About this file

This is a technical plans and standards document for an Infrastructure Repair Work Order Contract issued by the State of Florida for Pinellas County (REFF # 26-0208). The document provides standard detail specifications and construction guidelines for infrastructure repair projects, including concrete repairs, site cleanup, milling and resurfacing, landscape work, fencing, sidewalk repairs, ADA ramps, and sheet pile installation. The plans include four typical roadway sections (Type A P.C. Curb & Gutter, Type F FDOT Curb & Gutter, Stabilized Aggregate Shoulder, and Shoulder with Sod) with corresponding cross-sectional details and elevation markers. The document establishes requirements for tree and vegetation protection during construction, including specifications for barriers, restricted equipment use, and soil tracking prevention.

The document includes detailed specifications for Soil Tracking Prevention Devices (STPD) to minimize off-site sediment migration during construction activities. Key requirements include mandatory hand labor only within tree protection barriers, daily removal of spilled materials from public roads, sediment pit retention volumes of 3,600 cubic feet per acre, daily rinsing and maintenance of STPDs, and use of FDOT Size #1 aggregates. The contractor may propose alternative sediment control techniques subject to engineer approval. Standard STPD dimensions are 15 feet by 50 feet unless otherwise specified in project plans, with provisions for double-width (30 feet) STPDs when vehicle volumes warrant approval by the engineer. All STPD costs, including construction, maintenance, material replacement, removal, restoration, sediment disposal, and road cleaning, are included in the unit price compensation.

View the file

Other files

File Type Posted
Infrastructure_Repair_Work_Order_Contract.pdf PDF
Common_Carrier_Attestation_02.05.2025.pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
Foreign_Countries_of_Concern_Affidavit_02.05.2025_(1).pdf PDF
Appendix_6_Anderson_Blvd_Repair_Geotech_Services_Report_(2)_S&S.pdf PDF
Appendix_6_Indian_Rocks_Beach_Geotech_report.pdf PDF
Appendix_6_Sand_Key_Park_100%_Plans.pdf PDF
Appendix_6_Sand_Key_Park_Geotech_report.pdf PDF
Appendix_6_Anderson_Blvd_Repair_Pavement_Memo.pdf PDF
Appendix_6_IndianShores-Tiki_Garden_Geotechnical_Report.pdf PDF
Appendix_6_Madeira_Geotech_report.pdf PDF
Appendix_6_Redington_Shores_Geotech_report.pdf PDF
Appendix_6_-_Anderson_Blvd_Repair_Geotech_Services_Report__S&S.pdf PDF
SBE_Compliance_Form.pdf PDF
Sample_Agreement_-_26-0208.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Pricing_Proposal_26-0208(reference_only).pdf PDF
Special_Provisions.pdf PDF
Specifications.pdf PDF
Sample_Change_Order.pdf PDF
APPENDIX_1-Permits_(4).pdf PDF
Sample_Application_for_Payment.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Appendix_4_-_Special_Notices_5.28.pdf PDF
Appendix_6_Maderia_Beach_Access__90%_PLANS.pdf PDF
Appendix_6_Redington_Shores_Beach_Access_100%_Plans.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_4.26.pdf PDF
Appendix_6_Anderson_Blvd_Repair_100%_Plans_(1).pdf PDF
APPENDIX_6-Example_Projects.pdf PDF
Appendix_6_Indian_Shores-Tiki_Gardens_100%_Plans.pdf PDF
26-0208_Infrastructure_Estimate_5.22_(For_review_only).xlsx XLSX spreadsheet
4.26.Performance_and_Payment_Bonds.pdf PDF
Appendix_6_Indian_Rocks_Beach_100%_Plans.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Airport_Security_Program.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
E-Verify_Affidavit.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REFF # 26-0208

INFRASTRUCTURE REPAIR

WORK ORDER CONTRACT

STATE OF

No.

