Task Group Instruction for USS HIGGINS (DDG-76) AFT Intake Inspection, Repair, and Preservation

This Task Group Instruction (TGI) is a naval shipyard work directive for performing inspection, repair, and preservation activities on Engine Room No. 2 Gas Turbine Module (GTM) and Ship Service Gas Turbine Generator (SSGTG) No. 2 dirty side intake systems aboard USS HIGGINS (DDG-76). The contractor work runs from June 29, 2026, through December 8, 2026, with preparation and approval completed on April 30, 2026. The work encompasses multiple intake locations including port and starboard dirty and clean side intakes, intake trunks, and related structural components identified by specific compartment numbers.

The required work tasks include conducting visual inspections of current ship conditions; power tool cleaning to bare metal (up to 600 square feet) in accordance with Surface Preparation Specification SSPC-SP 11; additional visual inspections of cleaned surfaces for structural integrity; ultrasonic thickness measurements at up to 100 locations per area; and specified repairs comprising base metal buildup (50 square inches total), removal and installation of new deck/overhead/bulkhead sections (15 square feet total), removal and installation of new stiffeners (10 linear feet total), and vee-out and weld repairs of cracked intake welds (4 linear feet total). All repairs must be followed by surface grinding, coating per specification 009-032, and air hose testing of new welds with zero allowable leakage. A critical special requirement mandates fabrication and staging of a non-flammable closure due to the work affecting fire zone boundaries. Supporting services provided by SRF-JRMC include crane rigging, electrical and mechanical utilities, safety inspections, gas-free inspections, QA inspections, and on-site engineering support.

View the file

Other files

File Type Posted
Solicitation Amendment - N6264926RA0440008 Conformed.pdf PDF
Solicitation Amendment N6264926RA0440008 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440004 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440005 SF 30.pdf PDF
Att IX HIG_6C1_B3_POP_List_R4.xlsx XLSX spreadsheet
Solicitation Amendment N6264926RA0440007 SF 30.pdf PDF
Attachment II Price Proposal Form N6264926RA044 (rev1).xlsx XLSX spreadsheet
SOW_TGI_38KB312389A03_c1v1.pdf PDF
Solicitation Amendment N6264926RA0440003 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440002 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440001 SF 30.pdf PDF
Exhibits - Contract Data Requirements List (CDRL).pdf PDF
Attachment (VIII) Contracts Data Sheet.pdf PDF
SOW_TGI_38KB386501A01_c0v0.pdf PDF
SOW_TGI_38KB325102A01_c0v0.pdf PDF
SOW_TGI_38KB312389A01_c1v0.pdf PDF
SOW_TGI_38KB312388A01_c0v0.pdf PDF
SOW_TGI_38KB312387A01_c0v0.pdf PDF
SOW_TGI_38KB312386A01_c0v0.pdf PDF
Attachment (IV) Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
SOW_TGI_38KB313103A01_c1v0.pdf PDF
Attachment (VII) Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment (II) Price Proposal Form N6264926RA044.xlsx XLSX spreadsheet
Attachment (VI) Source of Repair Instruction.pdf PDF
Attachment (V) Warranty Tracking Information.pdf PDF
Attachment (III) Request for Information Sheet.docx DOCX document
Solicitation - N6264926RA044.pdf PDF
Pre-Solicitation Notice N6264926RA044.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: AFT INTAKE AY A 0 0

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

DDG-76 USS HIGGINS KB3

CU PHASE TITLE:

F/O – INSPECT, REPAIR, AND PRESERVE IN NO. 2 GTM AND SSGTG NO. 2 INTAKE

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

MISAKI KANEHIRA 231A 315-243-9883 30-APR-2026

APPROVED BY: CODE PHONE DATE

YUUJI NAKAMURA 231A 315-243-6041 30-APR-2026

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

CHANGE INSTRUCTIONS:

SPECIAL REQUIREMENTS:

SURFMEPP

This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: AFT INTAKE AY A 0

FOUO

SHIP: DDG-76 CHG/VER: 0/0

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-6 J1-2 M-1

1. SCOPE/PURPOSE

1.1 Title: Engine Room No. 2 Gas Turbine Module (GTM) and Ship Service Gas Turbine Generator (SSGTG) No. 2 Dirty Side Intake; inspect, repair, and preserve

