Pinellas County Redington Shores Beach Access Paving Project - 100% Plans Document
This document is a comprehensive set of construction plans and specifications for the Redington Shores Beach Access Paving Project (Project No. 90018G1-A4) prepared by professional engineer Matthew R. Ivie for Pinellas County, Florida. The project encompasses infrastructure repair and reconstruction work across approximately 2.98 acres, with 2.62 acres designated for disturbance activities. The scope of work includes roadway and parking lot projects featuring mobilization, temporary traffic control barricades (270 EA/day), sediment barriers (1,325 linear feet), removal of existing asphalt pavement (5,245 square feet), concrete pavement removal (10 square yards), fence removal (1,473 linear feet), and excavation for roadway and base installation (711 cubic yards). Major construction items include Superpave asphalt concrete placement (1,006 tons), concrete curb and gutter installation (approximately 2,956 linear feet combined), handrail installation (380 linear feet of galvanized steel pipe), fencing installation (1,075 linear feet of black vinyl coated chain link), and various site improvements including landscaping shell placement (216 cubic yards), traffic striping, wheel stops, water fountain installation, and bicycle racks. The project includes detailed erosion and sediment control measures, stormwater pollution prevention planning, and water quality monitoring protocols for turbidity compliance with Florida Department of Environmental Protection standards.
The project specifications establish comprehensive environmental and construction management requirements including weekly erosion control inspections and inspections after every 12 inches of rainfall, with mandatory stabilization of cleared areas within 14 calendar days using temporary sodding or seeding. The contractor must implement structural practices such as sediment barriers, soil tracking prevention devices, sediment basins, and floating turbidity barriers as specified in the plans. Material management practices require storage of all products in original manufacturer-labeled containers under roof or contained enclosures, with secondary containment required for opened containers and fuel tanks. Hazardous waste encountered during construction must be reported to Pinellas County within 24 hours and to the Florida Department of Environmental Protection, with the contractor responsible for proper disposal and submission of disposal manifests. Water quality monitoring must occur twice daily at least four hours apart at background stations 500 feet up-current and compliance stations 300 feet down-current, with turbidity sampling at multiple depths and turbidity readings recorded using properly calibrated turbidimeters. The receiving waters for stormwater discharge are identified as the Gulf of America, and the contractor must cease construction activities immediately if water quality standards are violated, implementing corrective measures at no additional cost to the county.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PINELLAS COUNTY
REDINGTON SHORES BEACH ACCESS PAVING
PROJECT NO: 90018G1-A4
STATE OF
No.
PR
O
FESSIONAL ENGIN
EE
R
MA
TTHEW R. IVIE
FLORI'A
86205
18200 GULF BOULEVARD
REDINGTON SHORES, FLORIDA 33708
PARCEL NO. 31-30-15-52506-002-0010
Pay Item No. Description Quantity Unit
ROADWAY / PARKING LOT PROJECTS
101-0100 MOBILIZATION 1 LS
102-1655 BARRICADE, TYPE III, (TEMPORARY MOT), PER FDOT INDEX NO. 102-600 270 EA/DAY
104-10-3 SEDIMENT BARRIER 1,325 LF
104-15 SOIL TRACKING PREVENTION DEVICE 1 EA
110-0100-0009 CURB, REMOVAL 89 LF
110-0100-0010 ASPHALT-REMOVAL, INCLUDES ROADWAY, DRIVEWAY & PARKING LOTS REMOVAL, VARIABLE THICKNESS 5,245 SF
110-0100-0011 PAVEMENT, CONCRETE REMOVAL, SIDEWALK, DRIVEWAYS, PADS 4" - 6" THICK 10 SY
110-4000 FENCE, REMOVAL, ALL TYPES 1,473 LF
