10 51 13 Amendment 0002.pdf

PDF 27 KB Posted

Attached to
Alert Facility and Alert Apron Federal contract opportunity
Solicitation number
N69450-20-R-0129
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document contains a federal solicitation for the construction of an Alert Facility and Alert Apron at NAS JRB New Orleans. The solicitation seeks the construction of an Aerospace Control Alert Facilities and Alert Apron utilizing conventional design and build methods. The facilities must accommodate the mission and be designed in accordance with UFC requirements. The Alert Facility requires two aircraft shelters with drive-through capability, installed heating, fire suppression, metal walls and standing seam metal roof. An aircrew alert quarters and mission support structure with Alternate Command Post capabilities, a secure area and entry control facility are also required. The solicitation requires the provision of standby power, pile foundations and site preparation including surcharging for the Alert Facility. The Alert Apron requires all utilities, communication support, site improvements, exterior and security lighting, lightning protection and security upgrades. A parking apron for two alert ready aircraft and security fencing, access gates with airfield lighting, security lighting controls and communications and electrical conduit must be provided. Pile foundations and site preparation including soil dewatering as required are also included. This will result in an award of a firm-fixed price design-bid-build construction contract for a total project completion schedule of 1300 calendar days from award. The project magnitude is between $25,000,000 to $100,000,000.

View the file

Other files for this federal contract opportunity

Other files attached to Alert Facility and Alert Apron, newest first.
File Type Posted
N6945020R0129_Amendment_0007.pdf PDF
C201 SITE PLAN_Amd06_2020-10-21.pdf PDF
N69450-20-R-0129_AMENDMENT_0006.pdf PDF
C511 STORM DRAINAGE DETAILS_Amd06_2020-10-21.pdf PDF
N6945020R0129_0005.pdf PDF
Amd_0004_CLINS.pdf PDF
N6945020R0129_Amendment_0004.pdf PDF
PROJECT TOC Amendment 0003.pdf PDF
ESD106 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 11 20 Amendment 0003.pdf PDF
ESD107 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 12 16 Amendment 0003.pdf PDF
ESD108 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
ESD109 - ELECTRICAL SITE DEMOLITION_Amd0003_2020-10-06.pdf PDF
32 01 13.62 Amendment 0003.pdf PDF
32 11 23 Amendment 0003.pdf PDF
N6945020R0129_0003.pdf PDF
E506 - ELECTRICAL DETAILS_Amd0003_2020-10-06.pdf PDF
A351 - SHELTER_1 BUILDING SECTIONS Amd 0002.pdf PDF
P402 - ENLARGED CREW SANITARY PLAN SOUTH Amd 0002.pdf PDF
CA200 - APRON GEOMETY AND UTILITY PLAN Amd 0002.pdf PDF
A602 - DOOR_WINDOW_LOUVER DETAILS Amd 0002.pdf PDF
C201 - SITE PLAN Amd 0002.pdf PDF
C200 - OVERALL SITE PLAN Amd 0002.pdf PDF
08 34 02 Amendment 0002.pdf PDF
N6945020R0129_Amendment_0002.pdf PDF
A352 - SHELTER_ BUILDING SECTIONS Amd 0002.pdf PDF
10 26 00 Amendment 0002.pdf PDF
10 21 23.16 Amendment 0002.pdf PDF
S154 - SHELTER_2 SLAB PLAN Amd 0002.pdf PDF
01 30 01_00 22 Amendment 0002.pdf PDF
S152 SHELTER _1 SLAB PLAN_Amd01_2020-09-14.pdf PDF
P403 ENLARGED CREW PIPING PLAN NORTH_Amd01_2020-09-14.pdf PDF
E503 ELECTRICAL DETAILS_Amd01_2020-09-14.pdf PDF
26 20 00 Amendment 0001.pdf PDF
ESL101 EXTERIOR LIGHTING PLAN_Amd01_2020-09-14.pdf PDF
S001 GENERAL NOTES_DESIGN CRITERIA_Amd01_2020-09-14.pdf PDF
P102 OVERALL ECP PLUMBING FLOOR PLAN_Amd01_2020-09-14.pdf PDF
P103 OVERALL SHELTER 1 PLUMBING PLAN_Amd01_2020-09-14.pdf PDF
NOLA_Alert_R0129_SiteVisit_Roster.pdf PDF
S154 SHELTER _2 SLAB PLAN_Amd01_2020-09-14.pdf PDF
N6945020R0129_Amendment_0001.pdf PDF
P502 PLUMBING DETAILS_Amd01_2020-09-14.pdf PDF
P402 ENLARGED CREW SANITARY PLAN SOUTH_Amd01_2020-09-14.pdf PDF
ES109 ELECTRICAL SITE PLAN - NEW WORK_Amd01_2020-09-14.pdf PDF
P401 ENLARGED CREW SANITARY PLAN NORTH_Amd01_2020-09-14.pdf PDF
B-3 RQLH059034 NORTHCOM Construct Alert Apron Drawings.pdf PDF
Attachment B_COVID-19 Screening Questionnaire.pdf PDF
Exhibit E SB Participation Commitment Doc.docx DOCX document
Exhibit A Construction Experience Project Data Sheet.docx DOCX document
Show all 50

Alert Facility and Alert Apron has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORTHCOM CONSTRUCT ALERT APRON/FACILITIES WON: 1323108/1621243

NAS JRB NEW ORLEANS, LOUISIANA B-3 DESIGN SUBMITTAL

SECTION 10 51 13

METAL LOCKERS

05/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A568/A568M (2017a) Standard Specification for Steel, Sheet, Carbon, Structural, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled, General Requirements for

