimley-Horn is also providing permitting services for the Developer constructing Phase 2A).
Phase 2B permits in process:
ERP entire project limits (grandfathering granted under former permitting rules) Mercedes Benz Permit ERP Modification Triangle Parcel Permit ERP Modification Conservation Easement Impact (Alternative Site required to mitigate)
Transportation Engineering Division
Project Schedule
| Activity | Start | Finish | 2026 | 2027 | 2028 | 2029 | ||||||||||||
| Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | |||
| Permitting Process | July 25 | July 27 | ||||||||||||||||
| Procurement Phase | Jul 26 | Mar 27 | ||||||||||||||||
| Design, Permitting & Construction | Apr 27 | Nov 30 |