120-0031 EXCAVATE, (DETENTION POND, MITIGATION AREA, CHANNEL &/OR DITCH) 251 CY
120-0036 EXCAVATION FOR ROADWAY AND BASE INSTALLATION 711 CY
160-0012 STABILIZATION, TYPE B 12.5, VARIABLE THICKNESS 984 SY
204-1000 BASE, RECYCLED CONCRETE AGGREGATE, MINIMUM LBR 150, VARIABLE THICKNESS 164 CY
334-3125-000 SUPERPAVE ASPHALT CONCRETE, TYPE SP 12.5, FINE, TRAFFIC LEVEL C, VARIABLE THICKNESS 1,006 TN
350-0206 PAVEMENT, CEMENT CONCRETE, 6" THICK, DRIVEWAYS 103 SY
380-3490 MILLING EXISTING ASPHALT PAVEMENT, 2" THICKNESS OR LESS, FULL WIDTH 9,150 SY
515-8801 HANDRAIL, STEEL PIPE, GALVANIZED, FDOT INDEX 515-080, PEDESTRIAN HEIGHT 380 LF
520-1305-1012 CURB & GUTTER, CONCRETE, HEADER, PCED INDEX 1305 1,715 LF
520-2000-4000 CURB & GUTTER, CONCRETE, FDOT TYPE D 1,241 LF
550-10-215 FENCING, TYPE B, 0.5-5.0', BLACK VINYL COATED CHAIN LINK WITH TOP RAIL (4' HEIGHT) 1,075 LF
550-60-283 FENCE GATE, TYPE B, SLIDING/CANTILIVER, 12.1-18' OPENING, BLACK VINYL COATED CHAIN LINK (4'
HEIGHT) 1 LS
710-23-61 TRAFFIC STRIPE-SOLID,WHITE/BLACK/BLUE,6" 4,230 LF
710-25-241 TRAFFIC STRIPE SOLID, WHITE / BLACK 24" 10 LF
710-6 DIRECTIONAL ARROWS, PAINTED 9 EA
710-7 PAVEMENT MESSAGE, PAINTED 8 EA
810-3 WHEEL STOP, CONCRETE, IN-KIND, BLUE, ADA 9 EA
810-5 WHEEL STOP, CONCRETE, REMOVE 498 EA
L-1 LANDSCAPING SHELL, 6" 216 CY
SS-333900-302-K002 ADJUST MANHOLE RIM & COVER TO FINISHED GRADE (IN PAVEMENT) 1 EA
OTHER ITEMS
999-0000 BENCH, REMOVE 4 EA
999-0001 BENCH, IN-KIND 4 EA
999-0002 WATER FOUNTAIN, REMOVE 1 EA
999-0003 WATER FOUNTAIN, MOST DEPENDABLE FOUNTAINS, INC. MODEL 10135 SMSS OR APPROVED EQUAL 1 EA
999-0004 GATE, REMOVE 1 EA
999-0005 WEED BARRIER 11,689 SF
999-0006 DUMPSTER ENCLOSURE WOOD PANELS AND GATE REPAIR 1 LS
999-0007 BICyCLE RACK, 5 LOOPS 7 BIKE CAPACITY, BELSON MODEL - CBBR-7URI-BK OR APPROVED EQUAL 1 EA
999-0008 TREE PROTECTION 1,606 LF
TAMPA, FLORIDA
Feet 60300 15
TAMPA, FLORIDA
MULTICORELINK:90018G1-A4-PLAN-9
MULTICORELINK:90018G1-A4-PLAN-10
MULTICORELINK:90018G1-A4-PLAN-11
MULTICORELINK:90018G1-A4-PLAN-12
MULTICORELINK:90018G1-A4-PLAN-13
MULTICORELINK:90018G1-A4-DEMO-4
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-6
MULTICORELINK:90018G1-A4-DEMO-7
MULTICORELINK:90018G1-A4-DEMO-8
20100 5
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-6
MULTICORELINK:90018G1-A4-DEMO-7
20100 5
MULTICORELINK:90018G1-A4-DEMO-6
MULTICORELINK:90018G1-A4-DEMO-4
MULTICORELINK:90018G1-A4-DEMO-6
MULTICORELINK:90018G1-A4-DEMO-7
MULTICORELINK:90018G1-A4-DEMO-8
MULTICORELINK:90018G1-A4-DEMO-4
20100 5
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-4
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-7
20100 5
MULTICORELINK:90018G1-A4-DEMO-4
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-4
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-6
20100 5
MULTICORELINK:90018G1-A4-DEMO-6
MULTICORELINK:90018G1-A4-DEMO-7
MULTICORELINK:90018G1-A4-DEMO-4
MULTICORELINK:90018G1-A4-DEMO-5
MULTICORELINK:90018G1-A4-DEMO-6
20100 5
MULTICORELINK:90018G1-A4-PLAN-13
20100 5
MULTICORELINK:90018G1-A4-PLAN-9
MULTICORELINK:90018G1-A4-PLAN-9
MULTICORELINK:90018G1-A4-PLAN-13
MULTICORELINK:90018G1-A4-PLAN-9
20100 5
MULTICORELINK:90018G1-A4-PLAN-9
MULTICORELINK:90018G1-A4-PLAN-9
MULTICORELINK:90018G1-A4-PLAN-9
I. SITE DESCRIPTION
A. CONSTRUCTION ACTIVITY
VARIES DEPENDING ON THE SPECIFIC SITE.
TO INCLUDE: MILL & RESURFACE, RESTRIPING, SIDEWALK AND CURB
REPAIR/REPLACEMENT, DRAINAGE DESILTING AND UTILITY
ADJUSTMENTS.
B. PROJECT LIMITS
VARIES DEPENDING ON THE SPECIFIC WORK ORDER.
C. PROJECT DESCRIPTION
FEDERAL SITE INFRASTRUCTURE REPAIR.
D. MAJOR SOIL DISTURBING ACTIVITIES
CLEARING, GRUBBING, EXCAVATION, AND GRADING ACTIVITIES
E. TOTAL PROJECT AREA: 2.98 ACRES
TOTAL AREA TO BE DISTURBED: 2.62 ACRES
F. RUNOFF DATA
THE RUNOFF WILL NOT CHANGE IF NO IMPERVIOUS IS ADDED. IF IMPERVIOUS IS ADDED,
A PERMIT WILL BE OBTAINED BY THE COUNTY PRIOR TO CONSTRUCTION.
