This document includes exterior elevation plans and specifications for a federal construction project. The project involves building an Alert Facility and Alert Apron at NAS JRB New Orleans, including two aircraft shelters, aircrew alert quarters, an entry control facility, and an apron for two alert ready aircraft. The facilities will be designed for permanent construction according to DoD criteria and will include features such as drive-through capability for the shelters, installed heating, fire suppression, metal walls, standing seam metal roofs, and Alternate Command Post capabilities for the quarters. The project will also provide utilities, communications support, exterior lighting, security upgrades, foundations, and site preparation work. This firm-fixed-price construction contract valued between $25-100 million will be awarded following a full and open competition solicitation and has a total projected duration of 1300 calendar days from award. The soliciting agency is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files for this federal contract opportunity

Other files attached to Alert Facility and Alert Apron, newest first.
File Type Posted
N6945020R0129_Amendment_0007.pdf PDF
C201 SITE PLAN_Amd06_2020-10-21.pdf PDF
N69450-20-R-0129_AMENDMENT_0006.pdf PDF
C511 STORM DRAINAGE DETAILS_Amd06_2020-10-21.pdf PDF
N6945020R0129_0005.pdf PDF
Amd_0004_CLINS.pdf PDF
N6945020R0129_Amendment_0004.pdf PDF
PROJECT TOC Amendment 0003.pdf PDF
ESD106 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 11 20 Amendment 0003.pdf PDF
ESD107 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 12 16 Amendment 0003.pdf PDF
ESD108 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
ESD109 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 01 13.62 Amendment 0003.pdf PDF
32 11 23 Amendment 0003.pdf PDF
N6945020R0129_0003.pdf PDF
E506 - ELECTRICAL DETAILS_Amd0003_2020-10-06.pdf PDF
A351 - SHELTER_1 BUILDING SECTIONS Amd 0002.pdf PDF
P402 - ENLARGED CREW SANITARY PLAN SOUTH Amd 0002.pdf PDF
CA200 - APRON GEOMETY AND UTILITY PLAN Amd 0002.pdf PDF
A602 - DOOR_WINDOW_LOUVER DETAILS Amd 0002.pdf PDF
C201 - SITE PLAN Amd 0002.pdf PDF
C200 - OVERALL SITE PLAN Amd 0002.pdf PDF
08 34 02 Amendment 0002.pdf PDF
N6945020R0129_Amendment_0002.pdf PDF
A352 - SHELTER_ BUILDING SECTIONS Amd 0002.pdf PDF
10 26 00 Amendment 0002.pdf PDF
10 21 23.16 Amendment 0002.pdf PDF
S154 - SHELTER_2 SLAB PLAN Amd 0002.pdf PDF
10 51 13 Amendment 0002.pdf PDF
S152 SHELTER _1 SLAB PLAN_Amd01_2020-09-14.pdf PDF
P403 ENLARGED CREW PIPING PLAN NORTH_Amd01_2020-09-14.pdf PDF
E503 ELECTRICAL DETAILS_Amd01_2020-09-14.pdf PDF
26 20 00 Amendment 0001.pdf PDF
ESL101 EXTERIOR LIGHTING PLAN_Amd01_2020-09-14.pdf PDF
S001 GENERAL NOTES_DESIGN CRITERIA_Amd01_2020-09-14.pdf PDF
P102 OVERALL ECP PLUMBING FLOOR PLAN_Amd01_2020-09-14.pdf PDF
P103 OVERALL SHELTER 1 PLUMBING PLAN_Amd01_2020-09-14.pdf PDF
NOLA_Alert_R0129_SiteVisit_Roster.pdf PDF
S154 SHELTER _2 SLAB PLAN_Amd01_2020-09-14.pdf PDF
N6945020R0129_Amendment_0001.pdf PDF
P502 PLUMBING DETAILS_Amd01_2020-09-14.pdf PDF
P402 ENLARGED CREW SANITARY PLAN SOUTH_Amd01_2020-09-14.pdf PDF
ES109 ELECTRICAL SITE PLAN - NEW WORK_Amd01_2020-09-14.pdf PDF
P401 ENLARGED CREW SANITARY PLAN NORTH_Amd01_2020-09-14.pdf PDF
B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings.pdf PDF
Attachment B_COVID-19 Screening Questionnaire.pdf PDF
Exhibit E SB Participation Commitment Doc.docx DOCX document
Exhibit A Construction Experience Project Data Sheet.docx DOCX document
Show all 50

