32 01 13.62 Amendment 0003.pdf
PDF 49 KB Posted
- Attached to
- Alert Facility and Alert Apron Federal contract opportunity
- Solicitation number
- N69450-20-R-0129
About this file
This document includes an amendment to a federal construction contract specification and details of a related federal contract opportunity. The specification amendment provides requirements for asphalt surface treatment for a construction project at NAS JRB New Orleans, including materials, application methods, testing, and other technical specifications.
The related federal contract opportunity is a solicitation for the Alert Facility and Alert Apron project at NAS JRB New Orleans, with an estimated value between $25-100 million. The project includes construction of an Aerospace Control Alert Facility, alert aircraft apron, security fencing and gates, site utilities and lighting. The contract will be a firm-fixed-price design-bid-build agreement, with a period of performance of 1300 calendar days from award. The solicitation is unrestricted and open to all responsible sources through full and open competition.
View the file
Other files for this federal contract opportunity
Show all 50
Alert Facility and Alert Apron has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NORTHCOM CONSTRUCT ALERT APRON/FACILITIES WON: 1323108/1621243
NAS JRB NEW ORLEANS, LOUISIANA B-3 DESIGN SUBMITTAL
SECTION 32 01 13.62
ASPHALT SURFACE TREATMENT
05/18
PART 1 GENERAL
1.1 UNIT PRICES
The bituminous material and aggregate to be paid for will be the measured quantities used in the accepted work.
1.1.1 Measurement
1.1.1.1 Bituminous Material
The amount of bituminous material to be paid for will be measured in 2000 pounds tons .
1.1.1.2 Aggregate
The amount of aggregate paid for will be the number of cubic yards of aggregate placed and accepted in the completed work or placed in authorized stockpiles.
1.1.1.3 Quantity Limits
Spread the bituminous material and aggregate within the quantity limits shown in PART 2; base bids on the mean of the values in the tables. The individual quantities of bituminous material and aggregate may be varied to meet specific field conditions at all times during progress of the work, as directed, without adjustments to contract unit prices.
1.1.2 Payment
The quantities of aggregates and bituminous material, determined as specified in paragraph MEASUREMENT, will be paid for at the respective contract unit prices. Payment will constitute full compensation for all operations necessary to complete the work as specified herein.
1.1.3 Waybills and Delivery Tickets
Submit copies of waybills and delivery tickets during progress of the work. Before the final statement is allowed, file with the Contracting Officer certified waybills and delivery tickets for aggregate and bituminous material used in the bituminous surface treatment. Do not remove bituminous material from the tank car or storage tank until initial outage and temperature measurements have been taken. Do not release the car or tank until final outage has been taken.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 32 01 13.62 Page 1 michelle.contestabil Text Box
REVISION 1: AMENDMENT 0003
ASTM INTERNATIONAL (ASTM)
ASTM C29/C29M (2017a) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate
ASTM C88 (2018) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate
ASTM C131/C131M (2014) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates
ASTM D140/D140M (2016) Standard Practice for Sampling Asphalt Materials
ASTM D946/D946M (2015) Penetration-Graded Asphalt Cement for Use in Pavement Construction
ASTM D977 (2017) Standard Specification for Emulsified Asphalt
ASTM D1139/D1139M (2015) Aggregate for Single or Multiple Bituminous Surface Treatments
ASTM D2028/D2028M (2015) Cutback Asphalt (Rapid-Curing Type)
ASTM D2397/D2397M (2017) Standard Specification for Cationic Emulsified Asphalt
ASTM D2995 (1999; R 2009) Determining Application Rate of Bituminous Distributors
ASTM D3625/D3625M (2012) Standard Practice for Effect of Water on Bituminous-Coated Aggregate Using Boiling Water
ASTM D6373 (2016) Standard Specification for Performance Graded Asphalt Binder
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
SECTION 32 01 13.62 Page 2
Waybills and Delivery Tickets Cutback Asphalt Emulsified Asphalt Asphalt Cement
SD-06 Test Reports
Tests
1.4 QUALITY CONTROL
1.4.1 Safety Precautions
Smoking or open flames will not be permitted within 25 feet of heating, distributing, or transferring operations of bituminous materials other than bituminous emulsions.
1.4.2 Sampling and Testing
Sampling and testing is the responsibility of the Contractor. Perform sampling and testing using an approved commercial testing laboratory, or by the Contractor, subject to approval. Sampling must be in accordance with ASTM D75/D75M for aggregates and ASTM D140/D140M for bituminous material, unless otherwise directed. Perform aggregate gradation tests on each sample in accordance with ASTM C136/C136M. Perform all other aggregate tests on the initial source samples and repeat tests when there is a change of source. Perform sieve analyses daily from material samples including an analysis of each gradation of material. Perform tests in sufficient number to ensure that materials meet specified requirements. Submit copies of test results, within 24 hours after completion of each test. Repeat aggregate testing (wear, soundness, deleterious material and stripping) for each 20,000 tons of aggregate used in the project.
