This is a Task Group Instruction (TGI) for maintenance work on the USS Higgins (DDG-76), a naval destroyer. The instruction document establishes requirements for inspection, repair, and preservation of the forward uptake space system, with work scheduled from June 29, 2026 through December 8, 2026.
The work encompasses multiple compartments and systems across the vessel, including the 05 Level Weather deck (Frames 189-216, Port and Starboard), Uptake Engine Room No. One, Ships Service Gas Turbine Generator (SSGTG) exhaust and intake trunks, passage ways, fan rooms, communication centers, Halon Cylinder Room, administrative offices, Tomahawk Equipment Room, and Auxiliary Machinery Room No. One. Specific deliverables include visual inspection of exterior and interior surfaces for corrosion and structural integrity; power tool cleaning to bare metal (up to 3,578 square feet); ultrasonic thickness measurements at up to 100 locations; removal and installation of three Boundary Layered Infrared Suppression (BLISS) caps; base metal weld build-up (up to 160 square inches); plate replacement (up to 94 square feet); stiffener installation (up to 75 linear feet); weld repairs (up to 25 linear feet); and surface coating per SSPC-SP 11 standards. The contractor must submit inspection reports with sketches identifying deficiencies and repair areas. A critical special requirement mandates fabrication and staging of a non-flammable closure to maintain fire zone boundaries during access work. Government-furnished materials include fibrous glass gaskets and ferrules, with the Navy providing crane services, utilities, and QA inspections. The instruction references multiple engineering drawings, maintenance standards, and nondestructive testing requirements per Navy and military specifications.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: FWD UPTAKE SPACE AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-76 USS HIGGINS KB3
CU PHASE TITLE:
F/O - INSPECT, REPAIR, AND PRESERVE FWD UPTAKE SPACE
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
KAZUMI WATANABE 231A 315-243-4518 19-DEC-2025
APPROVED BY: CODE PHONE DATE
YUUJI NAKAMURA 231A 315-243-6041 19-DEC-2025
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
SURFMEPP
This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: FWD UPTAKE SPACE AY A 0
FOUO
SHIP: DDG-76 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-7 J1-2 M1-4
1. SCOPE/PURPOSE
1.1 Title: Inspection, Repair, and Preservation of Forward Uptake Space; accomplish
1.2 Location of Work:
1.2.1 05 Level Weather, Frames between 189 and 216, Port and Starboard (Stbd)
1.2.2 Uptake Engine Room No. One (02-186-0-Q)
1.2.3 Intake/Uptake Engine Room No. One (01-174-0-Q)
1.2.4 Ships Service Gas Turbine Generator (SSGTG) Exhaust Trunk (2-166-2-Q)
1.2.5 Intake/Uptake Engine Room No. One (1-174-3-Q)
1.2.6 Passage (01-118-1-L)
1.2.7 SSGTG Intake Trunk (2-161-2-Q)
1.2.8 Fan Room Radio Transmitter Room Communication Center, Combat Information Center (01-158-0-Q)
1.2.8.1 Vent Plenum for HVAC Recirculating System (RS) 01-169-1
1.2.9 Halon Cylinder Room No. One (1-186-1-A)
1.2.10 Administer Office (1-158-4-Q)
1.2.11 Tomahawk Equipment Room (2-153-2-C)
1.2.12 Auxiliary Machinery Room No. One (4-126-0-E)
1.3 Identification:
1.3.1 Quantity (One Lot), Exterior Surface of 05 Level Deck Plating, Frames between 189 and 216, including vertical surface up to height of top of shroud from above 76 feet 5 inches above base line, Port and Stbd
