Attachment (VII) Quality Assurance Surveillance Plan (QASP).pdf

PDF 236 KB Posted

Attached to
USS HIGGINS (DDG 76) 6C1 BUNDLE 3
Solicitation number
N6264926RA044
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) for the USS HIGGINS (DDG 76) FY26 maintenance contract under the Department of the Navy, Chief of Naval Operations (CNO) 6C1, Solicitation N6264926RA044, and serves as Attachment VII to the contract.

The QASP establishes the Government's framework for monitoring contractor performance to ensure deliverables are timely, adequate, and complete. The Administrative Contracting Officer (ACO) holds ultimate responsibility for determining performance adequacy and ensuring contractor compliance with contract terms, while the Project Manager/Contracting Officer Representative (PM/COR) manages technical administration and maintains a quality assurance file. The Government will employ three primary surveillance methods: direct on-site observation, verification of documentation and deliverables for accuracy and completeness, and inspections as needed for accident investigations and other circumstances. Performance will be continuously monitored with periodic reassessment of surveillance frequency appropriateness, and ratings will be assigned as either acceptable or unacceptable based on standards outlined in Enclosure (1). The Government will document all positive and negative performance for inclusion in past performance records via the Contractor Performance Assessment Report System (CPARS).

Enclosure (1) specifies five key performance standards and acceptable quality levels: submission of schedule and associated reports per NAVSEA Standard Item (NSI) 009-60, including Initial Integrated Production Schedule, Schedule of Record, Weekly IPS, and 25/50/75 Percent Conference Support deliverables in required formats; timely response and adequate resolution to Method C and Method D Corrective Action Requests; accurate submission of Condition Found Reports via hard copy or approved electronic media to SRF-JRMC containing required NSI 009-01 information; timely response and complete resolution to Letters of Concern and Letters of Direction issued by the ACO; and compliance with FAR 49.402-3 procedures requiring timely response and adequate resolution to cure notices and show cause notices.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926RA0440008 SF 30.pdf PDF
Solicitation Amendment - N6264926RA0440008 Conformed.pdf PDF
Solicitation Amendment N6264926RA0440005 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440004 SF 30.pdf PDF
Att IX HIG_6C1_B3_POP_List_R4.xlsx XLSX spreadsheet
Solicitation Amendment N6264926RA0440007 SF 30.pdf PDF
SOW_TGI_38KB312389A02_c0v0.pdf PDF
Attachment II Price Proposal Form N6264926RA044 (rev1).xlsx XLSX spreadsheet
SOW_TGI_38KB312389A03_c1v1.pdf PDF
Solicitation Amendment N6264926RA0440003 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440002 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440001 SF 30.pdf PDF
Exhibits - Contract Data Requirements List (CDRL).pdf PDF
Attachment (IV) Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
SOW_TGI_38KB313103A01_c1v0.pdf PDF
Attachment (II) Price Proposal Form N6264926RA044.xlsx XLSX spreadsheet
Attachment (VIII) Contracts Data Sheet.pdf PDF
SOW_TGI_38KB386501A01_c0v0.pdf PDF
SOW_TGI_38KB325102A01_c0v0.pdf PDF
SOW_TGI_38KB312389A01_c1v0.pdf PDF
SOW_TGI_38KB312388A01_c0v0.pdf PDF
SOW_TGI_38KB312387A01_c0v0.pdf PDF
SOW_TGI_38KB312386A01_c0v0.pdf PDF
Attachment (VI) Source of Repair Instruction.pdf PDF
Attachment (V) Warranty Tracking Information.pdf PDF
Attachment (III) Request for Information Sheet.docx DOCX document
Solicitation - N6264926RA044.pdf PDF
Pre-Solicitation Notice N6264926RA044.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

DEPARTMENT OF THE NAVY

Quality Assurance Surveillance Plan (QASP)

For

USS HIGGINS (DDG 76) FY26

Chief of Naval Operations (CNO) 6C1

Solicitation: N6264926RA044

Attachment VII

1. Purpose

This QASP provides the performance criteria, standards, and procedures for the Government’s surveillance and oversight of the Contractor’s performance to assure deliverables are timely, adequate, and complete and to assure performance is meeting the requirements specified in the contract.

2. Government Roles and Responsibilities

The following personnel shall oversee and coordinate surveillance activities:

a. Administrative Contracting Officer (ACO) – The ACO shall assure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The ACO shall also assure the contractor receives impartial, fair, and equitable treatment under this contract. The ACO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.

b. Project Manager (PM) / Contracting Officer Representative (COR) – The PM/COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The PM/COR shall keep a quality assurance file. The PM/COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.