PRE-CONSTRUCTION (WEIGHED RUN-OFF COEFFICIENT,
OR CAN USE PRE-DEV. Q IN CFS)
POST-CONSTRUCTION (WEIGHTED RUN-OFF COEFFICIENT,
OR CAN USE POST-DEV. Q IN CFS)
G. SOIL DATA
VARIES (ATTACH USA-SCS SOILS MAP AND LEGEND WITH PROJECT AREA DELINEATED, OR
STATE SOIL TYPES)
H. DRAINAGE AREA (ATTACH DRAINAGE MAP OR PROVIDE DRAINAGE AREA IN ACRES)
VARIES
I. RECEIVING WATERS
THE RECEIVING BODY IS: GULF OF AMERICA
J. WETLANDS AREAS
WHEN WETLANDS ARE ENCOUNTERED, A PERMIT WILL BE OBTAINED BY THE COUNTY
PRIOR TO CONSTRUCTION.
II. CONTROLS
ALL CONTROLS SHALL BE CONSISTENT WITH PERFORMANCE STANDARDS FOR EROSION AND
SEDIMENT CONTROL AND STORM-WATER TREATMENT SET FORTH IN s.62-40.432, F.A.C., THE STATE
OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL, THE
APPLICABLE STORM-WATER OR ENVIRONMENTAL RESOURCE PERMITTING REQUIREMENTS OF THE
DEPARTMENT OR A WATER MANAGEMENT DISTRICT, THE GUIDELINES CONTAINED IN THE FLORIDA DEVELOPMENT MANUAL: A GUIDE TO SOUND LAND AND WATER MANAGEMENT (DEP, 1988) AND ANY
SUBSEQUENT AMENDMENTS.
A. SEQUENCE OF MAJOR ACTIVITIES
1. INSTALL E&S MEASURES AS DIRECTED BY ENGINEER.
2. STABILIZE, MAINTAIN, AND REPLACE E&S AS DIRECTED BY ENGINEER.
3. PERFORM WEEKLY INSPECTION OF E&S AND AFTER EVERY 12" RAINFALL
4. REMOVE ALL SEDIMENTS THAT HAVE MIGRATED OFF SITE AS DIRECTED BY THE ENGINEER.
5. WHEN CONSTRUCTION ACTIVITY IS COMPLETE AND THE SITE IS STABILIZED, REMOVE
EROSION PROTECTION DEVICES AND CONSTRUCTION ENTRANCE AS REQUIRED.
B. EROSION AND SEDIMENT CONTROL CONSTRUCTION ACTIVITIES
THE CONTRACTOR IS REQUIRED TO REVIEW THE SITE SPECIFIC EROSION CONTROL PLAN. THE
CONTRACTOR MAY ALSO BE REQUIRED TO MODIFY THE PLAN OR MATERIALS TO ADAPT TO
SEASONAL VARIATIONS OR SITE CONDITIONS. CONTRACTOR WILL COMPLY WITH E & S PLAN. ANY MODIFICATIONS TO THIS PLAN MUST BE SIGNED BY A PROFESSIONAL ENGINEER REPRESENTING THE CONTRACTOR. THE EROSION CONTROL DEVICES, DETAILS, AND NOTES APPLICABLE TO THESE
ACTIVITIES ARE SPECIFIED IN THE PLANS. THE PROJECT ENGINEER IS RESPONSIBLE FOR
DETERMINING IF ADDITIONAL CONTROLS ARE THE PROJECT ENGINEER MAY REQUIRE ADDITIONAL
CONTROLS TO MEET STANDARDS AND REGULATIONS.
PERFORM WEEKLY INSPECTION OF EROSION AND SEDIMENT CONTROLS AND AFTER EVERY 12"
RAINFALL
REMOVE ALL SEDIMENTS THAT HAVE MIGRATED OFF SITE AND RESTORE AFFECTED AREAS AS
DIRECTED BY THE ENGINEER
C. STABILIZATION PRACTICES
DURING CONSTRUCTION THE CONTRACTOR WILL PROVIDE STABILIZATION FOR AREAS WHICH HAVE
BEEN CLEARED AND NOT REWORKED WITHIN FOURTEEN (14) CALENDAR DAYS. THE CONTRACTOR
MAY UTILIZE TEMPORARY SEEDING OR TEMPORARY SODDING IN ACCORDANCE WITH SECTION 570
OF THE "FDOT STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION".