1.4.3 Wear Test
Perform the wear test in accordance with ASTM C131/C131M to ensure that aggregates have a percentage of wear not exceeding 40 percent after 500 revolutions.
1.4.4 Soundness Test
Perform the soundness test as specified by ASTM C88 to ensure that aggregates have a weight loss not greater than 18 percent when subjected to five cycles of the magnesium sulfate test or 12 percent when subjected to five cycles of the sodium sulfate test.
1.4.5 Stripping Test
Perform stripping tests meeting the requirements of ASTM D3625/D3625M.
Deleterious substances must not exceed the requirements of ASTM D1139/D1139M.
1.5 DELIVERY, STORAGE, AND HANDLING
Inspect the materials delivered to the site for contamination and damage.
Unload and store the materials with a minimum of handling. Store aggregates preventing segregation and contamination.
SECTION 32 01 13.62 Page 3
1.6 EQUIPMENT, TOOLS AND MACHINES
Provide equipment dependable and adequate for the purpose intended and properly maintained in satisfactory and safe operating condition at all times. Discontinue the use of equipment which fails to produce satisfactory work and replace with satisfactory equipment. Equipment such as asphalt distributors, scales, batching equipment, spreaders and similar equipment, must have been calibrated by an approved calibration laboratory within 12 months prior to commencing work .
1.6.1 Bituminous Distributors
Provide a self propelled distributor with pneumatic tires of such size and number to prevent rutting, shoving or otherwise damaging the surface being sprayed. Calibrate the distributer in accordance with ASTM D2995. Design and equip the distributor to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled total liquid rates from 0.03 to 1.0 gallons per square yard, with a pressure range of 25 to 75 psi and with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Include with the distributor equipment a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. The distributor will be capable of circulating and agitating the bituminous material during the heating process.
1.6.2 Single-Pass, Surface-Treatment Machines
Use only machines capable of spraying bituminous material and spreading aggregate in one pass. Use only bituminous spraying equipment conforming to the requirements given above for a bituminous distributor. Use only machines capable of spreading aggregates at controlled amounts per square yard as specified. In addition, only use single-pass, surface-treatment machines capable of placing a surface treatment adjacent to an existing surface treatment, forming a joint of the same thickness and uniformity as other portions of the surface treatment. Ridges or blank spaces will not be permitted. Form joints in the second application at least 1 foot from those formed in the first application.
1.6.3 Heating Equipment for Storage Tanks
Use equipment consisting of coils and equipment for producing steam or hot oil and designed to prevent the introduction of steam or hot oil into the material. Affix an armored thermometer with a range of 100 to 400 degrees F to the tank so the temperature of the bituminous material may be determined at all times.
1.6.4 Power Rollers
Use only steel-wheeled or pneumatic-tired type power rollers conforming to the following requirements:
a. Use only steel-wheeled rollers having at least one steel drum and weigh a minimum of 5 tons. Equip steel wheels of the rollers with adjustable scrapers.
SECTION 32 01 13.62 Page 4
b. Use only self-propelled pneumatic-tired rollers having wheels mounted on two axles in such manner that the rear tires will not follow in the tracks of the forward group. Maintain uniform tire inflation to not less than 60 psi nor more than 80 psi pressure.
Equip pneumatic-tired rollers with boxes or platforms for ballast loading. Load rollers so that the tire print width of each wheel is not less than the clear distance between tire prints.
1.6.5 Mechanical Spreaders
Use only adjustable spreaders capable of spreading aggregate at controlled amounts per square yard, as specified.
1.6.6 Brooms and Blowers
Use only power type brooms and blowers capable of cleaning surfaces to be treated.
1.6.7 Scales
Use standard truck scales of the beam type equipped with a weight-recording device. Use scales with sufficient size and capacity to accommodate the trucks used in hauling aggregates. The scales must be tested and approved by an inspector of the State Inspection Bureau charged with scale inspection within the state in which the project is located. If an official of the inspection bureau is not available, test the scales in accordance with state specifications and in the presence of the Contracting Officer. Keep the necessary number of standard weights on hand, at all times, for testing the scales.
1.6.8 Weighhouse
Provide a weatherproof weighhouse constructed in a manner to afford adequate protection for the indicating and recording devices of the scales.
1.7 ENVIRONMENTAL REQUIREMENTS
Apply bituminous surface treatment only when the existing surface or base course is dry or contains moisture not in excess of the amount that will permit uniform distribution of the asphalt material and provide the desired adhesion between the asphalt material and the materials underneath and above. Do not apply bituminous surface treatment when either the atmospheric temperature, in the shade, is below 50 degrees F or the pavement surface to be treated is below 70 degrees F unless otherwise directed.
