This is a Task Group Instruction (TGI) document for the U.S. Navy detailing repair work on the USS Higgins (DDG-76). The document specifies structural repairs to the main deck weather area, frames 370-379 on the starboard side, with contractor work scheduled to commence on 29 June 2026 and complete by 8 December 2026.
The work scope includes removal, fabrication, and installation of corroded structural members including Stringer 21, Stringer 22, tripping brackets, vertical stiffeners, and a brass shield on a watertight transverse bulkhead. Materials required include 7 square feet of plate steel (stock number 002375333) and 14 square feet of additional plate steel (stock number 002243086), ordered through the contractor. The repair effort also encompasses surface treatment and reinstallation of rubber tile coverings on affected areas, with rubber tile work covered under separate TGIs 38KB313103U01 and 38KB313103R01. Special requirements mandate hot work procedures in magazine and adjacent spaces per S6740-AA-SAF-010 and NAVSEA OP 4, with prior verification required from Code 294 (VLS Subject Matter Expert) before work commencement. Support services to be provided by the shipyard include crane and rigging, electrical utilities, low/medium pressure air and water supply, safety and gas-free inspections, and QA inspections. The work responds to CCIMS deficiency report CCIMS-G1N6-DDG76-067-25 and resolves deficiency DDG-76-1023-2025.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: MAIN WEA STRCT AY A 0 1
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-76 USS HIGGINS KB3
CU PHASE TITLE:
F/O - REPAIR STRUCTURAL MEMBER IN MAIN DECK WEATHER
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
KEIGO ABE 231A 315-243-3161 18-DEC-2025
APPROVED BY: CODE PHONE DATE
YUUJI NAKAMURA 231A 315-243-6041 18-DEC-2025
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
Contractor work start/completion date of 1.6 and 1.7 were missing.
CHANGE INSTRUCTIONS:
CH-1: Add contractor work start/completion date of 1.6 and 1.7.
SPECIAL REQUIREMENTS:
HOT WORK IN MAGAZINE AND ADJACENT SPACES IAW S6740-AA-SAF-010 AND NAVSEA OP 4
TGI CONCURRENCE BY CODE 294 MR. A. Kumagaya, DATED 12/12/2025
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: MAIN WEA STRCT AY A 0
FOUO
SHIP: DDG-76 CHG/VER: 1/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-4 J-1 M-1
1. SCOPE/PURPOSE
1.1 Title: Structural Member in Main Deck Weather; repair
1.2 Location of Work:
1.2.1 Main Deck Weather, Frames between 370 and 379, Starboard (Stbd)
1.2.2 Supply Department Storeroom No. 2 (2-370-3-A)
1.2.3 B-Size Module 61 Cell Vertical Launching System (3-338-0-M)
1.3 Identification:
1.3.1 Quantity (One Lot), Structural Member in Main Deck Weather, Frames between 372 and 378, Stbd
JCN: ES01-NALT
1.3.1.1 Quantity (One Lot), Stringer 21 (S) on Fashion Plate (S), Frames between 370 and 378, Stbd
Remarks: See Plan 4-A of 2.3 for material and detail
1.3.1.2 Quantity (One Lot), Tripping Bracket of Stringer 21 (S) and Vertical Stiffener on Fashion Plate (S), Frame 378, Frames between 375 and 377, Stbd
Remarks: See Detail 4-B of 2.3 for material and detail
1.3.1.3 Quantity (One Lot), Stringer 22 (S) on Fashion Plate (S), Frames between 373 and 379, Stbd
Remarks: See Plan 5-A of 2.3 for material and detail
1.3.1.4 Quantity (One Lot), Vertical Stiffener on Fashion Plate (S), Frame 374, Stbd
Remarks: See Plan 5-B of 2.3 for material and detail
1.3.2 Quantity (One EA), Brast Sheild on Watertight Transverse Bulkhead in Main Deck Weather, Frame 370, Stbd
Remarks: See Detail 152A-A of 2.4 for material and detail
1.3.3 Quantity (4 SF), Stringer 21 (S) on Fashion Plate (S), Frames between 370 and 378, Stbd
Remarks: The area where rubber tile is installed.
1.3.4 Quantity (2 SF), Stringer 22 (S) on Fashion Plate (S), Frames between 373 and 379, Stbd
Remarks: The area where rubber tile is installed.
1.3.5 Quantity (8 SF), Vertical Stiffener on Fashion Plate (S), Frame 374, Stbd
FOUO
SHIP: DDG-76 CHG/VER: 1/0
Remarks: The area where rubber tile is installed.
