This solicitation requests proposals for an Alert Facility and Alert Apron project at NAS JRB New Orleans. The project includes construction of an Aerospace Control Alert Facility and Alert Apron utilizing conventional methods. The Alert Facility requires two aircraft shelters with drive-through capability, alert quarters, and an Alternate Command Post. The Alert Apron requires utilities, communications support, exterior lighting, security upgrades, and a parking apron for two alert ready aircraft. The acquisition will result in a firm-fixed price design-bid-build construction contract with a completion schedule of 1300 calendar days from award. The total project magnitude is between $25 million and $100 million. The solicitation is unrestricted and open to all responsible sources, and is subject to World Trade Organization and Free Trade Agreement terms. Proposals are due under solicitation number N69450-20-R-0129.

View the file

Other files for this federal contract opportunity

Other files attached to Alert Facility and Alert Apron, newest first.
File Type Posted
N6945020R0129_Amendment_0007.pdf PDF
C201 SITE PLAN_Amd06_2020-10-21.pdf PDF
N69450-20-R-0129_AMENDMENT_0006.pdf PDF
C511 STORM DRAINAGE DETAILS_Amd06_2020-10-21.pdf PDF
N6945020R0129_0005.pdf PDF
N6945020R0129_Amendment_0004.pdf PDF
PROJECT TOC Amendment 0003.pdf PDF
ESD106 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 11 20 Amendment 0003.pdf PDF
ESD107 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 12 16 Amendment 0003.pdf PDF
ESD108 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
ESD109 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 01 13.62 Amendment 0003.pdf PDF
32 11 23 Amendment 0003.pdf PDF
N6945020R0129_0003.pdf PDF
E506 - ELECTRICAL DETAILS_Amd0003_2020-10-06.pdf PDF
A351 - SHELTER_1 BUILDING SECTIONS Amd 0002.pdf PDF
P402 - ENLARGED CREW SANITARY PLAN SOUTH Amd 0002.pdf PDF
CA200 - APRON GEOMETY AND UTILITY PLAN Amd 0002.pdf PDF
A602 - DOOR_WINDOW_LOUVER DETAILS Amd 0002.pdf PDF
C201 - SITE PLAN Amd 0002.pdf PDF
C200 - OVERALL SITE PLAN Amd 0002.pdf PDF
08 34 02 Amendment 0002.pdf PDF
N6945020R0129_Amendment_0002.pdf PDF
A352 - SHELTER_ BUILDING SECTIONS Amd 0002.pdf PDF
10 26 00 Amendment 0002.pdf PDF
10 21 23.16 Amendment 0002.pdf PDF
S154 - SHELTER_2 SLAB PLAN Amd 0002.pdf PDF
10 51 13 Amendment 0002.pdf PDF
01 30 01_00 22 Amendment 0002.pdf PDF
S152 SHELTER _1 SLAB PLAN_Amd01_2020-09-14.pdf PDF
P403 ENLARGED CREW PIPING PLAN NORTH_Amd01_2020-09-14.pdf PDF
E503 ELECTRICAL DETAILS_Amd01_2020-09-14.pdf PDF
26 20 00 Amendment 0001.pdf PDF
ESL101 EXTERIOR LIGHTING PLAN_Amd01_2020-09-14.pdf PDF
S001 GENERAL NOTES_DESIGN CRITERIA_Amd01_2020-09-14.pdf PDF
P102 OVERALL ECP PLUMBING FLOOR PLAN_Amd01_2020-09-14.pdf PDF
P103 OVERALL SHELTER 1 PLUMBING PLAN_Amd01_2020-09-14.pdf PDF
NOLA_Alert_R0129_SiteVisit_Roster.pdf PDF
S154 SHELTER _2 SLAB PLAN_Amd01_2020-09-14.pdf PDF
N6945020R0129_Amendment_0001.pdf PDF
P502 PLUMBING DETAILS_Amd01_2020-09-14.pdf PDF
P402 ENLARGED CREW SANITARY PLAN SOUTH_Amd01_2020-09-14.pdf PDF
ES109 ELECTRICAL SITE PLAN - NEW WORK_Amd01_2020-09-14.pdf PDF
P401 ENLARGED CREW SANITARY PLAN NORTH_Amd01_2020-09-14.pdf PDF
B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings.pdf PDF
Attachment B_COVID-19 Screening Questionnaire.pdf PDF
Exhibit E SB Participation Commitment Doc.docx DOCX document
Exhibit A Construction Experience Project Data Sheet.docx DOCX document
Show all 50

Alert Facility and Alert Apron has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N6945020R0129

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Project

Base - Alert Facility

FFP

Construction of an Aerospace Control Alert Facilitiy in accordance with drawings and specifications included in the solicitation.