1.3.2 Quantity (One EA), Boundary Layered Infrared Suppression System (BLISS) Cap, 1A Propulsion Gas Turbine Exhaust
1.3.3 Quantity (One EA), BLISS Cap, 1B Propulsion Gas Turbine Exhaust
1.3.4 Quantity (One EA), BLISS Cap, No. One SSGTG Exhaust
1.3.5 Quantity (One EA), 1A Propulsion Gas Turbine Exhaust Duct
1.3.6 Quantity (One EA), 1B Propulsion Gas Turbine Exhaust Duct
1.3.7 Quantity (One EA), SSGTG No. One Exhaust Duct
FOUO
SHIP: DDG-76 CHG/VER: 0/0
1.3.8 Quantity (One EA), 02 Level, 1A Module Gas Turbine Engine Deck Foundation and Bolting Ring
1.3.9 Quantity (One EA), 02 Level, 1B Module Gas Turbine Engine Deck Foundation and Bolting Ring
1.3.10 Quantity (One EA), 02 Level, Engine Room No. One SSGTG Deck Foundation and Bolting Ring
1.4 Security Classification:
1.4.1 Spaces - 1.2.11
1.5 Initial Condition: None.
1.6 Contractor work start date: 29/JUN/2026
1.7 Contractor work completion date: 8/DEC/2026
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
3 MP AL14-
KB312386-
CF03ZBM0
NO.1 SSGTG INTAKE SYSTEM
FOD PROTECTION FOR UPTAKE
PRESERVATION IN 2-166-2-Q
- Y AL
L
4 DWG 180-
6219046
Fdn Arr Dwg Dsgn Zone 4420 Bklt No.1
R Y SE
E N
OT
E
5 DWG 100-
6218913
UNIT STRL ARR DWG ASSY UNIT
W Y 3-
6 DWG 100-
6218918
UNIT STRL ARR DWG ASSY UNIT
R Y 3-
7 DWG 100-
6218914
UNIT STRL ARR DWG ASSY UNIT
W Y SE
E N
OT
E
8 DWG 100-
6218919
UNIT STRL ARR DWG ASSY UNIT
V Y SE
E N
OT
E
9 DWG 100-
6218915
UNIT STRL ARR DWG ASSY UNIT
V Y SE
E N
OT
E
10 DWG 100-
6218920
UNIT STRL ARR DWG ASSY UNIT
V Y SE
E N
OT
E
11 DWG 150-
6218955
UNIT STRL ARR DWG ASSY UNIT
Y Y SE
E N
OT
E
FOUO
SHIP: DDG-76 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
12 DWG 150-
6218962
UNIT STRL ARR DWG ASSY UNIT
V Y SE
E N
OT
E
13 DWG 150-
6218964
UNIT STRUCTURAL ARR DWG
ASSY UNIT 4410
W Y SE
E N
OT
E
14 DWG 150-
6218965
UNIT STRL ARR DWG ASSY UNIT
U Y SE
E N
OT
E
15 DWG 259-
6218406
FAB & INSTL OF GTRB UPTAKE &
AIR INTAKE ENG RM NO.1 &
ABOVE
W N
16 DWG 259-
6218421
FAB & INSTL of SS GTRB Uptake & Air Intakes AUX MCHRY RM
NO.1 & ABV
AB N
17 DWG 259-
8436353
SHIPALT DDG-51-76087 GTRB &
SS GTRB BLISS CAP MODS & ML
A Y AL
L
18 LAR
76087/DDG7
2/1141796
EXHAUST ANCHOR FDN CHOCK
NOT CONFIGURED LIKE
DRAWING
- Y AL
L
19 TM
SYSTEMS &
SPECIFICAT
IONS
SSPC Painting Manual Volume 2 - N
20 TM T9074-
AS-GIB-
010/271
Requirements for Nondestructive Testing Methods
1 N
21 TM S9086-
DA-STM-
010/CH-100
Hull Structures 4 N
22 MIL MIL-
STD-2035
Nondestructive Testing Acceptable Criteria
A N
3. APPENDICES:
3.1 Appendix “J” TGI Job Summary Information Sheet
3.2 Appendix "M" TGI Material List
3.3 Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Accomplish the requirements of 2.3.
(V)(G) “GAS TURBINE MAINTENANCE PROCEDURE”
5.2 Accomplish a visual inspection of the current ship condition, listed in 1.3.1 through 1.3.10, located in 1.2.1 through 1.2.5, using 2.4 through 2.18 for guidance, and as designated by the SUPERVISOR.
FOUO
SHIP: DDG-76 CHG/VER: 0/0
5.2.1 Ensure to inspect each exterior vertical, horizontal, step platform, deck, and foundation surface, and each interior exhaust stack, uptake duct, anchor foundation, eductor, eductor nozzle, eductor foundation, flange joint, overhead, bulkhead, deck, restraint, steel channel, penetration, deck spool, ladder foundation, bolting ring, and pipe hanger.
5.2.2 Mark each identified and designated area requiring repair.
5.2.3 Submit one legible copy, in hard copy or approved transferrable media, of a report with a sketch listing results of the requirements of 5.2 to the SUPERVISOR.