X TEMPORARY SODDING
X TEMPORARY GRASSING
X PERMANENT SODDING OR SEEDING
X PRESERVATION OF NATURAL RESOURCES
X BUFFER ZONES
D. STRUCTURAL PRACTICES
X SYNTHETIC BALES (LF)
X ARTIFICIAL COVERINGS/ ROLLED EROSION CONTROL PRODUCTS (SY)
X INLET PROTECTION SYSTEM (EA)
X LITTER REMOVAL AND DISPOSAL (AC)
X MOWING (AC)
SLOPE DRAINS (TEMPORARY)/ RUNOFF CONTROL STRUCTURES (LF)
X SOIL TRACKING PREVENTION DEVICE (EA)
X SEDIMENT BASINS/CONTAINMENT SYSTEMS (EA)
X SEDIMENT BASIN/ CONTAINMENT SYSTEM CLEANOUT (EA)
X FLOATING TURBIDITY BARRIER (LF)
X STAKED SILT FENCE (LF)
CHEMICAL TREATMENT - POWDERED (SY)
CHEMICAL TREATMENT (FLOC LOGS, DRUMS OF PRODUCT) (EA)
OTHER
E. DESCRIPTION OF STORM WATER MANAGEMENT
STORM WATER COLLECTION WILL BE PROVIDED FOR THE URBAN ROADWAY PORTION OF
THIS PROJECT WITHIN THE CLOSED COLLECTION AND TREATMENT SYSTEM. THE RURAL
SECTION WILL USE THE EXISTING ROADSIDE SWALES FOR CONVEYANCE AND TREATMENT.
EVENTUAL OUTFALL WILL REMAIN.
F. WASTE DISPOSAL
THE CONTRACTOR SHALL PROVIDE LITTER CONTROL AND COLLECTION WITHIN THE PROJECT
BOUNDARIES DURING CONSTRUCTION ACTIVITIES. ANY CHEMICAL CONTAINERS SHALL BE
DISPOSED OF BY THE CONTRACTOR ACCORDING TO EPA'S STANDARD PRACTICES AS DETAILED BY
THE MANUFACTURER. NO SOLID MATERIALS INCLUDING BUILDING & CONSTRUCTION MATERIALS
SHALL BE DISCHARGED TO WETLANDS OR BURIED ON SITE. ALL WASTE MATERIAL WILL BE
COLLECTED AND STORED IN DUMPSTERS PER LOCAL SOLID WASTE REGULATIONS. ALL TRASH AND CONSTRUCTION DEBRIS FROM THE SITE WILL BE DEPOSITED IN THE DUMPSTER. THE DUMPSTER WILL BE EMPTIED A MINIMUM OF TWICE A WEEK OR MORE OFTEN IF NECESSARY, AND THE TRASH
WILL BE HAULED TO THE APPROPRIATE COUNTY LOCATION FOR DUMPING.
G. OFFSITE VEHICLE TRACKING
STABILIZED CONSTRUCTION ENTRANCES SHALL BE PROVIDED TO HELP REDUCE VEHICLE
TRACKING OF SEDIMENTS AND INSPECTED/MAINTAINED DAILY. THE PAVED STREETS WILL BE
CLEANED AS DIRECTED BY THE CONSTRUCTION INSPECTOR AND ENGINEER TO REMOVE ANY
EXCESS MUD, DIRT OR ROCK TRACKED FROM THE SITE. DUMP TRUCKS HAULING MATERIAL FROM
OR TO THE SITE WILL BE COVERED WITH A TARPAULIN AT ALL TIMES.
H. SANITARY WASTE
FDOT STANDARD SPEC. FOR ROAD AND BRIDGE CONSTRUCTION" SECTION 7 - 6 "SANITARY
PROVISIONS. "THE CONTRACTOR SHALL PROVIDE AND MAINTAIN, IN A NEAT AND SANITARY
CONDITION, SUCH ACCOMMODATION FOR THE USE OF HIS EMPLOYEES AS ARE NECESSARY TO
COMPLY WITH THE REQUIREMENTS AND REGULATIONS OF THE STATE AND LOCAL BOARDS OF
HEALTH. COMMIT NO PUBLIC NUISANCE."
I. HAZARDOUS WASTE
THE CONTRACTOR WILL IMMEDIATELY NOTIFY THE COUNTY IN WRITING IF ANY HAZARDOUS WASTE
MATERIAL IS ENCOUNTERED DURING SITE INVESTIGATION OR CONSTRUCTION.
THE CONTRACTOR WILL ALSO BE RESPONSIBLE FOR NOTIFYING THE FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION (FDEP) WITHIN 24 HOURS OF THE DISCOVERY.
ALL HAZARDOUS WASTE MATERIALS, IF ENCOUNTERED, WILL BE DISPOSED OF IN THE MANNER
SPECIFIED BY LOCAL, STATE, AND FEDERAL REGULATIONS. THE CONTRACTOR WILL BE
RESPONSIBLE FOR SEEING THAT THESE PRACTICES ARE FOLLOWED.
IN CASE OF DISPOSING ANY HAZARDOUS WASTE MATERIAL FOLLOWING LOCAL, STATE, AND
FEDERAL REGULATIONS, A COPY OF DISPOSAL MANIFEST HAS TO BE PROVIDED TO THE COUNTY IN
TIMELY FASHION.
