This is a Pre-Bid Conference Response Form for the Maryland Aviation Administration's Invitation for Bids (IFB) MAA-CO-26-022, Wilson Point Stormwater Management Improvements at Martin State Airport. The project involves construction of a storm drain conveyance system with a new outfall into Dark Head Cove, including 30-inch, 48-inch, and 38-inch by 60-inch wide elliptical reinforced concrete pipe, inlets, precast manholes, and bulkhead outfall installation. The scope encompasses approximately 2,315 linear feet of reinforced concrete pipe in various diameters, site stabilization and restoration across 11,640 square yards, pavement rehabilitation, erosion and sediment control, and tree clearing across 57 bid line items. A mandatory pre-bid conference was held July 22, 2026 via Microsoft Teams at 11:00 a.m., with RSVP required by 11:00 a.m. on July 21, 2026. Sealed bids are due August 20, 2026 at 1:00 p.m. via eMaryland Marketplace Advantage. No site inspection will be conducted. The project is structured in seven phases with Phase 1 anticipated to begin July 2027, with a total contract duration of 220 calendar days and completion extended through summer 2028 due to winter/spring utility relocation shutdowns.
The minimum contract value is $419,000, comprising fixed allowances of $314,000 for miscellaneous construction, $100,000 for utility relocation, and $5,000 for security services. This is a federally funded project with no set-asides or Disadvantaged Business Enterprise participation goals. Federal compliance requirements include Davis-Bacon prevailing wage rates, FHWA Form 1273 contract provisions, Buy American certification, 50% contractor self-performance requirement, and performance and payment bonds equal to contract price. Bid bonds of 5% are required for bids exceeding $100,000. The contract will be awarded to the lowest responsive and responsible bidder, subject to Maryland Board of Public Works approval. Liquidated damages are assessed at $1,800 per calendar day for failure to meet phase or overall project completion deadlines. Designated subcontractors are required for certain systems including Building Automation, paging, security access, video surveillance, fire alarm, and gate security systems.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Conference Response Form Solicitation Number MAA-CO-26-022 Wilson Point Stormwater Management Improvements at Martin State Airport A Pre-Bid conference will be held via Microsoft Teams at 11:00: a.m. on July 22, 2026 for interested Offerors.
Please return this form by 11:00 a.m. July 21,2026, advising whether or not your firm plans to attend. The below information will be posted in an upcoming Addendum as an interested party. The completed form should be returned via e-mail to the Procurement Officer at jreese2@bwiairport.com Please indicate:
Yes, the following representatives will be in attendance.
Attendees 1.
2.
3.
4.
No, we will not be in attendance.
Company Name:
Bidding as a Prime or Sub:
Printed Name:
E-Mail Address:
Date:
File details come from the government source that posted it. Updated .