FOB: Destination

PSC CD: Y1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Project

Base - Alert Apron

FFP

Construction of an Aerospace Alert Apron in accordance with drawings and specifications included in the solicitation.

FOB: Destination

PSC CD: Y1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Project

Base - Soil Surcharge and Wick Drains

FFP

Refer to "B-3 RQLH059034 NORTHCOM" Construct Alert Apron drawing sheet C101 for proposed soil surcharge plan and Specifications, including for Wick Drains. This soil surcharge requirement shall be deducted from and not be included within the estimate of the Apron plans.”

FOB: Destination

PSC CD: Y1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0004 Project OPTION Demolition of Old Alert Facility

FFP

Refer to B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings C100 and C201 (Keyed Note 16). Demolish Existing Buildings 185, 185A, 185B, 186 and 478 (approximately 12,735 sf). Demolish buildings in their entirety including slab and haul away debris. For foundations, assume 6” concrete spread foundation with 3’ wide by 1’ thick continuous footings. This bid option shall account for all demo costs involved with the buildings referenced herein. This option may be exercised within 365 days from date of contract award.

FOB: Destination

0005 Project

OPTION EARTHWORK, IMPORTED FILL

FFP

Refer to B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings C400, C401, CA400, CA401, and CA402 for existing contours and proposed grades.

Contractor to place imported fill as needed to meet proposed ubgrade elevations prior to soil surcharge. This must also include compaction to meet minimum density of 95%. This does not include fine grading, clearing and grubbing. This imported fill requirement is in addition to the CLIN 0003 SOIL SURCHARGE AND WICK DRAINS. This option may be exercised within 365 days from date of contract award.

FOB: Destination

PSC CD: Y1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0006 Project

OPTION DUCTBANK

FFP

ES106, keynote 3. Provide separate price and quantity for proposed electrical ductbank in its entirety, including any conduits, structures, fill material, encasement material, connections, handholds and fittings required. This option may be exercised within 365 days from date of contract award.

FOB: Destination

0007 Project OPTION APRON SHOULDER (Construction Only)

FFP

Refer to “B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings CA100 (see Legend), CA200, and CA500. Pricing for this bid option consists of the 15” ACC shoulder (typically shown in cross-hatching) around the aprons. This option may be exercised within 365 days from date of contract award.

FOB: Destination

PSC CD: Y1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0008 Project

OPTION POV PARKING

FFP

Refer to “B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings C200 (see keynote 10) refer to hatched area for POV parking limits, C201, C220, C401.

This option includes all pavement, base and subgrade compaction (after soil surcharge), pavement striping, and parking blocks. Should this option not be exercised, the proposed dumpster pad shall be re-located to be adjacent to the entrance driveway at the proposed POV entrance. This option may be exercised within 365 days from date of contract award.

FOB: Destination

0009 Project OPTION AGEHMS Driveway

FFP

Refer to “B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings C200 (see keynote 11) refer to hatched area for AGEHMS driveway limits, C201, C220, and C401. This option includes all pavement, base and subgrade compaction (after soil surcharge), pavement striping. This option may be exercised within 365 days from date of contract award.

FOB: Destination

PSC CD: Y1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0010 Project

OPTION FF & E

FFP

Procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) for Alert Facilities in accordance with the plans and specifications and in accordance with the following schedule:

Furniture, Fixtures, and Equipment (FF&E) (see FF&E Note) Estimated FF&E Budget for Alert Facilities: $453,170 Handling and Administrative Rate (HAR) (NTE 5%) ______% HAR Amount (Estimated Budget x HAR%):$ __________ Total CLIN 0010 (Budget +HAR):$ __________ FOB: Destination