This is Standard Form 30 (SF 30), an Amendment of Solicitation/Modification of Contract issued by the Naval Supply Flotilla Logistics Center in Yokosuka, Japan. The amendment is numbered 0001 with an effective date of 04 May 2026, amending solicitation N6264926RA044 dated 09 April 2026. The requisition number is N62649, and the contracting officer is Peter Jommel S. Arrieta.

The amendment serves three primary purposes: (1) cancellation of TGI 38KB312389A01; (2) revision of Section J (List of Attachments); and (3) response to a contractor question regarding critical coated area requirements. Regarding the question, the Government clarified that Technical Group Instructions (TGIs) 38KB312386A01, 38KB312387A01, and 38KB312388A01 involve preservation work consisting of touch-up coating for areas identified through visual inspection. Per NSI 009-032 paragraph 3.6.1.3, critical coated area preservation requirements are waived if the preservation area does not exceed 10 square feet and represents less than 10 percent of the total paint area of the compartment. If the contractor reports coating removed areas exceeding these thresholds, additional critical coated area preservation requirements will be processed by the Design Lead through a Change Request. Section J was modified to list six active TGIs: 38KB312386-A01, 38KB312387-A01, 38KB312388-A01, 38KB313103-A01, 38KB325102-A01, and 38KB386501-A01, with associated references to non-standard drawings, NAVSEA standard drawings, military standards, naval ships technical manuals, test procedures, and liaison documentation. The amendment includes eight attachments covering work specifications, proposal breakdown forms, Government furnished property listings, warranty tracking, quality assurance surveillance plans, and contract data requirements.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926RA0440008 SF 30.pdf PDF
Solicitation Amendment - N6264926RA0440008 Conformed.pdf PDF
Solicitation Amendment N6264926RA0440005 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440004 SF 30.pdf PDF
Att IX HIG_6C1_B3_POP_List_R4.xlsx XLSX spreadsheet
Solicitation Amendment N6264926RA0440007 SF 30.pdf PDF
Attachment II Price Proposal Form N6264926RA044 (rev1).xlsx XLSX spreadsheet
SOW_TGI_38KB312389A03_c1v1.pdf PDF
Solicitation Amendment N6264926RA0440003 SF 30.pdf PDF
SOW_TGI_38KB312389A02_c0v0.pdf PDF
Solicitation Amendment N6264926RA0440002 SF 30.pdf PDF
Exhibits - Contract Data Requirements List (CDRL).pdf PDF
Attachment (IV) Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
SOW_TGI_38KB313103A01_c1v0.pdf PDF
Attachment (VII) Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment (II) Price Proposal Form N6264926RA044.xlsx XLSX spreadsheet
Attachment (VI) Source of Repair Instruction.pdf PDF
Attachment (V) Warranty Tracking Information.pdf PDF
Attachment (III) Request for Information Sheet.docx DOCX document
Solicitation - N6264926RA044.pdf PDF
Attachment (VIII) Contracts Data Sheet.pdf PDF
SOW_TGI_38KB386501A01_c0v0.pdf PDF
SOW_TGI_38KB325102A01_c0v0.pdf PDF
SOW_TGI_38KB312389A01_c1v0.pdf PDF
SOW_TGI_38KB312388A01_c0v0.pdf PDF
SOW_TGI_38KB312387A01_c0v0.pdf PDF
SOW_TGI_38KB312386A01_c0v0.pdf PDF
Pre-Solicitation Notice N6264926RA044.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): The purpose of this amendment is as follows:

1. To cancel TGI 38KB312389A01.

2. To revise Section J.

3. To respond to the question received.

All other information remains unchanged.

Questions and Responses Below is the question received and the Government's response:

Question (1) For 38KB312386A01 (Para 5.10), 38KB312387A01 (Para 5.9), and 38KB312388A01 (Para 5.7), the following items are included:

GTM Intake SSGTG Intake Intake/Exhaust Trunk However, there is no description of the critical coated area in the TGI.

Is it possible to confirm requirement of Critical coated area?

Government Answer (1) TGIs don't describe critical coated area because the preservation work of Para 38KB312386A01(5.10)/38KB312387A01(5.9)/38KB312388A01(5.7) of below TGIs is touch up for coating removed areas that are reported by visual inspection.

Para 3.6.1.3 of NSI 009-032 states that even though it is critical coated area, if preservation area is not greater than 10SF and less than 10% of total paint area of the compartment, it is handled as touch up and requirement of critical coated area preservation is waived.

If the contractor reported coating removed area is greater than 10SF or 10%, additional requirement of critical coated area preservation will be processed by DL per CR.

Section J - List of Attachments

Miscellaneous text in this section has been modified to:

Attachment (I) Work Specification(s) for TGI

38KB312386-A01

38KB312387-A01

38KB312388-A01

38KB313103-A01

38KB325102-A01

38KB386501-A01

SRF Reference:

Non-Standard Drawings Builder's Drawings

NAVSEA Standard Drawings Military Standards

Naval Ships Technical Manuals Test Procedures

Liaison Action Record Form (LAR)

N6264926RA0440001

Engineering Liaison Memorandum (ELM)

Attachment (II) Proposal Breakdown Form (Contractor Response Required)

Attachment (III) Request for Information Sheet

Attachment (IV) Government Furnished Property (GFP-GFM listings)

Attachment (V) Warranty Tracking Information

Attachment (VI) Source of Repair Instruction

Attachment (VII) Quality Assurance Surveillance Plan (QASP)

Attachment (VIII) Contracts Data Sheet

Exhibits: Contract Data Requirements List (CDRL)

N6264926RA0440001

IDCode: J
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 04 May 2026
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N62649
AdmCode:
IssuedBy: NAVSUP FLT LOG CTR YOKOSUKA

PSC 473 BOX 11, FPO AP 96349-1500

FPO, AP 96349-1500

UNITED STATES

Risa Sakurai, Email: risa.sakurai.ln@us.navy.mil Telephone: 315-243-8400 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N6264926RA044
SolDate: 09 Apr 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: Peter Jommel S. Arrieta
ContDate:
CODate: 04 May 2026