1.3.6 Quantity (6 SF), Vertical Stiffener on Fashion Plate (S), Frame 378, Stbd
Remarks: The area where rubber tile is installed.
1.3.7 Quantity (14 SF), Fashion Plate (S), Frames between 372 and 379, Stbd
Remarks: The area where rubber tile is installed.
1.3.8 Quantity (6 SF), Watertight Transverse Bulkhead, Frame 370, Stbd
Remarks: The area where rubber tile is installed.
1.4 Security Classification:
1.4.1 Spaces – 1.2.3
1.5 Initial Condition:
1.5.1 Contact Code 294 VLS SME prior to conducting the work procedure out of sequence in this TGI.
1.5.2 Potential Asbestos Hazard
1.6 Contractor work start date: 29/JUN/2026
1.7 Contractor work completion date: 8/DEC/2026
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
3 PDD 100-
ELM-260041
RPR PLAN OF CORRODED
STIFFENERS ON STBD FASHION
PL (MN DK, FR 372-378)
- Y AL
L
4 DWG 611-
6221132
FABRICATION OF MISC DECK
FITTING - ZONE 3
AK Y 15
2A
5 DWG 600-
6219304
HULL OUTFIT INSTL DESIGN
ZONE 3350 MN DK FR 370 - 410
(WEA)
AD Y 5C
6 DWG 100-
6218940
UNIT STRL ARR DWG ASSY UNIT
Y Y 5A -10
3. APPENDICES:
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
FOUO
SHIP: DDG-76 CHG/VER: 1/0
5. PROCEDURE:
5.1 Remove existing, fabricate, and install new each structural member and blast shield listed in 1.3.1 and 1.3.2 in accordance with 2.3 through 2.5, using 2.6 for guidance.
5.1.1 Accomplish the requirements of 009-012 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line(s) 46, for each area listed in 1.3.3 through 1.3.8.
5.3 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
5.4 Notes:
5.4.1 Planner: Code 231A K. Abe, 243-3161
5.4.2 This TGI is in response to CCIMS report No. CCIMS-G1N6-DDG76-067-25 from TGI No. 38KBA11021I03.
5.4.3 This TGI clears DFS DDG-76-1023-2025 in its entirety.
5.4.4 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
5.4.5 Removal and installation of rubber tile on stringer, vertical stiffener, fashion plate, and watertight transverse bulkhead in main deck weather frames between 370 and 379 will be covered by TGI No(s). 38KB313103U01 and
38KB313103R01 (SRF-JRMC TGI).
5.4.6 Prior to commencement of the work, verification by Code 294 is required for work control and oversight relating to above, inside, or below the VLS launcher.
5.4.7 JCNs ES01-NALT, ES01-NALU, and ES01-NALW are related to this TGI.
5.5 Government Furnished Material (GFM):
5.5.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.6 SRF-JRMC will provide the following service work: (TGI No. 38KB313103S02).
5.6.1 [C740] Crane and crane rigging service.
5.6.2 [X99E] Utility service, electrical.
5.6.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.
5.6.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.6.6 [C133] QA Inspection for (G) symbol(s).
5.6.7 [C294] Work scope review and verification for VLS relating work prior to commencement of the work.
FOUO
J-1
SHIP: DDG-76 CHG/VER: 1/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
MAIN WEA STRCT AY A 0 0
CU PHASE TITLE:
F/O - REPAIR STRUCTURAL MEMBER IN MAIN DECK WEATHER
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
MAIN DECK EXT STBD MS
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
38KB313103 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to repair structural member in main deck weather.
Location of Work:
Main Deck Weather, Frames between 370 and 379, (Stbd) Supply Department Storeroom No. 2 (2-370-3-A) B-Size Module 61 Cell Vertical Launching System (3-338-0-M)
FOUO
M-1
SHIP: DDG-76 CHG/VER: 1/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
MAIN WEA STRCT AY A 0 0
CU PHASE TITLE:
F/O - REPAIR STRUCTURAL MEMBER IN MAIN DECK WEATHER
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
38KB313103 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M PLATE,ME, ORDER FOR KTR
ORIGINATOR C231A K. ABE
243-3161
9B 9515 002375333 NA 4 N 53535127 7/SF
002 M PLATE,ME, ORDER FOR KTR
ORIGINATOR C231A K. ABE
243-3161
9B 9515 002243086 NA 4 N 53535129 14/SF
NOTES:
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-76 MAIN WEA STRCT AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38KB313103 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-76 MAIN WEA STRCT AY A 0