5.3 Remove each BLISS cap listed in 1.3.2 through 1.3.4, located in 1.2.1, using 2.17 and 2.18 for guidance.
5.4 Power tool clean to bare metal for each location reported in 5.2.3, listed in 1.3.1 through 1.3.10, located in 1.2.1 through 1.2.5, to include each exposed longitudinal, vertical, and transverse stiffener, for up to 3,578 square feet.
Accomplish each requirement of Surface Preparation Specification SSPC-SP 11 of 2.19, as designated by the
SUPERVISOR.
5.5 Accomplish a visual inspection in each location for coating removed in 5.4, listed in 1.3.1 through 1.3.10, located in 1.2.1 through 1.2.5 for structural integrity, deterioration, pitting, each crack, and area of damage or distortion, using
2.4 through 2.18 for guidance.
5.5.1 Mark each corroded, damaged and/or deteriorated area.
5.5.2 Submit one legible copy, in hard copy or approved transferable media, of a report with a sketch listing results of the requirements of 5.5 to the SUPERVISOR.
5.6 Accomplish each ultrasonic thickness measurement (UTM) up to 100 locations in each location reported in 5.5.2, listed in 1.3.1 through 1.3.10, located in 1.2.1 through 1.2.5 in accordance with Paragraph 6.7 of 2.20 and 2.21, as designated by the SUPERVISOR, using 2.4 through 2.18 for guidance. The acceptance criteria must be in accordance with 2.22.
5.6.1 Submit one legible copy, in hard copy or approved transferable media, of a report listing results of the requirements of 5.6 to the SUPERVISOR.
5.6.2 Ensure a sketch showing each location of each UTM reading, original material thickness, existing material thickness, and percentage of material thickness reduction.
5.7 Accomplish the following repairs to each BLISS Cap listed in 1.3.2 through 1.3.4, located in 1.2.1, in accordance with 2.15 through 2.18 as designated by the SUPERVISOR. See 5.15.4 and 5.15.5.
5.7.1 Remove existing and install new, up to 30 square feet of BLISS Cap.
5.8 Accomplish the following repairs reported in 5.2.3, 5.5.2, and 5.6.1, listed in 1.3.1 and 1.3.5 through 1.3.10, located in 1.2.1 through 1.2.5, using 2.4 through 2.18 for guidance, as designated by the SUPERVISOR. See 5.15.4 and 5.15.5.
5.8.1 Base metal weld build-up, up to 160 square inches.
5.8.1.1 Ensure each base metal buildup area does not exceed 2 inches in diameter.
5.8.1.2 Estimate the base metal buildup repair to be one quarter inch thick for pricing purposes.
5.8.1.3 Fill each local pit and groove with weld metal prior to the application of each principal build-up layer.
5.8.1.4 Ensure each surface is ground smooth to metal.
FOUO
SHIP: DDG-76 CHG/VER: 0/0
5.8.2 Remove existing and install new, up to 94 square feet of plate for each bulkhead, overhead, and deck plate.
5.8.3 Remove existing and install new, up to 75 linear feet of longitudinal, vertical, and traverse stiffener.
5.8.4 Remove existing and install new, up to 5 square feet of eductor foundation and flange joint.
5.8.5 Remove existing and install new each deck spool, gasket and bolting ring.
5.8.6 Vee out and weld up to 25 linear feet of cracked, split, broken or damaged weld.
5.8.7 Chip and grind each surface flush in way of each repair.
5.8.8 Template exact size, configuration, and location from each existing shipboard condition.
5.8.9 Accomplish the requirements of 009-012 of 2.1, including Table 2, Columns A, B, and D, Lines One through 7.
5.8.10 Accomplish the requirements of 009-025 of 2.1 for a local air hose test of each new weld seam. Allowable leakage: None.
5.9 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line(s) 3, for coating removed in 5.4, listed in 1.3.1.
5.10 Accomplish the requirements of 009-032 of 2.1, including Table 3, Line(s) 22A, for coating removed in 5.4, located in 1.2.2 through 1.2.5.
5.11 Accomplish the requirements of 009-032 of 2.1, including Table 5, Line(s) 15A, for each Bliss Cap listed in
1.3.2 through 1.3.4.
