Addendum No. 2.pdf
PDF 6 MB Posted
- Solicitation number
- BPM058000
- Issued by
- Maryland
About this file
File Summary
This Addendum No. 2 document is issued by the Maryland Aviation Administration (MAA) Office of Procurement and Materials Management for Contract No. MAA-CO-26-022, Wilson Point Road Stormwater Management Improvements at Martin State Airport, a federally funded project. The project involves constructing a new storm drain outfall alignment to Dark Head Cove, removing a damaged 18-inch corrugated metal pipe, and repairing an existing 18-inch reinforced concrete pipe tie-in across MAA property, State Highway Administration property, and Lockheed Martin property. The scope includes stormwater conveyance piping (ranging from 8-inch to 48-inch diameter reinforced concrete pipe and 38-inch by 60-inch horizontal elliptical pipe), precast concrete manholes, stormwater inlets, erosion and sediment control measures, soil stockpiling and testing, and a soil and groundwater management plan for the Lockheed Martin property. A pre-bid conference was held on July 22, 2026, with the original bid due date of August 13, 2026, revised to August 20, 2026, at 1:00 p.m. local time via eMaryland Marketplace Advantage. The project is planned for completion in seven phases with an anticipated construction start date in July 2027, subject to coordination with the Baltimore County water and sewer project.
The contract includes three contingency allowances totaling $419,000: $314,000 for miscellaneous construction, $100,000 for utility relocation, and $5,000 for security services. The project has a 0% Disadvantaged Business Enterprise (DBE) goal and no Minority Business Enterprise (MBE) participation requirements due to federal funding. Contractor overhead and profit for allowance work shall not exceed 3%. Multiple plan holders and prospective bidders, including Bourn Environmental LLC, Triangle Contracting, DXI Construction, Allan Myers, DSM Contracting, Brawner Builders Inc., Kibler Construction, and Urban N Zinc Contractor Inc., obtained bid documents. The addendum incorporates revised technical specifications for Section 01 2100 (Allowances), Section 33 4200 (Stormwater Conveyance), Item 51 0070 (Excavation and Embankment), and Item 51 0360 (Sign Supports), along with updated bid forms and contract drawings. Special provisions address phasing requirements, AOA security training for workers, Phase 2 scheduling coordination with the county, environmental compliance with the Lockheed Martin Soil and Groundwater Management Plan, and OSHA Level D protection standards for potential contaminated soil exposure unless contamination is discovered.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 2
MAA-CO-26-022 Federal Funded Addendum No. 2
Wilson Point Road SWM Improvements
August 10, 2026 at Martin Airport
MARYLAND AVIATION ADMINISTRATION
OFFICE OF PROCUREMENT AND MATERIALS MANAGEMENT
ADDENDUM No. 2 to
TECHNICAL PROVISIONS AND DRAWINGS
for
CONTRACT NO.: MAA-CO-26-022
WILSON POINT ROAD STORMWATER MANAGEMENT IMPROVEMENTS
AT
MARTIN STATE AIRPORT
(advertised) July 16, 2026
IMPORTANT: Bidders must acknowledge receipt of this Addendum. Please sign and date the attached “Acknowledgement of Receipt”. All documents must be fully executed at the time the
Bid is submitted. All information contained herein shall form a part of this Addendum.
The MAA encourages Contractors to return the Addendum Acknowledgement attached to this
Addendum No. 2.
This Addendum forms a part of the Contract Documents and modifies the original Bidding
Documents advertised July 16, 2026.
This Addendum No. 2 consists of 7 pages and the following attachments and revisions:
1. Attachment No. 1 – Pre-Bid Conference Transcript
2. Attachment No. 2 – Pre-Bid Conference RSVP List
3. Attachment No. 3 – Pre-Bid Conference Attendance Sheet
4. Attachment No. 4 – Plan Holders/Bidders list
5. Attachment No. 5 – Technical Specifications
6. Attachment No. 6 – Technical Provisions Part IV – Section 7 – Bid Proposal – Bid
Tabulation Forms
7. Attachment No. 7 – Addendum No. 2 Contract Drawings Revisions (Will be sent to Plan
Holders only under separate cover)
8. Attachment No. 8 – Addendum No. 2 Acknowledgement Form
Addendum Date: August 10, 2026
Bid Due Date: August 13, 2026; 1:00:00 p.m. local time
Revised Bid Due Date: August 20, 2026; 1:00:00 p.m. local time
Bids Delivered to: Submitted on eMaryland Marketplace Advantage (eMAA)
Bid Opening Time: August 13, 2026; 1:05:00 p.m. local time
Revised Bid Opening Date: August 20, 2026; 1:00:00 p.m. local time
RESPONSE TO CONTRACTORS’ QUESTION
DXI Construction
1) Please clarify in further detail what is expected to be included under Bid Item No.1 soil stockpiling and testing for MAA Property?
Response: Bid Item 02 2200.1, Soil Stockpiling and Testing for MAA Property, shall include all labor, materials, equipment, transportation, handling, sampling, testing, reporting, and incidentals necessary to characterize and manage excavated soil designated for potential reuse on MAA property. This item shall include the establishment, maintenance, protection, and removal of stockpile areas; erosion and sediment control measures associated with the stockpile; collection and laboratory analysis of soil samples;
coordination of testing; and preparation and submission of required documentation. The
Contractor shall include all activities necessary to determine the suitability of the material for reuse on MAA property in accordance with the Contract Documents.
2) Please clarify in further detail what is expected to be included under Bid item No. 3 Soil and Ground Water Management plan for Lockheed Martin Property?