PERMITTEE CERTIFICATION
I CERTIFY UNDER PENALTY OF LAW THAT THIS DOCUMENT AND ALL ATTACHMENTS WERE PREPARED UNDER MY DIRECTION OR SUPERVISION IN ACCORDANCE WITH A SYSTEM DESIGNED TO ASSURE THAT QUALIFIED PERSONNEL PROPERLY GATHERED AND EVALUATED THE INFORMATION SUBMITTED. BASED ON MY INQUIRY OF THE PERSON OR PERSONS WHO MANAGE THE SYSTEM, OR THOSE PERSONS DIRECTLY RESPONSIBLE FOR GATHERING THE INFORMATION, THE INFORMATION SUBMITTED IS, TO THE BEST OF MY KNOWLEDGE AND BELIEF, TRUE, ACCURATE, AND COMPLETE. I AM AWARE THAT THERE ARE SIGNIFICANT PENALTIES FOR SUBMITTING FALSE INFORMATION, INCLUDING POSSIBILITY OF FINE AND IMPRISONMENT FOR KNOWING
VIOLATIONS.
MATTHEW R. IVIE, P.E., ENGINEER OF RECORD DATE
CONTRACTOR CERTIFICATION
I CERTIFY UNDER PENALTY OF LAW THAT I UNDERSTAND, AND SHALL COMPLY WITH , THE TERMS AND CONDITIONS OF THE STATE OF FLORIDA GENERIC PERMIT FOR STORMWATER DISCHARGE FROM LARGE AND SMALL CONSTRUCTION ACTIVITIES AND THIS STORMWATER POLLUTION PREVENTION PLAN PREPARED
THEREUNDER.
GENERAL CONTRACTOR NAME & TITLE DATE
COMPANY NAME .
COMPANY STREET ADDRESS .
CITY, STATE, ZIP CODE .
J. WATER QUALITY MONITORING (MIXING ZONES)
THE WATER THAT WILL BE SAMPLED FOR STATE WATER QUALITY STANDARDS FOR CONSTRUCTION
ACTIVITIES PROHIBIT A TURBIDITY INCREASE OF GREATER THAN 29 NTU'S ABOVE AMBIENT
CONDITIONS AT THE COMPLIANCE LOCATION OF THE MIXING ZONES. TO MAINTAIN THIS STANDARD, TURBIDITY MONITORING SHALL OCCUR DURING ALL IN-WATER CONSTRUCTION ACTIVITIES AT EACH
COMPLIANCE AND BACKGROUND STATION. THE FOLLOWING PROCEDURE SHALL BE USED:
FREQUENCY: TWICE A DAY, AT LEAST 4 HOURS APART DURING FREQUENCY OF ACTUAL
CONSTRUCTION OPERATIONS.
LOCATIONS: ALL STATIONS SHALL BE SAMPLED AT 2 FEET ABOVE LOCATIONS THE BOTTOM, AT MID-DEPTH, AND AT THE SURFACE, OR AS DIRECTED BY PERMITTING AGENCIES. IF WATER IS
LESS THAN THREE FEET DEEP, ONLY MID-DEPTH SAMPLES ARE REQUIRED.
BACKGROUND: 500 FEET UP-CURRENT FROM THE CONSTRUCTION BACKGROUND ACTIVITY AND
OUTSIDE OF ANY TURBIDITY PLUME FROM THE CONSTRUCTION ACTIVITY.
COMPLIANCE: 300 FEET DOWN CURRENT FROM THE CONSTRUCTION COMPLIANCE ACTIVITY WITHIN
ANY VISIBLE TURBIDITY PLUME, OR AS DIRECTED BY PERMITTING AGENCIES.
METHOD: ALL SAMPLES SHALL BE COLLECTED ON SITE VIA GRAB METHOD AND TURBIDITY READ, USING A PROPERLY CALIBRATED TUBIDIMETER ON SITE, TAKING 3 READINGS AT EACH SITE.
REPORTING: ALL MONITORING DATA SHALL BE SUBMITTED WITHIN ONE REPORTING WEEK OF
ANALYSIS WITH DOCUMENTS CONTAINING THE FOLLOWING INFORMATION:
1. PERMIT NUMBER
2. DATES OF SAMPLING AND ANALYSIS
3. LOCATION OF SAMPLE (I.E., STATION AND WATER COLUMN LOCATION)
4. A STATEMENT DESCRIBING THE METHODS USED IN COLLECTION, HANDLING,
5. STORAGE, AND ANALYSIS OF THE SAMPLES
6. SAMPLE RESULTS
7. A MAP INDICATING THE SAMPLING LOCATIONS
8. STATEMENT, BY THE INDIVIDUAL RESPONSIBLE FOR IMPLEMENTATION OF THE SAMPLING PROGRAM, CONCERNING THE AUTHENTICITY, PRECISION, LIMITS OF DETECTION AND ACCURACY OF DATA.
MONITORING REPORTS SHALL INCLUDE INFORMATION ON THE GENERAL ANTECEDENT WEATHER
CONDITIONS.