Alert Facility and Alert Apron has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINISH_FLOOR

0'-0"

ACQ T/WALL

13'-4"

SPLIT FACE

PRECAST STONE- 8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL FASCIA

AF AC.8 AC AAAD.9

PREFINISHED

STANDING SEAM ROOF

33' - 4" 9' - 4" 21' - 0" 33' - 0"

96' - 8"

ACQ EAVE

13'-9"

ACQ RIDGE

25'-0"

42" x 42" x36" ROOF

TOP LOUVERS - SEE

MECH

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT JOINT

@ CORNERS

FINISH_FLOOR

0'-0"

ACQ T/WALL

13'-4"

INSULATED HOLLOW

METAL DOOR- TYPICAL

A3 A1A4 A2A5

4' - 0"37' - 4"41' - 4"8' - 4" 82' - 8"

ACQ EAVE

13'-9"

ACQ RIDGE

25'-0"

SPLIT FACE

PRECAST STONE- 8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL FASCIA

PREFINISHED

STANDING SEAM ROOF

42" x 42" x36" ROOF TOP

LOUVERS - SEE MECH

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

PENTHOUSE LOUVER CURB

- SEE DETAIL 1/A501

FINISH_FLOOR

0'-0"

INSULATED METAL DOOR

A3A1 A4A2 A5

4' - 0" 37' - 4" 41' - 4" 8' - 4"

2'

- 8

2'

- 8

8"

4'

- 0

8"

2'

- 8

82' - 8"

ACQ EAVE

13'-9"

ACQ RIDGE

25'-0"

SPLIT FACE

PRECAST STONE- 8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL FASCIA

PREFINISHED

STANDING SEAM ROOF

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT

JOINT

FINISH_FLOOR

0'-0"

ACQ T/WALL

13'-4"

INSULATED HOLLOW

METAL DOORS- TYPICAL

AB AE AFACAA AD

32' - 8" 4" 22' - 10" 8' - 2" 32' - 8" 96' - 8"

2' -8

2'

-8

8" 4'

-0

8" 2'

-8

ACQ RIDGE

25'-0"

SPLIT FACE

PRECAST STONE- 8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL FASCIA

PREFINISHED

STANDING SEAM ROOF

42" x 42" x36" ROOF TOP

LOUVERS - SEE MECH

3/8" SOFT

JOINT

3/8" SOFT

JOINT

3/8" SOFT JOINT

@ CORNERS

ECP T/WALL

11'-4"

E1E2E3E4

ECP FIN FLR

0'-0"

FENCE- SEE SITE PLAN SPLIT FACE

PRECAST STONE-

8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL

STANDING SEAM

PREFINISHED MTL

GUTTER & DOWN SPOUT

PREFINISHED METAL FASCIA

IM BULLET RESISTANT DOORS

15' - 0"4' - 8"11' - 4" 31' - 0"

BANKERS WINDOW

W/ PASSTHOUGH

FENCE- SEE SITE PLAN

EAEBECED

ECP T/WALL

11'-4"

SPLIT FACE

PRECAST STONE-

8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL

STANDING SEAM

PREFINISHED MTL

GUTTER & DOWN SPOUT

PREFINISHED METAL FASCIA

8' - 0" 7' - 8" 10' - 4"

ECP FIN FLR

0'-0"

26' - 0"

2'

- 1

3'

-4 "9'

- 4 7/

BULLET RESISTANT

WINDOWS

PASSTHOUGH HEIGHT

SET BY MANUFACTURES

REQUIREMENTS WITH

USER APPROVAL

4'-0" SWING GATE

GENERAL NOTE:

ALL WINDOWS ARE BULLET/ RESISTANT

PREFINISHED ALUM INSULATED WINDOW MEETING

DESIGN PSI ON S003 W/ BULLET RESISTANT

MEETING LEVEL 5.