Response: Bid Item 02 2200.3, Soil and Groundwater Management Plan for Lockheed
Martin Property, shall include all labor, materials, equipment, supervision, documentation, coordination, monitoring, and incidentals necessary to implement and comply with the requirements of the attached Lockheed Martin Soil and Groundwater Management Plan during construction. This includes, but is not limited to, management, handling, segregation, stockpiling, characterization, transportation, tracking, and disposition of soil and groundwater encountered within the limits of the Lockheed Martin property;
implementation of applicable health and safety requirements; environmental monitoring;
sampling and testing required by the Management Plan; recordkeeping; reporting; and coordination with the Owner, Engineer, and regulatory agencies as required. The attached
Soil and Groundwater Management Plan is provided as part of the Contract Documents and should be used by the Contractor to determine the full scope of work associated with this pay item.
3) Please change Bid item No.2 Contingent Item – Contaminated Soil Removal to a per load item.
Response: A per-load item can introduce significant variability because truck capacities differ and loads may not be full. A cubic yard unit provides a consistent basis for measurement regardless of truck size or load configuration and allows for equitable comparison of bids.
Urban N. Zink Contractor, Inc.
4) Please confirm that the project will be completed in the 7 phases as shown on the plans.
Response: Per Contract Drawings G201 and G202, the project is to be completed in 7 phases with a winter/spring shutdown.
5) Please confirm the anticipated start date for this project.
Response: The anticipated construction contract start date is expected in July 2027, as shown on the conceptual schedule on sheet G202.
6) Please confirm the duration for Phase 1 of the project.
Response: Per Contract Drawings G201 and G202, Phase 1 duration is 45 consecutive calendar days.
7) Please confirm that Phases 2 through 7 starts in Summer of 2028 as stated on the bid documents.
Response: Correct, the phases shown on Sheet G202 depict the conceptual construction schedule which was developed to coincide with the County water and sewer project.
Schedule is subject to change pending coordination with the County water and sewer project.
8) Will the existing topsoil need to be screened?
Response: The Contract Documents do not require screening of existing topsoil. Salvaged topsoil shall comply with the requirements of Section 329115X, including removal of vegetation, roots, debris, stones, and other unsuitable materials, and shall meet the specified topsoil quality requirements. The Contractor may screen the topsoil at their discretion if necessary to achieve compliance with the specification.
9) Will the existing topsoil need to be composted?
Response: The Contract Documents do not require composting of existing or salvaged topsoil. Salvaged topsoil shall comply with the requirements of Section 329115X and be free of unsuitable materials as specified. The Contractor may elect to incorporate compost or other soil amendments at its discretion if necessary to achieve the specified establishment of vegetation.
10) Please confirm that the DBE and MBE requirements for this project is 0%.
Response: The DBE goal for this solicitation is 0%. There are no MBE requirements for this solicitation.
11) Will the staging area require a stone base for the laydown area? If so, what depth?
Response: No stone base for the staging area will be required, as this area consists of aged asphalt and/or gravel surface.
12) Will temporary fence be required around the contractor staging area?
Response: Temporary fence around the contractor staging area is not a contract requirement, as this area is already within a fenced area. If the Contractor wants additional fencing, it will be at the contractor's cost.
13) Will caulking / sealant be required for the concrete work on this project?
Response: Caulking/sealant is not required for the concrete work around the bulkhead.
14) See sheet C511, will steel sheet piles be required or can a coffer dam be installed?
Response: The coffer dam design (using sheet piles or other method) is delegated to the
Contractor. Sheet piles for use as the coffer dam are not required by the Contract
Documents. The Contractor shall be responsible for design using any material (sheet pile or otherwise), including all associated exploratory surveys, geotechnical investigations and additional permitting if needed.
15) See unit price item 36, will an arborist be required for this work?
Response: An arborist will not be required for tree/vegetation clearing and grubbing.
16) See unit price item 57, what items fall under Temporary Construction Items?
Response: This pay item is intended to cover temporary construction-related items and activities that are necessary to complete the work but are not specifically identified for payment under another contract pay item. Contractors should refer to Section 01 0004X –
Temporary Construction Items for a complete description of the requirements.
17) See unit price item 60, what items fall under Miscellaneous Construction Allowance?
Response: The Miscellaneous Construction Allowance is intended to provide funding for unforeseen or indeterminate work that may be identified during construction and authorized by the MAA. This allowance may be used for work that is not reasonably quantifiable during design and is not specifically included in another contract pay item. Expenditures under this allowance shall be performed only when authorized by the MAA and shall be supported in accordance with the Contract Documents.
18) See unit price item 62, what items fall under Utility Relocation Allowance?
Response: The Utility Relocation Allowance may be used for owner-directed utility relocation or utility conflict resolution activities, including utility adjustments, protection in place, temporary utility support, emergency repairs, coordination with utility owners, and other unforeseen utility-related work that is not specifically included under another contract pay item. The allowance is intended to address utility conditions encountered during construction that could not be reasonably determined during design. Work performed under this allowance shall require prior authorization by the MAA and/or
Engineer.
19) See Sheet C123, please confirm if the asphalt / gravel area will need to be restored with asphalt once the RCP storm line is installed.
Response: The surface material can be replaced with graded aggregate base material in this location.
20) Please confirm if our crews will be required to wear hazmat suits / masks to handle the potential contaminated soils for this project.
Response: The staff would not be required to wear hazmat suits unless they were to find contaminated soils through visual or olfactory identification of contamination. OSHA
Level D worker protection would be the standard unless contamination is discovered.
Level D protection includes standard construction worker clothing:
• Coveralls (Work Uniform)
• Safety boots/shoes
• Safety glasses or chemical splash goggles
• Hard Hat
No respiratory protection is required under Level D and there is no chemical protective suit.
The Contractor will need to follow all of the environmental covenants for this property.
The covenants are identified in the Lockheed Martin Soil and Groundwater Management
Plan for Blocks A, B, D, D Panhandle, F, G and H.
ADDENDUM TO TECHNICAL PROVISIONS
Part I General Information:
No changes.