3. Performance Standards

The performance and acceptable quality level standards are listed in Enclosure (1). The Government shall use these standards to assess contractor performance.

4. Methods of Surveillance

Various methods exist to monitor performance. The Government may use, and is not limited to, the surveillance methods listed below in the administration of this QASP:

a. Direct Observation: The ACO and/or PM/COR will provide on-site oversight to assure the Contractor is adequately performing to the contract specifications.

b. Verification of documentation/deliverables provided by Contractor: Government review and assessment of deliverables (timely submission, accuracy, and completeness) and performance will be accomplished in accordance with the contract/order.

c. Inspections: Other inspections may be made in cases such as accident investigations, etc.

Inspections shall be divided and scheduled as required.

5. Evaluation Ratings

The Government will evaluate the Contractor’s performance of the contract/order and the PM/COR will assign a rating of either acceptable or unacceptable. The acceptable quality levels are outlined in Enclosure (1).

6. Documenting Performance

The Government will document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing past performance information using the Contractor Performance Assessment Report System (CPARS).

7. Frequency of Measurement

Frequency of Measurement. The frequency of measurement for deliverables is defined in the contract/order. The contractor’s performance will be continuously monitored. The Government will periodically analyze whether the frequency of surveillance is appropriate for the work being performed.

Enclosure (1): Performance Standards & Acceptable Quality Levels

A) Deliverable/ Assessment Area B) Performance / Acceptable Quality Level Requirement

1. Schedule and Associated Reports per NAVSEA Standard Item (NSI) 009-60

a) The Contractor is required to submit the following reports (hereinafter referred to as deliverables), in accordance with the schedule requirements stated in NSI 009-60 Tables 2 and 3 to support the milestones identified in Section F of the Contract:

1. Initial Integrated Production Schedule (IPS)

2. Schedule of Record

3. Weekly IPS

4. 25 Percent Conference Support

5. 50 Percent Conference Support

6. 75 Percent Conference Support

b) Deliverables shall be provided in accordance with the content and format requirements stated in NSI 009-60.

Notes:

i. If the Government does not provide schedules/information for Alteration Installation Team, Government-Contracted Third Party Maintenance Providers, Ship’s Force, Commercial Industrial Services, Fleet Maintenance Activity, or other schedules/information not known to the contractor, the contractor shall provide the schedule and associated reports (including the IPS) in the required timeframes to include all information known to the contractor up to 7 days prior to the date of required submission.

ii. Should the supervisor and the contractor disagree as to whether an element within NSI 009-60 is objectively required or discretionary, the supervisor will provide direction and/or clarification, which will take effect on the next required submission of the NSI 009-60 deliverable.

iii. Rejection or acceptance of a NSI 009-60 deliverable will be determined on whether:

a. The deliverable provided conforms to the schedule, content and format requirements in NSI 009-60; and

b. The deliverable provided conforms to the Supervisor’s direction and/or clarification of any disputed objective/discretionary elements.

Enclosure (1): Performance Standards & Acceptable Quality Levels

2. Corrective Action Requests (CARs)

a) The Contractor shall respond to Method C and Method D CARs by the required response date in each respective CAR.

b) The Contractor’s response/resolution to a Method C or Method D CAR is complete and adequate.

3. Accuracy of Condition Found Reports (CFRs)

a) CFRs shall be submitted via hard copy or approved electronic media to SRF-JRMC after discovery of the condition and at a minimum, contain the information required by Section C Paragraph C-3.1 of the contract/order and NSI 009-01.

4. Letters of Concern (LOCs) and Letters of Direction (LODs)

a) The Contractor shall respond to LOCs and LODs issued by the ACO for failure to meet a requirement of the contract/order by the required response date identified in each respective LOC or LOD.

b) The Contractor’s response/resolution to a LOC or LOD issued by the ACO for failure to meet a requirement of the contract/order is complete and adequate.

5. Cure Notices and Show Cause Notices

a) In accordance with FAR 49.402-3Procedure for default, the Contractor shall respond to cure notices and show cause notices by the required response date identified in each respective notice.

b) The Contractor’s response/resolution to a cure notice or show cause notice is complete and adequate.

UNCLASSIFIED
DEPARTMENT OF THE NAVY
Quality Assurance Surveillance Plan (QASP)
For
USS HIGGINS (DDG 76) FY26
Chief of Naval Operations (CNO) 6C1
Solicitation: N6264926RA044
Attachment VII