5.12 Install each BLISS cap listed in 1.3.2 through 1.3.4, located in 1.2.1, in accordance with 2.17 and 2.18.
5.13 Confirm that all personnel have exited the space prior to closure of the space listed in 1.2.3 through 1.2.5, and
1.2.8.1. Designate one person to account for all personnel who may have entered the space.
5.14 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
5.15 Notes:
5.15.1 Planner: Code 231A K. Watanabe, 243-4518
Planner: Code 234 T. Tsunoi, 070-7787-2058
5.15.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
5.15.3 This TGI meets the intent of DDG CSWT File No. 259-089.
5.15.4 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair in 5.7 and 5.8 are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.15.5 Materials for structural members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
5.15.6 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The
FOUO
SHIP: DDG-76 CHG/VER: 0/0
closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.15.7 WPC will copy the following pages in reference.
REF. 2.4: Pages 4, 4A-5, 5A1-9, 5B1-9, 5C1-9, 5D1-9, 5E1-9, 5F1-9, 7A1-7, 7B1-7, and 7C1-7.
REF. 2.7: Pages 5B-9, 7-11, 3-11, and 6-9.
REF. 2.8: Pages 5-11 and 3-10.
REF. 2.9: Pages 3-11, 5A-11, and 6-11.
REF. 2.10: Pages 3-11, 3A-11, and 5-11.
REF. 2.11: Pages 3-11, 5B-11, 7-11, and 5C-7.
REF. 2.12: Pages 7-1, 3-5, 6-5, 6A-5, 7B-10, and 5-5.
REF. 2.13: Pages 7-5, 6A-9, 3-11, and 5A-11.
REF. 2.14: Pages 3B-9, 3-7, 3D-7, 3A-10, and 3H-10.
5.15.8 JCNs CF03-ZBM0, EM01-ZCJ1, EM01-ZCJ2, EM01-ZCJ3, and EM01-ZCJ4 are related to this TGI.
5.16 Government Furnished Material (GFM):
5.16.1 SRF-JRMC will provide GFM listed in Appendix ”M”.
5.17 SRF-JRMC will provide the following service work: (TGI No. 38KB312386S02).
5.17.1 [C740] Crane and crane rigging service.
5.17.2 [X99E] Utility service, electrical.
5.17.3 [X99M] Utilities service, including water supply, steam supply, and low pressure air supply except onboard blasting work.
5.17.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.17.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.17.6 [C133] QA Inspection for (G) symbol(s).
5.17.7 [C285] Inspection for (G) symbol(s).
FOUO
J-1
SHIP: DDG-76 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
FWD UPTAKE SPACE AY A 0 0
CU PHASE TITLE:
F/O - INSPECT, REPAIR, AND PRESERVE FWD UPTAKE SPACE
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
CMPT 01-174-0-Q MS #1 SSGTG UPTAKE UT 05LVL & ABV EXTERIOR MS CMPT 2-166-2-Q
MS CMPT 1-174-3-Q MS #1 SSGTG INTAKE IT VNT RS 01-169-1 DT #1A GTM
UPTAKE UT #1B GTM UPTAKE UT CMPT 02-186-0-Q MS
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
38KB312386 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to inspect, repair, and preserve forward uptake space.