Part II Technical Specifications:
Section 01 2100 Allowances (Reissued Specification)
1. REPLACE Section 01 2100 specification in its entirety with revised Section 01 2100 specification, attached to this addendum (Attachment No. 5)
a. Replaced miscellaneous construction allowance amount
Section 33 4200 Stormwater Conveyance (Reissued Specification)
1. REPLACE Section 33 4200 specification in its entirety with revised Section 33 4200
a. Added section relevant Elliptical Pipe ASTM C507
b. Replaced Elliptical Pipe Class B with Elliptical Pipe Class C in the pay items
Item 51 0070 Excavation and Embankment (Reissued Specification)
1. REPLACE Item 51 0070 specification in its entirety with revised Item 51 0070
a. Added geotextile
Item 51 0360 Sign Supports (Reissued Specification)
1. REPLACE Item 51 0360 specification in its entirety with revised Item 51 0360
a. Added requirement for small structure sign
b. Added new pay item for small structure sign
Part III Wage Rates:
No changes.
Part IV Bid Forms:
1. REPLACE Section 7 – Bid Proposal, pages BF-1 – BF-8, with revised Section 7 – Bid
Proposal, dated Addendum No. 2 – August 10, 2026 pages BF-1 – BF-8 attached to this addendum and see electronic file. (Attachment No. 6)
ADDENDUM TO CONTRACT DRAWINGS
General Note: Sheets with changes listed below and not reissued with this Addendum will be issued with the Conformed Documents to the successful bidder.
Sheet No. G001 – Index of Drawings
1. REVISE the Index of Drawings to add new sheet C126 .
Sheet No. C124 – Roadway Crossing Storm Drain Plan (Reissued Sheet)
1. REPLACE sheet with revised C124 sheet dated 08/10/26 attached to this addendum
(Attachment No. 7)
Sheet No. C125 – Roadway Crossing Notes, Details And Cross Sections (Reissued Sheet)
1. REPLACE sheet with revised C125 sheet dated 08/10/26 attached to this addendum
(Attachment No. 7).
Sheet No. C126 – Roadway Crossing Notes and Details (New Sheet)
1. ADD new sheet C126 dated 08/10/26 attached to this addendum (Attachment No. 7)
Sheet No. C201 – Storm Drain Profiles - 1 (Reissued Sheet)
1. REPLACE sheet with revised C201 sheet dated 08/10/26 attached to this addendum
Sheet No. C401 – Erosion and Sediment Control Plan – 1 (Reissued Sheet)
1. REPLACE sheet with revised C401 sheet dated 08/10/26 attached to this addendum
Sheet No. C402 – Erosion and Sediment Control Plan – 2 (Reissued Sheet)
1. REPLACE sheet with revised C402 sheet dated 08/10/26 attached to this addendum
Sheet No. C403 – Erosion and Sediment Control Plan – 3 (Reissued Sheet)
1. REPLACE sheet with revised C403 sheet dated 08/10/26 attached to this addendum
Sheet No. C505 – Vegetative Stabilization Notes - 3 (Reissued Sheet)
1. REPLACE sheet with revised C505 sheet dated 08/10/26 attached to this addendum
Sheet No. C507 – Erosion and Sediment Control Details – 2 (Reissued Sheet)
1. REPLACE sheet with revised C507 sheet dated 08/10/26 attached to this addendum
Sheet No. C521 – Drainage Details - 1 (Reissued Sheet)
1. REPLACE sheet with revised C521 sheet dated 08/10/26 attached to this addendum
END OF ADDENDUM No. 2
- 1 -
MAA-CO-26-022 Wilson Point Road Stormwater Management Improvements at Martin State
Airport
Pre-Proposal Conference
Date: July 22, 2026
Time: 11:00AM (EST)
Place: Virtual via Microsoft Teams
Presenters:
Joe Reese – Procurement Officer II, Office of Procurement and Materials Management
Harold Fowler – Chief, Airport Operations and Management and Maintenance, Martin State Airport
Joshua Steininger – Michael Baker International
Sheldon Reynolds – Compliance Officer, Office of Civil Rights and Compliance
Attendees:
Candace Long – Michael Baker International
Chris Nevins – Triangle Contracting
Christa Marcotte – Procurement Officer, Office of Procurement and Materials Management
LaTeesha Swann – Director, Office of Operations
Margaret Owo – Program Compliance Manager, Office of Civil Rights and Compliance
Maureen Kinyua – USAFI Technologies
Monica Queen – Deputy Director of Procurement
Niqui Clark – Deputy Chief Engineer, Division of Planning and Engineering
Robin Bowie
Shirlita Lee – Procurement Officer
Thomas Thomas – Procurement Officer
Zonia Parks – Administrative Officer I, Office of Civil Rights & Compliance
- 2 -
Joe Reese 00:00
Good morning. I'm Joe Reese with the Maryland Aviation, Administration Office of Procurement and
Materials Management. I would like to welcome you to today's pre-bid web-conference meeting for contract MAA-CO-26-022 and that is the Wilson Point Road Stormwater Management Improvements at
Martin State Airport. I am the Procurement Officer for this project, and your sole point of contact. With me today are members from MAA's Planning and Engineering Team, and I will also allow each speaker to introduce themselves. Let's see here. Okay, so do we have Harold Fowler?
Harold Fowler 01:19
Yes. Good morning, everyone. My name is Harold Fowler. I am the Chief, Airport Operations and
Management and Maintenance here at Martin State Airport.
Joe Reese 01:29
Thank you, Jeffrey Kolb.
Joshua Steininger 01:34
This is Josh Steininger. I'm going to be representing on behalf of Jeff Kolb. I'm working with Michael
Baker International.