PART 2 PRODUCTS
Use mineral aggregate and bituminous material of the following types, gradations, grades, and consistencies that meet the requirements of stripping, wear, deleterious materials and soundness tests as specified in paragraph SAMPLING AND TESTING.
2.1 MINERAL AGGREGATE
Provide aggregate consisting of crushed stone, crushed gravel, or crushed slag of such nature that thorough coating of bituminous material, used in the work, will not strip off upon contact with water when testing using ASTM D3625/D3625M. Maintain aggregate moisture content so that the
SECTION 32 01 13.62 Page 5 aggregate will be readily coated with the bituminous material. Drying may be required, as directed. Use aggregate conforming to the gradation shown below. Determine gradation of the aggregates by ASTM C136/C136M.
AGGREGATE GRADATION SINGLE BITUMINOUS SURFACE TREATMENT
(PERCENT BY WEIGHT PASSING)
Sieve Designation No. 1 No. 2 No. 3
1 inch 100 -- --
3/4 inch 90-100 100 --
1/2 inch 20-55 90-100 100
3/8 inch 0-15 40-70 85-100
No. 4 0-5 0-15 10-30
No. 8 -- 0-5 0-10
No. 16 -- -- 0-5
AGGREGATE GRADATION DOUBLE BITUMINOUS SURFACE TREATMENT
(PERCENT BY WEIGHT PASSING)
Sieve Designation
No. 1 No. 2 No. 3 No. 4
1 inch 100 -- -- --
3/4 inch 90-100 -- 100 --
1/2 inch 20-55 100 90-100 --
3/8 inch 0-15 85-100 40-70 100
No. 4 0-5 10-30 0-15 85-100
No. 8 -- 0-10 0-5 10-40
No. 16 -- 0-5 -- 0-10
No. 50 -- -- -- 0-5
2.1.1 Crushed Stone
Provide crushed stone consisting of clean, sound, durable particles, free of soft or disintegrated pieces, dust, or foreign matter.
2.1.2 Crushed Gravel
Provide crushed gravel consisting of clean, sound, durable particles, free of soft or disintegrated pieces or foreign matter. At least 90 percent by weight of the particles must have at least two fractured faces.
SECTION 32 01 13.62 Page 6
2.1.3 Crushed Slag
Provide crushed slag which is an air-cooled blast-furnace product having a dry weight of not less than 70 pcf, and consists of angular particles uniform in density and quality and free of dust and foreign matter.
Determine the weight of a cubic foot of slag aggregate by ASTM C29/C29M.
2.1.4 Aggregate Quantities
Spread the bituminous material and aggregate within the quantity limits shown below. The individual quantities of bituminous material and aggregate may be varied to meet specific field conditions at all times during progress of the work, as directed, without adjustments to contract unit prices. Aggregate weights shown are for aggregates having a specific gravity of 2.65. Adjust the number of pounds required if the specific gravity of the aggregate used is other than 2.65 in order to ensure a constant volume of aggregate per square yard of treatment.
QUANTITIES (PER SQUARE YARD)
Gradation No. Bituminous Material (Gallons)
Aggregate (Pounds)
1 0.30-0.45 35-50
2 0.15-0.30 20-35
3 0.10-0.20 15-25
QUANTITIES (PER SQUARE YARD)
Gradation No. Bituminous Material (Gallons) First Application
Aggregate (Pounds) First Spreading
Bituminous Material (Gallons) Second Application
Aggregate (Pounds) Second Spreading
1 0.20-0.30 28-34 -- --
2 -- -- 0.20-0.30 20-25
3 0.15-0.20 20-25 -- --
4 -- -- 0.15-0.20 10-15
2.2 BITUMINOUS MATERIALS
2.2.1 Cutback Asphalt
Use rapid curing cutback asphalt conforming to ASTM D2028/D2028M, Designation RC-250 . Submit temperature-viscosity relationship of cutback asphalt.
2.2.2 Emulsified Asphalt
Use rapid-setting emulsified asphalt conforming to ASTM D977, Grade RS-1 or
SECTION 32 01 13.62 Page 7
RS-2 or ASTM D2397/D2397M, Grade CRS-1 or CRS-2.
2.2.3 Asphalt Cement
Use asphalt cement conforming to ASTM D946/D946M, Penetration Grade 120-150 or ASTM D6373, Performance Graded Asphalt Binder PG 58-28 . Submit temperature-viscosity relationship of asphalt cement.