IF MONITORING REVEALS VIOLATIONS OF THE STATE WATER QUALITY STANDARD FOR TURBIDITY, CONSTRUCTION ACTIVITIES SHALL CEASE IMMEDIATELY AND NOT RESUME UNTIL CORRECTIVE
MEASURES HAVE BEEN TAKEN AND TURBIDITY HAS RETURNED TO ACCEPTABLE LEVELS. ANY
SUCH OCCURRENCE SHALL ALSO BE IMMEDIATELY REPORTED TO THE REGULATORY AGENCIES. IN
THE EVENT THAT STATE WATER QUALITY STANDARDS ARE NOT ATTAINED, THE CONTRACTOR
SHALL IMPLEMENT A CONTINGENCY PLAN WHICH COMPLIES WITH THE PROJECT SWFWMD/FDEP
ERP AND PINELLAS COUNTY NPDES REQUIREMENTS AT NO ADDITIONAL COST TO THE COUNTY.
ANY FINES SHALL BE RESPONSIBILITY OF THE CONTRACTORS.
K. APPROVED STATE, LOCAL PLANS, OR STORM WATER PERMITS
NONE
III. MAINTENANCE
A. ALL OF THE CONTROLS SHALL BE MAINTAINED AT ALL TIMES.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR DAILY INSPECTION AND MAINTENANCE OF ALL
PERMANENT AND TEMPORARY EROSION CONTROL DEVICES THROUGHOUT ALL CONSTRUCTION
PHASES OF THE PROJECT. MAINTENANCE SHALL BE IN ACCORDANCE WITH THE STATE OF FLORIDA
EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL, PINELLAS COUNTY
"STANDARD TECHNICAL SPECIFICATIONS FOR ROADWAY AND RELATED CONSTRUCTION", AND THE
PROJECT CONSTRUCTION CONTRACT.
B. INSPECTION
THE COUNTY INSPECTOR SHALL BE RESPONSIBLE FOR COMPLETING THE PINELLAS COUNTY
NPDES / SWPPP CONSTRUCTION INSPECTION REPORT AFTER ANY 12" RAINFALL OR WEEKLY, IF NO RAIN EVENT OCCURRED. IT IS THE CONTRACTOR'S RESPONSIBILITY TO MAINTAIN RAIN GAUGES ON
THE PROJECT SITE AND RECORD WEEKLY RAIN FALL. THE COUNTY INSPECTOR SHALL NOTIFY
PINELLAS COUNTY DIVISION OF ENVIRONMENTAL MANAGEMENT OF ANY NON-COMPLIANCE PER
SECTION 58-244 TO 246 OF THE PINELLAS COUNTY CODE.
C. NON-STORM WATER DISCHARGES
IT IS EXPECTED THAT THE FOLLOWING NON-STORM WATER DISCHARGES MAY OCCUR FROM THE
SITE DURING THE CONSTRUCTION PERIOD:
· WATER FROM WATER LINE FLUSHING
· PAVEMENT WASH WATERS (WHERE NO SPILL OR LEAKS OF VEHICLE AND HAZARDOUS
MATERIALS HAVE OCCURRED)
· UNCONTAMINATED GROUNDWATER FROM DE-WATERING ACTIVITIES
ALL NON-STORM WATER DISCHARGES SHOULD BE CONTAINED ON SITE AND DIRECTED TO
SEDIMENT TREATMENT BMPs. UNTREATED OFF SITE DISCHARGES WILL BE REPORTED TO THE
COUNTY INSPECTOR AND PINELLAS COUNTY DIVISION OF ENVIRONMENTAL MANAGEMENT FOR
FURTHER INVESTIGATION. IF CONTAMINATED SOIL OR GROUNDWATER IS ENCOUNTERED,
DEWATERING SHOULD CEASE IMMEDIATELY AND THE ENGINEER WILL BE CONTACTED.
D. MATERIAL MANAGEMENT PRACTICES
THE FOLLOWING ARE THE MATERIAL HANDLING PRACTICES THAT WILL BE USED TO REDUCE THE
RISK OF SPILLS OR OTHER ACCIDENTAL EXPOSURE OF MATERIALS AND SUBSTANCES TO STORM
WATER RUNOFF:
1. THE FOLLOWING GOOD HOUSEKEEPING PRACTICES SHALL BE FOLLOWED ON-SITE
DURING THE CONSTRUCTION PROJECT.
· STORE ONLY ENOUGH PRODUCT REQUIRED TO DO THE JOB ON SITE.
· ALL MATERIALS STORED ON SITE SHALL BE STORED IN A NEAT, ORDERLY MANNER IN THEIR
ORIGINAL MANUFACTURER'S LABELED CONTAINERS UNDER A ROOF OR OTHER CONTAINED
ENCLOSURE.
· SUBSTANCES SHALL NOT BE MIXED WITH ONE ANOTHER UNLESS RECOMMENDED BY THE
MANUFACTURER.
· WHENEVER POSSIBLE, ALL OF A PRODUCT SHALL BE USED BEFORE DISPOSING OF THE
CONTAINER. MANUFACTURERS' RECOMMENDATIONS FOR PROPER USE AND DISPOSAL SHALL
BE FOLLOWED.
· THE SITE SUPERINTENDENT SHALL INSPECT DAILY TO ENSURE PROPER USE AND DISPOSAL
OF MATERIALS ON-SITE.
2. THESE PRACTICES ARE USED TO REDUCE THE RISKS ASSOCIATED WITH
HAZARDOUS MATERIALS.