Joe Reese 01:42
Okay. great, thank you. Okay, so we're going into some housekeeping rules here. What we want to do is remain on mute to minimize background noise. Also, click the raise hand button to ask questions or comments, and when speaking, please identify yourself and your company. So today we will discuss the procurement process, the project scope of work, and airport security requirements for Martin State
Airport. Should you have questions during this pre-bid meeting? Please announce your name and company before asking your question. We ask that you follow up with all questions in writing after this pre-bid meeting. So, we're going to go into the announcement of prospective vendors. We encourage networking during these meetings. So therefore, I will now introduce each company that submitted an
RSVP to this pre-bid conference. When you hear your company's name, please introduce yourself briefly. Advise if you plan to bid as a prime or a sub, and your capabilities if your company is a certified
MBE/DBE, so the first company that we have here is Bourn Environmental LLC. Okay, we also have
Triangle Contracting.
Chris Nevins 03:27
Hi. This is Chris with Triangle Contracting.
Joe Reese 03:35
Okay. Will you be bidding as a prime or a sub?
- 3 -
Chris Nevins 03:42
We're going to be a prime.
Joe Reese 03:47
Okay, thank you. Eastern Marine Services. Eastern Marine. Okay, USAFI Technologies. Forgive me if
I'm saying that incorrectly.
Maureen Kinyua 04:16
Yes, USAFI Technologies.
Joe Reese 04:22
Oh. Okay, you can go ahead and introduce yourself, and then let us know whether you are going to be bidding as a prime or a sub.
Maureen Kinyua 04:31
Maureen Kinyua with the USAFI Technologies. I'll be bidding as a sub.
Joe Reese 04:39
Okay, great. Thank you so much. If I did not introduce your company, please introduce yourself at this time. Okay. Is there anyone else that has not introduced their company? Okay. Thank you all. Now I will briefly go over the procurement process and the bid documents. The IFB consists of two volumes. Both volumes may be downloaded via eMaryland Marketplace Advantage. The bid number on eMMA is
BPM-058000 and the website for eMMA is https://eMMA.maryland.gov. So, we'll go into the advertisement. The bids are due August 13, 2026, no later than 1 p.m. Positively, no bids will be accepted after 1 p.m. on August 13. To submit a bid, bidders must first register on eMaryland
Marketplace Advantage, which is eMMA, and registration is free. The award of this contract shall be made to the responsible bidder that submits the lowest responsive bid that meets the specifications and minimum qualifications set forth in the IFB. To receive a contract award, a vendor must be registered on eMMA. Any questions posed from bidders after this meeting shall be submitted in writing, preferably by email, to my attention at jreese2@bwiairport.com. The cutoff for the receipt of all bidder questions is
July 30th, 2026, at 4 p.m. local time. Moving forward, members of our Planning and Engineering Team are here to provide an overview of the project scope. And speakers, please introduce yourself as you present. So, we're going to go on ahead and go with. I'm sorry. What is your name again? The individual filling in for Jeff?
Joshua Steininger 07:08
Josh.
Joe Reese 07:09
Josh. Yep. Okay.
https://emma.maryland.gov/ mailto:jreese2@bwiairport.com
- 4 -
Joshua Steininger 07:13
So, yeah, I am Josh Steininger with Michael Baker International, Civil Engineer. Let me. Joe, do you mind if I share my screen and show my presentation?
Joe Reese 07:25
Sure. Go right ahead.
Joshua Steininger 07:32
Okay. Let me know if you can see the screen.
Joe Reese 07:34
Yes.
Joshua Steininger 07:37
Okay. Alright. So, like Joe said, this is the Wilson Point Road Stormwater Management Improvements
Project at Martin State Airport. The main project goal is to construct a new storm drain outfall and alignment protruding to Dark Head Cove. It's going to be intercepting runoff that currently discharges to the Wilson Point Road as well. It's going to improve the Wilson Point Road corridor that we have right now, and then also it's going to be removing a damaged 18-inch corrugated metal pipe, repairing a tie-in and an 18-inch RCP. So, I just wanted to highlight those as the project’s main goals. So, this is the general project layout. I'll kind of zoom in a little bit more. Martin State Airport. Just wanted to make note for the contractors that this will be on MAA property, also SHA property, and then also Lockheed
Martin as also part of their property as well. So, you can kind of see in the hatch here's the proposed alignment corridor. Just wanted to note also we will be crossing Wilson Point Roads, so there's some utilities that the contractor needs to be aware of, such as a future sanitary, sewer and water main project that's going to be completed by Baltimore County. So that's something that the contractor needs to be aware of. And I'll go to next slide. So just kind of walking through the storm drain plans briefly, starting at upstream and working downstream. There's a crushed 18-inch CMP pipe that is going to be removed, compacted fill restore area with topsoil seed and soil stabilization matting right near the fence, and then starting at manhole 17, there's a manhole that's ultimately going to act as an inlet with an inlet top, and kind of going downstream, it's going to be intercepting manhole 16 is going to intercept the 18-inch
RCP line from the airfield. We did have an inspection report saying that this area needs to be repaired.