ASTM B456 (2017) Standard Specification for Electrodeposited Coatings of Copper Plus Nickel Plus Chromium and Nickel Plus Chromium

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FS AA-L-00486 (Rev J) Lockers, Clothing, Steel

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Types; G

Numbering system

SD-03 Product Data; G, NAVFAC Interior Designer

Material

Locking Devices

Handles

Finish

Locker components

SD-04 Samples

SECTION 10 51 13 Page 1 michelle.contestabil Typewritten Text

REVISION 1: AMENDMENT 0002

Color chips; G, NAVFAC Interior Designer

1.3 DELIVERY, HANDLING, AND STORAGE

Deliver lockers and associated materials in their original packages, containers, or bundles bearing the manufacturer's name and the name of the material. Protect from weather, soil, and damage during delivery, storage, and construction.

1.4 FIELD MEASUREMENTS

To ensure proper fits, make field measurements prior to the preparation of drawings and fabrication. Verify correct location

1.5 QUALITY ASSURANCE

1.5.1 Color Chips

Provide a minimum of three color chips, not less than 2 inches square, of each color indicated.

Government may request performance-characteristic tests on assembled lockers. Tests and results must conform to FS AA-L-00486. Lockers not conforming will be rejected.

PART 2 PRODUCTS

2.1 TYPES

Locker must have the following type and size in the location and quantities indicated. Locker finish colors will be selected from manufacturer's standard colors. Submit options to NAVFAC Interior Designer

2.1.1 Single-tier Lockers

Single-tier lockers must be as follows:

Type STL-1: Single-tier locker 12 inches wide, 15 inches deep, and 72 inches high, attached to 6-inch high base

Type STL-2: Single-tier locker 24 inches wide, 18 inches deep, and 72 inches high, attached to 6-inch high base

2.2 MATERIAL

2.2.1 Steel Sheet

ASTM A568/A568M, commercial quality, minimized spangle material. Prepare material surfaces for baked enamel finishing in accordance with FS AA-L-00486. Fabricate locker bodies from not less than 0.0239-inch thick steel sheet.

2.2.2 Chromium Coating

Nickel and chromium electrodeposited on the specified base metal. Conform to ASTM B456, SC-3, as applicable to the base metal.

SECTION 10 51 13 Page 2

2.2.3 Finish

Primer, topcoat.

2.2.3.1 Color

As selected from manufacturer's standard finishes.

2.3 [Enter Appropriate Subpart Title Here]COMPONENTS

2.3.1 Built-In Locks

FS AA-L-00486. Provide a padlock eye in the door latching mechanism.

Built-in locks are not required.

2.3.2 Coat Hooks

FS AA-L-00486, chromium plated.

2.3.3 Hanger Rods

FS AA-L-00486.

2.3.4 Door Handles

FS AA-L-00486. Provide steel handles with a chromium coating.

2.3.5 Doors

FS AA-L-00486, not less than 0.0598 inch thick steel sheet.

2.3.5.1 Hinges

In addition to the requirements of FS AA-L-00486, provide 5-knuckle hinges, minimum 2 inches high. Fabricate knuckle hinges from not less than 0.0787 inch thick steel sheet. A full height piano hinge may be provided if standard with the manufacturer. Weld or bolt hinges to the door frame.

Weld, bolt, or rivet hinges to the door.

2.3.5.2 Latching Mechanisms

FS AA-L-00486.

2.3.6 Latch Strikes

FS AA-L-00486. Fabricate from not less than 0.0787 inch thick steel sheet, except latch strike may be continuous from top to bottom and fabricated as part of the door framing.

2.3.7 Silencers

FS AA-L-00486.

2.3.8 Back and Side Panels, Tops, and Bottoms

FS AA-L-00486, not less than 0.0474 inch thick steel sheet.

SECTION 10 51 13 Page 3

2.3.9 Sloping Locker Tops

Provide sloping locker tops in addition to the locker-section flat tops.

Sloping tops must be continuous in length. Provide fillers or closures at the exposed end of sloping tops. Fabricate sloping tops from not less than 0.0478-inch thick steel sheet.

2.3.10 Shelves

FS AA-L-00486. Fabricate from not less than 0.0598 inch thick steel sheet.

2.3.11 Base Panels

FS AA-L-00486.

2.3.12 Number Plates

FS AA-L-00486. Aluminum. Provide consecutive numbers from 1 to 20.

2.3.13 Label Holders

FS AA-L-00486.

2.3.14 Fastening Devices

Provide bolts, nuts, and rivets as specified in FS AA-L-00486.

PART 3 EXECUTION

3.1 ASSEMBLY AND INSTALLATION

Assemble lockers according to the locker manufacturer's instructions.

Align lockers horizontally and vertically. Secure lockers to wall and base with screws as indicated. Bolt adjacent lockers together. Adjust doors to operate freely without sticking or binding and to ensure they close tightly.

3.2 FIELD QUALITY CONTROL

3.2.1 Testing

Government may request performance-characteristic tests on assembled lockers in accordance with FS AA-L-00486. Lockers not conforming will be rejected.

3.2.2 Repairing

Remove and replace damaged and unacceptable portions of completed work with new.

3.2.3 Cleaning

Clean surfaces of the work, and adjacent surfaces soiled as a result of the work, in an approved manner. Remove equipment, surplus materials, and rubbish from the site.

-- End of Section --

SECTION 10 51 13 Page 4

File details come from the government source that posted it. Updated .