· PRODUCTS WILL BE KEPT IN ORIGINAL CONTAINERS UNLESS THEY ARE NOT RE-SEALABLE.
· SECONDARY CONTAINMENT SHALL BE PROVIDED FOR ALL OPENED CONTAINERS. ORIGINAL
LABELS AND MATERIAL SAFETY DATA SHALL BE KEPT ON-SITE ON THE CONSTRUCTION
OFFICE TRAILER.
· IF SURPLUS PRODUCT MUST BE DISPOSED OF, MANUFACTURERS OR LOCAL STATE
RECOMMENDED METHODS OF PROPER DISPOSAL SHALL BE FOLLOWED.
· THE CONTRACTOR MUST IDENTIFY A DESIGNATED FUEL TANK STORAGE AREA, AWAY FROM
DRAINAGE STRUCTURES, PONDS, BASINS, AND WETLANDS, WITH SECONDARY CONTAINMENT
(SPILL COLLECTION).
3. CONCRETE TRUCKS
· CONTRACTOR SHALL DESIGNATE AN AREA AWAY FROM DRAINAGE STRUCTURES, PONDS,
BASINS, AND WETLANDS FOR DISCHARGE OF SURPLUS CONCRETE OR DRUM WASH WATER
AND SHALL INSTALL A CONTAINMENT BERM AROUND THIS AREA TO PREVENT RUNOFF TO THE
REMAINDER OF THE SITE.
· HARD DEBRIS SHALL BE DISPOSED OF BY CONTRACTOR UPON COMPLETION OF THE PROJECT.
· DISPOSAL OF CONCRETE SLURRY DIRECTLY INTO PUBLIC DRAINAGE SYSTEMS IS A VIOLATION
OF THE "ILLICIT DISCHARGE" PROVISION OF THE PINELLAS COUNTY LAND DEVELOPMENT
CODE AND SECTION 58-244 OF THE PINELLAS COUNTY CODE.
· SECTION 58-239 OF THE PINELLAS COUNTY CODE AUTHORIZES PENALTIES OF UP TO
$10,000.00 FOR EACH OFFENSE.
4. SPILL CONTROL PRACTICES
IN ADDITION TO THE GOOD HOUSEKEEPING AND MATERIALS MANAGEMENT PRACTICES DISCUSSED IN THE PREVIOUS SECTIONS OF THIS PLAN, THE FOLLOWING PRACTICES WILL BE FOLLOWED FOR
SPILL PREVENTION AND CLEANUP.
· MANUFACTURERS' RECOMMENDED METHODS FOR SPILL CLEANUP WILL BE CLEARLY POSTED
AND SITE PERSONNEL WILL BE MADE AWARE OF THE PROCEDURES AND THE LOCATION OF
THE INFORMATION CLEANUP SUPPLIES.
· ALL SPILLS WILL BE CLEANED UP IMMEDIATELY AFTER DISCOVERY.
· THE SPILL AREA WILL BE KEPT WELL VENTILATED AND PERSONNEL WILL WEAR APPROPRIATE
PROTECTIVE CLOTHING TO PREVENT INJURY FROM CONTACT WITH A HAZARDOUS
SUBSTANCE.
· SPILLS OF TOXIC OR HAZARDOUS MATERIAL WILL BE REPORTED TO THE APPROPRIATE STATE
OR LOCAL GOVERNMENT AGENCY, REGARDLESS OF THE SIZE.
· THE SPILL PREVENTION PLAN WILL BE PREPARED BY THE CONTRACTOR AND KEPT IN THE
CONSTRUCTION OFFICE TRAILER AND WILL INCLUDE MEASURES TO PREVENT THIS TYPE OF
SPILL FROM REOCCURRING AND HOW TO CLEAN UP THE SPILL IF THERE ARE OTHERS. A
DESCRIPTION OF THE SPILL, WHAT CAUSED IT, AND THE CLEANUP MEASURES WILL ALSO BE
INCLUDED. ALL SPILLS AND RESPONSES WILL BE REPORTED TO THE APPROPRIATE AGENCY.
· THE SITE SUPERINTENDENT WILL BE THE SPILL PREVENTION AND CLEANUP COORDINATOR.
HE WILL DESIGNATE OTHER SITE PERSONNEL WHO WILL RECEIVE SPILL PREVENTION AND
CLEANUP TRAINING. THESE INDIVIDUALS WILL EACH BECOME RESPONSIBLE FOR A
PARTICULAR PHASE OF PREVENTION AND CLEANUP. THE NAMES OF RESPONSIBLE SPILL
PERSONNEL WILL BE POSTED IN THE MATERIAL STORAGE AREA AND IN THE OFFICE TRAILER
ON SITE.