So, there's an attachment in the technical specifications that provides a bit more information about that, and that's going to be repaired with the following keynotes and the descriptions. Going a bit more downstream of the storm drain alignment, there's a future electric aircraft charging station that's going to be placed around this area that the contractor just needs to be aware of. And if we go a bit more downstream, manhole 14, 13, 12, and 11 go around the Baltimore City Police Hangar, Aviation Hangar, and we have a blowup of 13 and 12, kind of showing up right here. That's going to show that there's going to be a sanitary, sewer cleanout, a proposed new cleanout that's going to be installed since that's going to be hitting it, and that needs to be relocated along with the sanitary sewer line, and then some
- 5 -
PVC storm drain downspout connectors along with the cleanouts as well. So, we go back to the main viewport. 11 and 10 is going to be intercepting the under-drain storm drain lines that are kind of shown in right here, and it kind of keeps going downstream. There is a vacuum excavation that's going to end or start kind of around this stationing. That's a separate line item that the contractor needs to be aware of, and that's just to get eyes on the utilities that are here. And there are test bits that were completed during the design that are included in the contract documents. So, manhole 9, 8, 7, 6, 5, still kind of going downstream, and as shown, there's some utilities and some trees that also need to be removed and replaced. The trees that need to be removed and replaced and utilities, the contractor needs to be aware of, and I'll keep going downstream. It's going to cross Wilson Point Road, like I said before, there's going to be an elliptical pipe, as shown. We have a couple of sheets in the contract documents for the
Wilson Point Road, SHA section right here. It's going to be a 50-foot offset overlay roadway sign replacement, curb median, sidewalk to put back and replace in kind. Like I said, there's an existing water and sanitary sewer, and the county is planning to relocate those. So, we will be working around their schedule when they install their new lines and abandon the old lines. And then it's going to travel into
Lockheed Martin's property, manhole three, manhole two, manhole one, and ultimately, it's going to penetrate an outfall into Dark Head Cove at this end wall. There is a soil management plan that's in the technical specifications that the contractor needs to be aware of, and that is an attachment, and a pay item is included in there as well. So here is the construction safety and phasing plan. There are seven phases, kind of as shown, phase one going all the way up to phase seven, phase two, which is in Wilson
Point Road. We're trying to get that done as quickly as possible to minimize any disruptions for the SHA and the nearby folks. Low profile barricades are also shown here, since we're kind of getting close to the taxiway object-free area, so that would need to be placed. And then this is our conceptual construction schedule. This is conceptual. We're working with an outfall restriction from April 15 to October 15, so anticipating mobilization or NTP sometime in late summer or fall 2027. Here's the phases that are shown. And like I mentioned before, there's the county Water and Sewer Main Project in Wilson Point
Road that we'll just need to coordinate on that front. I think that's all I have for my presentation.
Candace, is there anything else you would like to discuss or add that I didn’t touch on.
Joe Reese 15:15
Okay, we'll go ahead and move on to the security issues that we may have over at Martin State Airport, and at this point, we will have Mr. Harold Fowler, who's the Chief at Martin State Airport Operations and Maintenance.
Harold Fowler 15:36
Alright. Good morning, everyone. I can't emphasize enough just to pay attention to the technical provisions that are laid out. They kind of spell out all of the segments that need to be adhered to. As just discussed, there is some work that is being done between the different phases that will be on the airport proper, and then some off of the airport. Security-wise, for those individuals who are going to need to access the AOA, that will be coordinated with our Airport Operations Office to ensure that the correct training is provided for those that are going to drive within the aircraft operating area. For those that are
- 6 -not, but just need to get on the airport again, within those technical provisions and construction documents, you will see staging areas and parking areas for your vehicles. Phase two, which was just discussed, is what is the Wilson Point Road crossing. That is the only, I would say main artery, but it is the only way in and out for the airport and all of our neighbors that are south of that point on Wilson
Point Road. So, being sure that one, we are doing everything we can to ensure it's being done safely.
Flaggers or whatever is necessary is going to be a big one, and then the communication with the project managers who communicate with us here at the airport, so that we can notify our neighbors when we expect to have some interruptions to that space. Right, so we have several neighbors, and then we also have a good number of law enforcement and emergency responders that are here at the airport themselves. So, ensuring that phase two is done in a safe and efficient way is going to be extremely important. The only other security side is, we did show in that phase one, the parcel ‘D’ for Lockheed
Martin, we do expect that will be transferred over to MAA, prior to the start of this first phase, and then so there won't be any additional security requirements that need to be fulfilled with Lockheed Martin directly to access that space. If that changes, we'll be sure to convey that to the teams. Outside of that, obviously, just all the regular safety aspects, Safety Officers, and PPE that's going to be necessary for this type of project, and any of those questions; safety, security questions can go to Joe, and then he'll get that back to us, so we can get some answers to you. Alright. Any questions before I turn it back over to Joe? Outstanding. Alright. Hearing none. I appreciate your time, and hope you guys have a good day.
Joe Reese 18:41
Okay. Thank you, Harold. So, I know that we have several people here from the OCRC. However, there is no goal on this contract. There is no DBE goal because there is federal funding on this contract. But I would like to ask if you guys have anything that you would need to add at this meeting. If not, we can move forward.
Sheldon Reynolds 19:25
Good morning, Joe, and the rest of everyone that's attending this meeting. I'll be speaking in place of
Brett Harold today. So, what we will add for the Office of Civil Rights and Compliance are the following provisions, which are within this contract. So, what I'm going to do now is read from our overall script of what's going to occur within the contract in regards to the MBE compliance. So, you said, Mr. Reese, you said there is no DBE compliance or DBE participation, that is correct. There is an
MBE participation, so I will read the provisions.
Joe Reese 20:11
No, there's no MBE and the DBE is a 0% goal. Yeah, there's none. Yeah, there was a PRG meeting that we just had recently that we had to change that based on the funding.
Sheldon Reynolds 20:32
So, there was no goal of MBE participation goal of 22% for contract MAA-CO-26-022. Okay, good enough. Alright then, I will pause. Thank you, Mr. Reese.
- 7 -
Joe Reese 20:47
Alright, no problem. Okay, so any questions that we have posed and responded to at this meeting will be included in the minutes of this meeting. Also, any questions posed from bidders after this meeting shall be submitted in writing by email to my attention at jreese2@bwiairport.com. However, I would also like you to send your questions, cc: Christa Marcotte, and she is going to be at cmarcotte3@bwiaport.com, and I'll go over that again. That's going to be cmarcotte3@bwiaport.com.