P R O

FESS IONAL EN

GIN

EE

R

Y I

THIERRY KU

FLORI'A

88713

SECTION A

DETAIL A

TYPICAL SECTION

P.C. TYPE A CURB & GUTTER

A

SECTION B

DETAIL B

TYPICAL SECTION

FDOT TYPE F CURB & GUTTER

B

SECTION C

DETAIL C

TYPICAL SECTION

STABILIZED AGGREGATE SHOULDER

DETAIL D

TYPICAL SECTION

SHOULDER WITH SOD

C D

NOTES:

1. NO TRUCKS OR HEAVY EQUIPMENT ALLOWED WITHIN BARRIERS, ONLY HAND LABOR ALLOWED.

2. NO CONSTRUCTION MATERIALS, SOIL DEPOSITS, OR SOLVENTS SHALL BE ALLOWED WITHIN BARRIERS.

3. BARRIERS ARE TO BE IN PLACE PRIOR TO ANY CONSTRUCTION ACTIVITIES WITHIN TREE AREA.

4. BARRIERS ARE TO STAY IN PLACE UNTIL ALL PAVING, CONSTRUCTION, AND HEAVY EQUIPMENT IS REMOVED

FROM THE AREA.

LARGE TREES AND BUSHESPALMS AND SMALL TREES

1. A SOIL TRACKING PREVENTION DEVICE (STPD) SHALL BE CONSTRUCTED AT LOCATIONS DESIGNATED BY THE ENGINEER FOR POINTS OF EGRESS FROM UNSTABILIZED AREAS OF THE PROJECT TO PUBLIC ROADS WHERE OFF SITE TRACKING OF MUD COULD OCCUR. TRAFFIC FROM UNSTABILIZED AREAS OF THE CONSTRUCTION PROJECT SHALL BE DIRECTED THROUGH STPD BARRIERS. FLAGGING, OR OTHER POSITIVE MEANS SHALL BE USED AS REQUIRED TO LIMIT AND DIRECT VEHICULAR EGRESS ACROSS THE STPD.

2. THE CONTRACTOR MAY PROPOSE AN ALTERNATIVE TECHNIQUE TO MINIMIZE OFF SITE TRACKING OF SEDIMENT. THE ALTERNATIVE MUST

BE REVIEWED AND APPROVED BY THE ENGINEER PRIOR TO ITS USE.

3. ALL MATERIALS SPILLED, DROPPED, OR TRACKED ONTO PUBLIC ROADS (INCLUDING THE STPD AGGREGATE AND CONSTRUCTION MUD)

SHALL BE REMOVED DAILY, OR MORE FREQUENTLY IF SO DIRECTED BY THE ENGINEER.

4. AGGREGATES SHALL BE DESCRIBED IN SECTION 901 EXCLUDING 901-2.3. AGGREGATES SHALL BE FDOT SIZE #1. IF THIS SIZE IS NOT AVAILABLE, THE NEXT AVAILABLE SMALLER SIZE AGGREGATE MAY BE SUBSTITUTED WITH THE APPROVAL OF THE ENGINEER. SIZES CONTAINING EXCESSIVE SMALL AGGREGATE WILL TRACK OFF THE PROJECT AND

ARE NOT SUITABLE.

5. THE SEDIMENT PIT SHOULD PROVIDE A RETENTION VOLUME OF 3600 CUBIC FEET/ACRE OF SURFACE AREA DRAINING TO THE PIT. WHEN THE STPD IS ISOLATED FROM OTHER DRAINAGE AREAS, THE FOLLOWING PIT VOLUMES WILL SATISFY THIS REQUIREMENT:

15'X50'=100 FT³

30'X50'=200 FT³

AS AN OPTION TO THE SEDIMENT PIT, THE WIDTH OF THE SWALE BOTTOM CAN BE INCREASED TO OBTAIN THE VOLUME.

WHEN THE SEDIMENT PIT OR SWALE VOLUME HAS BEEN REDUCED TO ONE HALF, IT SHALL BE CLEANED. WHEN A SWALE IS USED, SYNTHETIC BALES OR SILT FENCE SHALL BE PLACED ALONG THE ENTIRE LENGTH.