· USE AND CHARACTERISTICS OF FUEL OR CHEMICAL STORAGE TANK ON SITE SHALL COMPLY
WITH ALL RELATED FEDERAL, STATE, AND LOCAL REGULATIONS. STORAGE TANKS MUST BE
LOCATED AS FAR AS POSSIBLE FROM ANY DRAINAGE STRUCTURES, DITCHES, AND/OR
SURFACE WATERS. IN ADDITION, THE CONTRACTOR MUST PROVIDE A SECONDARY
CONTAINMENT WITH A LINER CHEMICALLY RESISTANT TO THE FUEL OR CHEMICAL STORED ON
SITE. THE SECONDARY CONTAINMENT MUST BE SIZED TO CONTAIN MINIMUM OF ONE AND A
HALF TIME THE TOTAL CAPACITY OF STORAGE TANK BEING USED. CONTRACTOR HAS TO
PROVIDE A DAILY INSPECTION LOG FOR THE SECONDARY CONTAINMENT WITH INDICATION OF
DATE, INSPECTORS NAME AND INSPECTION REPORT. FURTHERMORE, ANY CONTAMINATION
HAS TO BE IMMEDIATELY CONTAINED AND THE COUNTY INSPECTOR MUST BE NOTIFIED OF
THE NATURE AND EXTEND OF THE CONTAMINATION.
PERMITTEE CERTIFICATION
I CERTIFY UNDER PENALTY OF LAW THAT THIS DOCUMENT AND ALL ATTACHMENTS WERE PREPARED UNDER MY DIRECTION OR SUPERVISION IN ACCORDANCE WITH A SYSTEM DESIGNED TO ASSURE THAT QUALIFIED PERSONNEL PROPERLY GATHERED AND EVALUATED THE INFORMATION SUBMITTED. BASED ON MY INQUIRY OF THE PERSON OR PERSONS WHO MANAGE THE SYSTEM, OR THOSE PERSONS DIRECTLY RESPONSIBLE FOR GATHERING THE INFORMATION, THE INFORMATION SUBMITTED IS, TO THE BEST OF MY KNOWLEDGE AND BELIEF, TRUE, ACCURATE, AND COMPLETE. I AM AWARE THAT THERE ARE SIGNIFICANT PENALTIES FOR SUBMITTING FALSE INFORMATION, INCLUDING POSSIBILITY OF FINE AND IMPRISONMENT FOR KNOWING
VIOLATIONS.
MATTHEW R. IVIE, P.E., ENGINEER OF RECORD DATE
CONTRACTOR CERTIFICATION
I CERTIFY UNDER PENALTY OF LAW THAT I UNDERSTAND, AND SHALL COMPLY WITH , THE TERMS AND CONDITIONS OF THE STATE OF FLORIDA GENERIC PERMIT FOR STORMWATER DISCHARGE FROM LARGE AND SMALL CONSTRUCTION ACTIVITIES AND THIS STORMWATER POLLUTION PREVENTION PLAN PREPARED
THEREUNDER.
GENERAL CONTRACTOR NAME & TITLE DATE
COMPANY NAME
COMPANY STREET ADDRESS
CITY, STATE, ZIP CODE
SIDEWALK
CLOSEDDETOUR
DETOUR
SIDEWALK
CLOSED
ROAD
CLOSED
SID
EW
AL
K
CL
OSE
D
Feet 80400 20
EDGE OF PAVEMENT
72"
7"
24"
2"
5"
3"
1'-6"
6"
EXIST. SIDEWALK TO REMAIN EXIST. ADA SIGNS TO REMAIN
PRECAST WHEEL STOP (TYP)
60°
WHITE
BL
U
E BL
U
E
5' 6" 6"
2" 6" 6"
2"
BL
U
E W H
IT
E
6" 6" 2"
#4 BAR
18" DEEP
2 78" OD
GALVANIZED
STEEL PIPE
1 78" OD
GALVANIZED
STEEL PIPE
(SS40)
GROUND LEVEL
CONCRETE
2 78" OD
GALVANIZED
STEEL PIPE
SHUT-IT DUAL
SEALED BEARING HINGES
BARRIER
RECEIVER POST
4'X4' SQ. P.T. WOOD POST
SET IN 12" DIA. X 36" DEEP
CONC. FOOTING
ATTACH WOOD NAILER
EA. DIRECTIONAL
BORE HOLES IN CONCRETE TO
ACCEPT CANE BOLTS FOR BOTH
OPEN & CLOSED POSITIONS
4"X4"X9'-0" MAX. LONG WOOD POST
CAST INTO 3'-0"X12" DIA.
CONCRETE FOUNDATION
1"X6" P.T. WOOD FENCE BOARDS
OVER P.T. WOOD NAILERS.
2"X4" P.T. WOOD NAILERS ANCHORED
TO WOOD POSTS W/(2) 3" LONG S.S.
SCREWS COUNTERSINK BOLTS FLUSH
W/WOOD NAILERS BY RITEGUARD OR
APPROVED EQUAL
EXIST. CONCRETE SLAB
(2) 6d NAILS (TYP)
EXISTING CONCRETE SLAB
EXIST. GRADE
1"x6" P.T. WOOD FENCE
BOARDS. MAX. 14" SPACE
BETWEEN BOARDS
(3) STAINLESS STEEL
HEAVY DUTY HINGES2"X4" P.T. WOOD
NAILERS
| Sheets and Views |
| 1 KEY SHEET |