Please also send your questions to her as well. The cutoff for receipt of the bidder questions is going to be July 30th, 2026 at 4 p.m. That's July 30th, 2026 at 4 p.m. and the minutes of this meeting, attendance, and all responses to questions will be part of an addendum for this procurement, and the addendum will be posted on eMMA. So, before we take questions, if you have joined late or did not have an opportunity to introduce your company, please do so at this time. Okay, Margaret. I see your hand raised here.
Margaret Owo 22:32
Yes, good morning. My name is Margaret Owo. I'm the Compliance Deputy Director for Office of Civil
Rights and Compliance. I have a question. So, this solicitation has no participation goal. Is that correct?
Joe Reese 22:46
That's correct.
Margaret Owo 22:48
Okay. Alright. Thank you. Just wanted to confirm.
Joe Reese 22:57
Okay. So, at this time, we'll go ahead and take questions, and please announce your name and your firm before asking your question. Any questions? Okay, so if we do not have any questions for today, this will conclude today's pre-bid conference, and I thank you for your interest and good luck with your bid.
Meeting officially ended at 23:34 mailto:cmarcotte3@bwiaport.com mailto:cmarcotte3@bwiaport.com
Attachment A. Pre-Bid Conference Response Form
Solicitation Number MAA-CO-26-022
Wilson Point Stormwater Management Improvements at
Martin State Airport
A Pre-Bid conference will be held via Microsoft Teams at 11:00: a.m. on July 22, 2026 for interested Offerors.
Please return this form by 11:00 a.m. July 21,2026, advising whether or not your firm plans to attend. The below information will be posted in an upcoming Addendum as an interested party. The completed form should be returned via e-mail to the Procurement Officer at jreese2@bwiairport.com
Please indicate:
Yes, the following representatives will be in attendance.
Attendees
1.
2.
3.
4.
No, we will not be in attendance.
Company Name:
Bidding as a Prime or Sub:
Printed Name:
E-Mail Address:
Date:
Mark Rubio
Bourn Environmental LLC
Prime
Mark Rubio mrubio@bournenvironmental.org
07/17/2026
Wilson Point Stormwater Management Improvements at
Martin State Airport
A Pre-Bid conference will be held via Microsoft Teams at 11:00: a.m. on July 22, 2026 for interested Offerors.
Please return this form by 11:00 a.m. July 21,2026, advising whether or not your firm plans to attend. The below information will be posted in an upcoming Addendum as an interested party. The completed form should be returned via e-mail to the Procurement Officer at jreese2@bwiairport.com
Please indicate:
X Yes, the following representatives will be in attendance.
Attendees
1.Dave Capino 2.
Company Name: Eastern Marine Services
Bidding as a Prime or Sub: Sub
Printed Name: David W Capino
E-Mail Address: dcapino@easternmarineservices.com
Date: 7/20/2026
Wilson Point Stormwater Management Improvements at
Martin State Airport
A Pre-Bid conference will be held via Microsoft Teams at 11:00: a.m. on July 22, 2026 for interested
Offerors.
Please return this form by 11:00 a.m. July 21,2026, advising whether or not your firm plans to attend. The below information will be posted in an upcoming Addendum as an interested party. The completed form should be returned via e-mail to the Procurement Officer at jreese2@bwiairport.com
Please indicate:
Yes Yes, the following representatives will be in attendance.
Attendees
1. Christopher Nevins
2. Melissa Elliott
Company Name: Triangle Contracting
Bidding as a Prime or Sub: Prime
Printed Name: Melissa Elliott
E-Mail Address: melliott@trianglecontracting.com
Date: 07/20/2026
Wilson Point Stormwater Management Improvements at
Martin State Airport
A Pre-Bid conference will be held via Microsoft Teams at 11:00: a.m. on July 22, 2026 for interested
Offerors.
Please return this form by 11:00 a.m. July 21,2026, advising whether or not your firm plans to attend. The below information will be posted in an upcoming Addendum as an interested party. The completed form should be returned via e-mail to the Procurement Officer at jreese2@bwiairport.com
Please indicate:
X Yes, the following representatives will be in attendance.
Attendees
1. Maureen Kinyua
2.
Company Name: Usafi Technologies LLC
Bidding as a Prime or Sub: Sub
Printed Name: Maureen Kinyua
E-Mail Address: kinyua@usafitechllc.com
Date: July 21 2026
Pre-Bid Conference MAA-CO-26-022 Wilson Point Stormwater Management Improvements
Name Attendance Response Monica Queen <MQueen6@bwiairport.com> Required Accepted Shirlita Lee <SLee8@bwiairport.com> Required Accepted Thomas Thomas <TThomas21@bwiairport.com> Required Accepted Christa Marcotte <CMarcotte3@bwiairport.com> Required Accepted clong <clong@mcknightintl.com> Required Accepted Margaret Owo <MOwo@bwiairport.com> Required Accepted Brett Harrell (C) <Bharrell@bwiairport.com> Required Accepted Sheldon Reynolds <SReynolds@bwiairport.com> Required Accepted Zonia Parks <ZParks@bwiairport.com> Optional Accepted Steininger Joshua <Joshua.Steininger@mbakerintl.com> Accepted Bowie Robin <Robin.Bowie@mbakerintl.com> Accepted LaTeesha Swann <lswann@bwiairport.com> Optional Accepted
MARYLAND AVIATION ADMINISTRATION
OFFICE OF PROCUREMENT & MATERIALS MGMT
PLAN HOLDERS/BIDDERS LIST
CONTRACT NO: MAA-CO-26-022 TITLE: Wilson Point Road Stormwater Management at Martin
State Airport
PRE-BID DATE: July 22, 2026 @ 11:00 AM – Via Web Conference
BID DUE DATE: August 13, 2026 @ 01:00 PM
BID OPEN: August 13, 2026 @ 01:05 PM
Date 7/17/2026 Company Name Bourn Environmental LLC__________________
Issued by: Street Address 1209 Church Road
_Joe Reese_________ City Mitchellville State Maryland Zip 20721
Method of Delivery: Contact Name Mark Rubio
Email Address mrubio@bournenvironmental.org
Pickup eMail
Phone: 443-223-1402 Fax: N/A
Tracking:
Signature:
Date7/20/2026 Company Name Triangle Contracting LLC
Issued by: Street Address 313 East Fourth Street