PART 3 EXECUTION
3.1 SURFACE PREPARATION
Immediately before applying the first course of bituminous material, clean the surface of loose material with power brooms or power blowers. Take care to remove all dirt, clay, and other loose or foreign matter. Flush the surface with water, when necessary to achieve a clean surface, only when directed by the Contracting Officer; allow the surface to dry after flushing.
3.2 APPLICATION OF FIRST COURSE
3.2.1 Bituminous Material
Apply bituminous material by means of a bituminous distributor at the temperature specified in paragraph APPLICATION TEMPERATURE OF MATERIALS, below or as directed; and within the limits specified in paragraph QUANTITY LIMITS in PART 1. Apply bituminous material in such a manner that uniform distribution is obtained over all surfaces treated. Unless the distributor is equipped to obtain a satisfactory result at the junction of previous and subsequent applications, spread building paper on the surface for a sufficient distance back from the ends of each application so that flow through the sprays may be started and stopped on the paper in order that all sprays will operate at full force on the surface treated. Immediately after application, remove and destroy the building paper. Properly treat areas inaccessible to the distributor with bituminous material using the hose attachment. Protect adjacent buildings, structures, and trees to prevent their being spattered or marred.
3.2.2 Spreading of Aggregate
Immediately following application of bituminous material, spread aggregate uniformly over the surface within the limits of the quantities specified in paragraph QUANTITY LIMITS in PART 1 using mechanical spreaders. Spread aggregate evenly by hand on all areas missed by the mechanical spreader.
Operate equipment spreading aggregate so that the bituminous material will be covered ahead of the truck wheels. When hand spreading is employed on inaccessible areas, spread aggregate directly from trucks. Spread additional aggregate by hand over areas having insufficient cover. Continue spreading during these operations when necessary.
3.2.3 Brooming and Rolling
Roll the surface with a pneumatic-tired and a steel-wheeled roller after sufficient aggregate is spread. Continue rolling until no more aggregate can be worked into the treated surface. The use of the steel-wheeled roller will be discontinued, or a lighter weight steel wheel roller substituted, as directed, if the roller being used causes excessive crushing and shattering of the aggregate. If the aggregate is not
SECTION 32 01 13.62 Page 8 distributed properly, broom the surface as soon as possible after the first coverage by the roller, but not until the surface has set sufficiently to prevent excessive marking. Continue brooming, rolling, and supplemental spreading of aggregate until the surface is cured and rolled sufficiently to key and set the aggregate. In places not accessible to rollers, compact the aggregate with pneumatic tampers. Remove aggregate that has become contaminated with foreign matter and replace with clean aggregate and reroll as directed. Maintain and protect the treated areas by use of barricades until properly cured.
3.3 APPLICATION OF SECOND COURSE
3.3.1 Bituminous Treatment
Apply the bituminous material for the second course within 48 hours after construction of the first course, weather permitting. Remove excess aggregate prior to the second application of bituminous material. If the treated surface is excessively moistened by rain, allow the surface to dry for such time as deemed necessary. Perform the second application of bituminous material in the manner specified in paragraph APPLICATION OF FIRST COURSE, including temperature and QUANTITY LIMITS.
3.3.2 Aggregate
Immediately following the second application of bitumen, spread aggregate conforming to the gradation and limits specified in paragraph QUANTITY LIMITS uniformly over the bituminous material and process in the manner specified for the first course.
3.3.3 Brooming and Rolling Second Course
Roll and broom the surface in the manner specified for the first course until a thoroughly bonded, smooth, even-textured surface is produced.
Sweep off the surface surplus aggregate and remove it prior to final acceptance.
3.4 APPLICATION TEMPERATURE OF MATERIALS
3.4.1 Cutback Asphalt
Apply cutback asphalt in the range of 100 to 200 degrees F.
3.4.2 Emulsified Asphalt
Apply asphalt emulsions in the range of 90 to 160 degrees F.
3.4.3 Asphalt Cement
Apply asphalt cement in the range of 325 to 375 degrees F.
3.5 TRIAL APPLICATION
Preliminary to providing a complete surface treatment, treat three lengths of at least 100 feet each for the full width of the distributor bar. Use the appropriate typical application rates specified herein for one surface
SECTION 32 01 13.62 Page 9 treatment trial. Make other surface treatment trials using various amounts of materials as may be deemed necessary.
3.6 PROTECTION
Keep all traffic off surfaces freshly treated with bituminous material.
Provide sufficient warning signs and barricades so that traffic will not travel over freshly treated surfaces. Protect the treated areas from traffic for at least 24 hours after final application of bituminous material and aggregate, or for such time as necessary to prevent picking
up. Immediately prior to opening to traffic, roll the entire treated area with a self-propelled pneumatic-tired roller.
-- End of Section --
SECTION 32 01 13.62 Page 10