6. THE SWALE DITCH DRAINING THE STPD SHALL HAVE A 0.2% MINIMUM AND A 1.0% MAXIMUM GRADE ALONG THE STPD

AND TO THE SEDIMENT PIT.

7. MITERED END SECTIONS ARE NOT REQUIRED WHEN THE SIDE DRAIN PIPE SATISFIES THE CLEAR ZONE REQUIREMENTS.

8. THE STPD SHALL BE MAINTAINED IN A CONDITION THAT WILL ALLOW IT TO PERFORM ITS FUNCTION. TO PREVENT OFFSET TRACKING, THE STPD SHALL BE RINSED (DAILY WHEN IN USE) TO MOVE ACCUMULATED MUD DOWNWARD THROUGH THE STONE. ADDITIONAL STABILIZATION OF THE VEHICULAR ROUTE LEADING TO THE STPD MAY BE REQUIRED

TO LIMIT MUD TRACKED.

9. A STPD SHALL BE PAID FOR UNDER THE CONTRACT UNIT PRICE FOR SOIL TRACKING PREVENTION DEVICE, EA. THE UNIT PRICE SHALL CONSTITUTE FULL COMPENSATION FOR CONSTRUCTION, MAINTENANCE, REPLACEMENT OF MATERIALS, REMOVAL, AND RESTORATION OF THE AREA UTILIZED FOR THE STPD: INCLUDING BUT NOT LIMITED TO EXCAVATION, GRADING, TEMPORARY PIPE (INCLUDING M.E.S. WHEN REQUIRED), FILTER FABRIC, AGGREGATE, PAVED TURNOUT

(INCLUDING ASPHALT AND BASE CONSTRUCTION), DITCH STABILIZATION, APPROACH ROUTE STABILIZATION, SEDIMENT REMOVAL AND DISPOSAL, WATER, RINSING AND CLEANING OF THE STPD AND CLEANING OF PUBLIC ROADS, GRASSING AND SOD. SYNTHETIC BALES SHALL BE PAID FOR UNDER THE CONTRACT UNIT PRICE FOR HAY OR STRAW BALED, EA. SILT FENCE SHALL BE PAID FOR UNDER THE

CONTRACT UNIT PRICE FOR STAKED SILT FENCE, L.F.

10. THE NOMINAL SIZE OF A STANDARD STPD IS 15'X50' UNLESS OTHERWISE SHOWN IN THE PLANS. IF THE VOLUME OF ENTERING AND EXITING VEHICLES WARRANT, A 30' WIDTH STPD MAY BE USED IF APPROVED BY THE ENGINEER. WHEN A DOUBLE WIDTH (30')

STPD IS USED, THE PAY QUANTITY SHALL BE 2 FOR EACH LOCATION.

PALM TREES DECIDUOUS TREES CONIFEROUS TREES

TRANSITION DETAIL

SECTION A-A RURAL CONNECTION

DETAIL

SECTION B-B

EL. 10

EL. 15

EL. 20

EL. 25

EL. 30

DISTURBED AREA

PROTECTED AREA

10 L.F. PER END PLACED AT A 30° ANGLE

TO PREVENT END-AROUND FLOW

WOODEN STAKES

WOODEN STAKES

(4' O.C. FOR TYPE S,

6' O.C. FOR TYPE NS)DISTURBED AREA

PROTECTED AREA

1:1 MAX. SLOPE

COMPOST FILTER SOCK

(SEE PLAN FOR HEIGHT)

SECTION NTS

PLAN NTS

Sheets and Views
1 KEY - 01
2 25-138-DTL - General Notes
3 DTL - Roadway Typical Sections A-D
4 DTL - Sidewalk at Tree Detail and Notes
5 DTL - Details & Limits Clearing Grubbing Grading
6 GEN - 004973A SWPPP 1
7 GEN - 004973A SWPPP 2
8 GEN - 004973A EROSION CONTROL DETAILS
9 GEN - 004973A EROSION CONTROL NOTES
2026-05-15T08:57:50-0400
Yi T Ku

File details come from the government source that posted it. Updated .