_Joe Reese_________ City Frederick State Maryland____ Zip 21701
Method of Delivery: Contact Name Christopher Nevins
Email Address cnevins@trianglecontracting.com
Phone: 443-823-5474 Fax: N/A
X
Contract Number: MAA-CO-26-022 Page 2
Date 7/20/2026 Company Name DXI Construction
Issued by: Street Address 260 Hopewell Road
_Joe Reese_________ City Churchville State Maryland Zip 21028
Method of Delivery: Contact Name Robert (Bobby) Gibson
Email Address rgibson@dxiconstruction.com
Phone: 443-422-4623 Fax: N/A
Date_7/21/2026_____ Company Name Allan Myers
Issued by: Street Address P.O. Box 278
Krystal White City Fallston State Maryland Zip 21047
Method of Delivery: Contact Name Chris McKew
Email Address chris.mckew@allanmyers.com
Phone: 301-674-9366 Fax: N/A
Date__7/24/2026____ Company Name DSM Contracting
Issued by: Street Address 1417 Shoemaker Rd
_K. White_________ City Baltimore State MD Zip 21209
Method of Delivery: Contact Name Shane Hornberger
Email Address Shane.Hornberger@DSM-Contracting.com_
Phone: 443-721-3809 Fax: N/A
Contract Number: MAA-CO-26-022 Page 3
Date 07/27/26 Company Name Brawner Builders, Inc ____________
Issued by: Street Address 11011 McCormick Rd Ste 300
_Christa Marcotte_ City Hunt Valley State MD Zip 21031
Method of Delivery: Contact Name David Berkhimer
Email Address dberkhimer@brawnerbuilders.com
Pickup EMail
Phone:443-895-1350 Fax: 410-666-2843
Date07/28/26 Company Name __Kibler Construction________________
Issued by: Street Address 3332 Baltimore Blvd
_Christa Marcotte_____ City __Finksburg State MD Zip21048
Method of Delivery: Contact Name M. Dave
Email Address Dmitesh@kiblerconstruction.com
Phone:410-833-5345 Fax: 410-833-1732
Date 07/28/26 Company Name Urban N Zinc Contractor Inc.
Issued by: Street Address 11615 Crossroads Circle Ste L
_Christa Marcotte ___ City Middle River State MD Zip 21220
Method of Delivery: Contact Name Hogan Strickland
Email Address Hogan.Strickland@urbanzink.com
Phone:410-355-3456 Fax: N/A
MAA-CO-26-022 Federal Funded Technical Specifications
01 2100 - 1 Allowances
Martin State Airport August 10, 2026
SECTION 01 2100 - ALLOWANCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Maryland Department of Transportation/Maryland Aviation Administration Standard Provisions for Construction Contracts Volumes I and II, dated October 2017; and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. Contingency allowances.
1.3 DEFINITIONS
A. Allowance: A quantity of work or dollar amount included in the Contract, established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.
1.4 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections.
Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by Architect from the designated supplier.
1.5 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.
01 2100 - 2 Allowances
Martin State Airport August 10, 2026
1.6 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.7 CONTINGENCY ALLOWANCES
A. Use the contingency allowance only as directed by Architect for Owner's purposes and only by Change Orders that indicate amounts to be charged to the allowance.
B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs.
C. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and reasonable overhead and profit.
D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.
1.8 ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, required maintenance materials, and similar margins.
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.
B. Submit claims for increased costs due to a change in the scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
01 2100 - 3 Allowances
Martin State Airport August 10, 2026
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. 1: Contingency (Miscellaneous Construction) Allowance: Include a contingency allowance of $314,000.00 for use according to Owner's written instructions.
B. Allowance No. 2: Contingency (Utility Relocation) Allowance: Include a contingency allowance of $100,000.00 for the relocation of existing utilities that may be encountered during construction for use according to Owner's written instructions.
C. Allowance No. 3: Contingency (Security Guard) Allowance: Include a contingency allowance of $5,000.00 for providing security during installation of the proposed storm drain pipe under the Airport perimeter security fence for use according to Owner’s written instructions.
Contractor shall contract with MAA’s security provider for Martin State Airport, which at the time of bid advertisement is All County Security Agency, Inc.
PART 4 - MEASUREMENT
4.1 METHOD OF MEASUREMENT
A. No separate measurement will be made for work under this section.
PART 5 - PAYMENT
5.1 BASIS OF PAYMENT
A. Installed and accepted work will be paid for at the contract unit price bid for work bid under items or agreed upon in writing prior to start of the allowance work. The bid price or the agreed upon price shall be full compensation for mobilization and demobilization; temporary construction items; maintenance of traffic; supervision; for furnishing all materials and for all
01 2100 - 4 Allowances
Martin State Airport August 10, 2026 layout, erection, labor, equipment, tools, and incidentals necessary to complete the item in accordance with these specifications.
B. Payment will be made on the basis specified in the Special Provisions articles governing negotiated payment. In no case will the Contractor’s overhead and profit exceed 3%. Partial payments will be made out of the allowance amounts as the Contractor’s monthly applications for payments with supporting bills and invoices are approved. The Contractor shall furnish evidence to the Construction Manager that bills and invoices have been paid for prior to receiving payment from the MAA. The Contractor shall include the cash amounts set forth herein on the Bid Proposal Forms for each allowance item. The Contractor shall not be entitled to any unspent or non-approved portion of allowances.