BALLISTIC PROTECTED

BUILDING

ECP T/WALL

11'-4"

SPLIT FACE

PRECAST STONE-

8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL PARAPET

PREFINISHED MTL GUTTER

PREFINISHED MTL FASCIA

E1 E2 E3 E4

ECP FIN FLR

0'-0"

15' - 0" 4' - 8" 11' - 4" 31' - 0"

HAZ MAT BLDG EAVE

15'-0"

4'

- 0

BULLET RESISTANT

WINDOWS

EA EB EC ED

ECP T/WALL

11'-4"

10' - 4" 7' - 8" 8' - 0"

ECP FIN FLR

0'-0" SPLIT FACE

PRECAST STONE-

8'-0" SECTIONS

BRICK VENEER

SMOOTH GROUND FACE

PREFINISHED METAL

STANDING SEAM

PREFINISHED MTL

GUTTER & DOWN SPOUT

PREFINISHED METAL FASCIA

26' - 0"

BULLET RESISTANT

WINDOW

HEAT PUMPS

SEE MECH

SCALE:

CONSTR. CONTR. NO.

SHEET

NAVFAC DRAWING NO.

DES DRW

SY

M

D

ES

C R

IP

TI

O N

D

AT

E

AP

PR

DRAWFORM REVISION: 5 APRIL 2012

CHK

SATISFACTORY TO DATE

APPROVED

ACTIVITY

FOR COMMANDER NAVFAC

SEAL

A/E INFO

OF

EPROJECT NO.:

A

B

C

D

1 2 3 4 5

1 2 3 4 5

A

B

C

D

DE

PA

RT

ME

NT

O

F

TH

E

NA

VY

NA

VA

L F

AC

ILI

TI

ES

E

NG

IN

EE

RI

NG

C

OM

MA

ND

N

AV

AL

F

AC

IL

IT

IE

S

EN

G

IN

EE

R

IN

G

C O

M M

AN

D

S O

U

TH

EA

ST

NA

VA

L A

IR

S

TA

TI

ON

JA

CK

SO

NV

ILL

E

SHEET FORMAT IS 22" X 34". IF PRINTED SHEET IS NOT 22" X 34", THEN IT IS NOT TO SCALE

B-3 SUBMITTAL 02/28/2020

DESIGN MANAGER

CHIEF ENG/ARCH

FIRE PROTECTION

PROJECT MANAGER

ANTHONY DISANTO

Michelle Contestabile

HOLLY KING

JOANNE DIZ

1/8" = 1'-0"

IP

T

SO

U

TH

EA

ST

1621243

N69450-XX-C-XXXX

A201

NO

RT

HC

O

M R

EP

LA

CE

A

LE

RT

C O

M

PL

EX

AC

Q

E C

P

EX

TE

R

IO

R

E

LV

AT

IO

N S

N

AS

J R

B N

EW

O

R

LE

AN

S

BE

LL

E C

H

AS

SE

, L

O U

IS

IA

N A

41 164

AM

EN

D

M

EN

T

/2 1/

15135281

SCALE: 1/8" = 1'-0"1B ACQ EAST ELEVATION

SCALE: 1/8" = 1'-0"1A AQC NORTH ELEVATION

SCALE: 1/8" = 1'-0"1D ACQ SOUTH ELEVATION

SCALE: 1/8" = 1'-0"1C ACQ WEST ELEVATION

SCALE: 1/8" = 1'-0"2A ECP NORTH ELEVATION

SCALE: 1/8" = 1'-0"2B ECP EAST ELEVATION

SCALE: 1/8" = 1'-0"2D ECP SOUTH ELEVATION

SCALE: 1/8" = 1'-0"2C ECP WEST ELEVATION

Sheets
A201 - ACQ & ECP EXTERIOR ELVATIONS
A351 - SHELTER #1 BUILDING SECTIONS
A352 - SHELTER #2 BUILDING SECTIONS
A353 - SHELTER WALL SECTIONS
A601 - DOOR / WINDOW ELEVATIONS & DOOR SCHEDULE
A602 - DOOR, WINDOW & LOUVER DETAILS