Location of Work:
05 Level Weather, Frames between 189 and 216, Port and Starboard (Stbd) Uptake Engine Room No. One (02-186-0-Q) Intake/Uptake Engine Room No. One (01-174-0-Q) Ships Service Gas Turbine Generator (SSGTG) Exhaust Trunk (2-166-2-Q) Intake/Uptake Engine Room No. One (1-174-3-Q) Passage (01-118-1-L) SSGTG Intake Trunk (2-161-2-Q) Fan Room Radio Transmitter Room Communication Center, Combat Information Center (01-158-0-Q) Vent Plenum for HVAC Recirculating System (RS) 01-169-1 Halon Cylinder Room No. One (1-186-1-A) Administer Office (1-158-4-Q) Tomahawk Equipment Room (2-153-2-C) Auxiliary Machinery Room No. One (4-126-0-E)
FOUO
J-2
SHIP: DDG-76 CHG/VER: 0/0
FOUO
M-1
SHIP: DDG-76 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
FWD UPTAKE SPACE AY A 0 0
CU PHASE TITLE:
F/O - INSPECT, REPAIR, AND PRESERVE FWD UPTAKE SPACE
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
1 259-8436353
JOB ORDER: KEY OP:
38KB312386 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
400 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
TAPE,
SPEC: HH-P-31, TYPE I, CLASS
2, SIZE: 1/2"W X 1/8"THK X 20FT
L, REMARKS: NON ASBESTOS
REQUIRED,
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5330 LL4924382 NA 4 N 13/RO
NOTES:
FOUO
M-2
SHIP: DDG-76 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
401 M GASKET,FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, MATERIAL: FIBER GLASS,
WIRE INSERT, FIBER GLASS
SIZE: 81-11/16" OD X 76-7/16"
ID X 3/8" THK, BOLT CIRCLE
DIA: 79-11/16" , 36 BOLT
HOLES, 25/32 DIA HOLES,
HOLES EQUALLY SPACED
BIW CAT# 52248-469,
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5330 LL9810157 NA 4 N 4/EA
402 M FERRULE, FERRULE, FIBROUS
GLASS, WIRE-REINFORCED
PLAIN, CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 31/32"OD X 21/32"ID X
1/2" THK,
REMARKS: NON ASBESTOS
REQUIRED,
BIW CAT NO. 54638-027,
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5340 LL4941032 NA 4 N
350/EA
403 M WASHER,2, WASHER,
FIBROUS GLASS, WIRE-
REINFORCED PLAIN, CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
SIZE: 2" OD X 21/32" ID, 3/8"
THK.
BIW CAT#: 52419-026
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9Z 5310 LL4917124 NA 4 N 53467404
420/EA
404 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 88-11/16” OD X 83-7/16”
ID X 3/8” THK,
BOLT CIRCLE DIA: 86-11/16”,
40 BOLT HOLES, 25/32” DIA
HOLES, HOLES EQUALLY
SPACED,
BIW CAT# 52248-442
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5330 LL9810187 NA 4 N 2/SH
FOUO
M-3
SHIP: DDG-76 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
405 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 53-11/16"OD X 48-7/16"ID
X 3/8"THK,
REMARKS:BOLT CIRCLE DIA
51-11/16" (24) 25/32"DIA
HOLES* HOLES EQUALLY
SPACED*
BIW CAT NO. 52248-434
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5330 LL9604082 NA 4 N 3/EA
406 M FERRULE, FERRULE, FIBROUS
GLASS, WIRE-REINFORCED
PLAIN, CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 31/32"OD X 21/32"ID X
3/8"LG,
REMARKS: NON ASBESTOS
REQUIRED,
BIW CAT#: 54638-035,
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5340 LL4941033 NA 4 N
120/EA
407 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 62-11/16"OD X 57-7/16"ID
X 3/8"THK,
BOLT CIRCLE DIA: 60-11/16",
30 BOLT HOLES, 25/32" DIA
HOLES, EQUALLY SPACED,
REMARKS: NON ASBESTOS
REQUIRED,
BIW CAT NO. 52248-426,
C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5330 LL4941030 NA 4 N 1/EA
408 105 1 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 104-7/8" OD X 95-1/8" ID X
3/8" THK,
BOLT CIRCLE DIA: 102-3/8", 40
BOLT HOLES, 9/16" DIA
HOLES, EQUAL SPACED,
BIW CAT#: 52248-710 (OLD:
88033-507), C234 T.TSUNOI, 070-7787-2058
9B 5330 LL7051201 NA 4 N 2/EA
FOUO
M-4
SHIP: DDG-76 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
409 119 1 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 60-7/8" OD X 51-1/8" ID X
3/8" THK,
BOLT CIRCLE DIA: 58-3/8", 24
BOLT HOLES, 9/16" DIA
HOLES, EQUALLY SPACED,
BIW CAT#: 52248-728 (OLD:
88033-493), C234 T.TSUNOI, 070-7787-2058
ORDER FOR KTR
9B 5330 LL7051200 NA 4 N 1/EA
410 M GASKET,FIBROUS GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 106-11/16"OD X 101-
7/16"ID X 3/8"THK,
BOLT CIRCLE DIA: 104-11/16",
40 BOLT HOLES, 25/32" DIA
HOLES, HOLES EQUALLY
SPACED,
BIW CAT NO. 52248-451
C234 T.TSUNOI, 070-7787-2058
9B 5330 LL4941031 NA 4 N 2/EA
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-76 FWD UPTAKE SPACE AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38KB312386 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-76 FWD UPTAKE SPACE AY A 0
File details come from the government source that posted it. Updated .