1. The cost of the work described in this section shall be included in the lump sum contract price for Section 01 2100.
C. Costs for work performed under an Allowance Item shall be determined in accordance with General Provision GP-4.07 – Negotiated Payment Provision and Special Provision SP-9.04 – Negotiated Payment or General Provision GP-9.02 – Force Account Work, as directed by the Construction Manager. Mark-ups for subcontractor bond costs, and mark-ups for third tier subcontractor overhead, profit, and bonds shall not be permitted. The Contractor shall not be entitled to any unspent or non-approved portion of Allowances.
D. Payment will be made under:
1. Item 01 2100.1 Allowance No.1 – Miscellaneous Construction Allowance – per
ALLOW.
2. Item 01 2100.2 Allowance No. 2 – Utility Relocation Allowance – per ALLOW.
3. Item 01 2100.3 Allowance No. 3 – Security Guard Allowance – per ALLOW.
END OF SECTION 01 2100
Wilson Point Road SWM Improvements Stormwater Conveyance
Martin State Airport 33 4200-1 August 10, 2026
SECTION 334200 - STORMWATER CONVEYANCE
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Maryland Department of
Transportation/Maryland Aviation Administration Standard Provisions for Construction
Contracts Volume I and II, dated October 2017; and Division 01 Specification Sections, apply to this Section.
B. Incorporated by reference: Maryland Department of Transportation State Highway
Administration Standard Specifications for Construction and Materials and Supplemental
Specifications and Provisions, most recent edition. Hereinafter referred to as SHA
Specifications. May be accessed on-line, current URL (subject to change):
https://roads.maryland.gov/mdotsha/pages/sscm.aspx?PageId=853&lid=SSP
C. Incorporated by reference: Maryland Department of Transportation State Highway
Administration Book of Standards - for Highway and Incidental Structures, most recent edition.
Hereinafter referred to as SHA Standards. May be accessed on-line, current URL (subject to change): https://www.roads.maryland.gov/mdotsha/pages/Index.aspx?PageId=69
D. ACPA's "Concrete Pipe Installation Manual."
E. ASTM A536 (2019 or most recent) Standard Specification for Ductile Iron Castings
F. ASTM C76 (2025 or most recent) Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe.
G. ASTM C361 (2022 or most recent) Standard Specification for Reinforced Concrete Low-Head
Pressure Pipe
H. ASTM C443 (2021 or most recent) Standard Specification for Joints for Concrete Pipe and
Manholes, Using Rubber Gaskets
I. ASTM C478 (2022 or most recent) Standard Specification for Circular Precast Reinforced
Concrete Manhole Sections
J. ASTM C507 (2022 or most recent) Standard Specification for Reinforced Concrete Elliptical
Culvert, Storm Drain, and Sewer Pipe
K. ASTM C877 (2021 or most recent) Standard Specification for External Sealing Bands for
Concrete Pipe, Manholes, and Precast Box Sections
L. ASTM C890 (2021 or most recent) Standard Practice for Minimum Structural Design Loading for Monolithic or Sectional Precast Concrete Water and Wastewater Structures
Martin State Airport 33 4200-2 August 10, 2026
M. ASTM C913 (2021 or most recent) Standard Specification for Precast Concrete Water and
Wastewater Structures
N. ASTM C923 (2000 or most recent) Standard Specification for Resilient Connectors Between
Reinforced Concrete Manhole Structures, Pipes and Laterals
O. ASTM C969 (2019) Standard Practice for Infiltration and Exfiltration Acceptance Testing of
Installed Precast Concrete Pipe Sewer Lines
P. ASTM C990 (2019 or most recent) Standard Specification for Joints for Concrete Pipe, Manholes, and Precast Box Sections Using Preformed Flexible Joint Sealants
1.2 SUMMARY
A. Section Includes:
1. Pipe.
2. Manholes.
3. Stormwater inlets.
1.3 DEFINITIONS
A. AASHTO American Association of State Highway and Transportation Officials
B. ACPA American Concrete Pipe Association
C. ASTM American Society for Testing Materials International
1.4 ACTION SUBMITTALS`
A. Product Data: For each type of product.
B. Shop Drawings:
1. Manholes: Include plans, elevations, sections, details, frames, steps, gasket type and material, waterproof joint wrap and covers.
2. Stormwater Inlets. Include plans, elevations, sections, details, frames, covers, steps, gasket type and material, waterproof joint wrap and grates.
3. Stormwater Pipe: Include manufacturer, fabricating plant, ASTM designation, class, wall thickness, gasket type and material
1.5 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Show pipe sizes, locations, and elevations. Show other piping in same trench and clearances from storm drainage system piping and other existing utilities. Indicate interface and spatial relationship between manholes, piping, existing utilities, proximate structures and any conflicts or obstructions.
Martin State Airport 33 4200-3 August 10, 2026
B. Product Certificates: For each type of pipe, structure and fitting, from manufacturer.
C. Field quality-control reports.
1.6 QUALITY ASSURANCE
A. Piping materials shall bear label, stamp, or other markings of manufacture to include; name of fabricating facility, date of manufacture and ASTM designation.
B. Storm drain structures shall be clearly marked with the structure identifier as shown on the
Drawings.
1.7 DELIVERY, STORAGE, AND HANDLING
A. Protect pipe, pipe fittings, and seals from dirt and damage.
B. Handle manholes in accordance with manufacturer's written rigging instructions.
C. Handle stormwater inlets in accordance with manufacturer's written rigging instructions.
1.8 PERMITTING
A. Permitting not covered by the General Permit for Stormwater Discharge Associated With
Construction Activity (20CP), if necessary depending on means and methods, for hydrostatic testing and cleaning water disposal are the responsibility of the Contractor.
1.9 FIELD CONDITIONS
A. Interruption of Existing Utilities: Do not interrupt existing utility service unless permitted under the following conditions and then only after arranging to provide temporary service in accordance with owner and operator.