1.2 Location of Work:

1.2.1 Intake Engine Room No. 2, Port (Dirty Side) (02-284-0-Q)

1.2.2 Intake Engine Room No. 2, Starboard (Stbd) (Dirty Side) (02-284-0-Q)

1.2.3 Intake Engine Room No. 2, Port (Dirty Side) (02-275-0-Q)

1.2.4 Intake Engine Room No. 2, Stbd (Dirty Side) (02-275-0-Q)

1.2.5 Intake Engine Room No. 2, Port (Dirty Side) (03-274-0-Q)

1.2.6 Intake Engine Room No. 2, Stbd (Dirty Side) (03-274-0-Q)

1.2.7 Ship Service Gas Turbine Generator (SSGTG) Intake (Dirty Side) (01-260-1-Q)

1.2.8 Intake Trunk (A) Engine Room No. 2 (1-289-2-Q)

1.2.9 Intake Engine Room No. 2, Port and Stbd (Clean Side) (02-284-0-Q)

1.2.10 Intake Engine Room No. 2 (01-276-0-Q)

1.2.11 Intake Engine Room No. 2, Port and Stbd (Clean Side) (02-275-0-Q)

1.2.12 Intake Engine Room No. 2, Port and Stbd (03-274-0-Q)

1.2.13 SSGTG Intake (Clean Side) (01-260-1-Q)

1.2.14 SSGTG Intake Trunk (1-260-1-Q)

1.3 Identification:

1.3.1 Quantity (One EA), Dirty Side of No. 2A GTM Intake in 02-284-0-Q

1.3.2 Quantity (One EA), Dirty Side of No. 2B GTM Intake in 02-275-0-Q

1.3.3 Quantity (One EA), Dirty Side of No. 2B GTM Intake in 03-274-0-Q

1.3.4 Quantity (One EA), Dirty Side of SSGTG No. 2 Intake in 01-260-1-Q

1.4 Security Classification: None.

1.5 Initial Condition: None.

FOUO

SHIP: DDG-76 CHG/VER: 0/0

1.6 Contractor work start date: 29/JUN/2026

1.7 Contractor work completion date: 8/DEC/2026

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 MP LM23-

KB312389-

EM02ZBY2

2A /2B GTM & NR.2/NR.3 SSGTG

INTK SYS FOD PRTN FOR INTK

DIRTY SIDE PARTIALLY RPR

- Y AL

L

4 DWG 100-

6218930

UNIT STRUCTURAL ARR DWG-

ASSY UNIT 2450

Y Y 3-

5 DWG 150-

6218967

UNIT STRL ARR DWG ASSY UNIT

V Y SE

E N

OT

E

6 DWG 150-

6218969

UNIT STRUCTURAL ARR DWG

ASSY 4610

V Y 3-9

7 DWG 150-

6218971

UNIT STRL ARR DWG ASSY UNIT

Y Y SE

E N

OT

E

8 TM

SYSTEMS &

SPECIFICAT

IONS

SSPC Painting Manual Volume 2 - N

9 TM T9074-

AS-GIB-

010/271

Requirements for Nondestructive Testing Methods

1 N

10 TM S9086-

DA-STM-

010/CH-100

Hull Structures 4 N

11 MIL MIL-

STD-2035

Nondestructive Testing Acceptable Criteria

A N

3. APPENDICES:

3.1. Appendix “J” TGI Job Summary Information Sheet

3.2. Appendix "M" TGI Material List

3.3. Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Accomplish the requirements of 2.3.

(V)(G) "GAS TURBINE MAINTENANCE PROCEDURE"

FOUO

SHIP: DDG-76 CHG/VER: 0/0

5.2 Accomplish a visual inspection of the current ship condition, listed in 1.3.1 through 1.3.4 and located in 1.2.1 through 1.2.7, using 2.4 through 2.7 for guidance.

5.2.1 Ensure to inspect each deck, bulkhead, overhead surface, steel channel, stiffener, penetration, pipe hanger and vibration damping.

5.2.2 Mark each corroded, damaged and/or deteriorated area.

5.2.3 Submit one legible copy, in hard copy or approved transferable media, of a report with a sketch listing results of the requirements of 5.2 to the SUPERVISOR.

5.3 Power tool clean to bare metal each location reported in 5.2.3, located in 1.2.1 through 1.2.7, to include each exposed longitudinal, vertical, and traverse stiffener, for up to 600 square feet. Accomplish each requirement of Surface Preparation Specification SSPC-SP 11 of 2.8, as designated by the SUPERVISOR.

5.4 Accomplish a visual inspection of each surface power tool cleaned to bare metal in 5.3, listed in 1.3.1 through 1.3.4, located in 1.2.1 through 1.2.7 for structural integrity, deterioration, pitting, each crack, and area of damage or distortion, using 2.4 through 2.7 for guidance.

5.4.1 Mark each corroded, damaged and/or deteriorated area.

5.4.2 Submit one legible copy, in hard copy or approved transferable media, of a report with a sketch listing results of the requirements of 5.4 to the SUPERVISOR.

5.5 Accomplish each ultrasonic thickness measurement (UTM) up to 100 locations in each location reported in 5.4.2, listed in 1.3.1 through 1.3.4, located in 1.2.1 through 1.2.7 in accordance with Paragraph 6.7 of 2.9 and 2.10, as designated by the SUPERVISOR, using 2.4 through 2.7 for guidance. The acceptance criteria must be in accordance with 2.11.

5.5.1 Submit one legible copy, in hard copy or approved transferable media, of a report listing results of the requirements of 5.5 to the SUPERVISOR.

5.5.2 Ensure a sketch showing each location of each UTM reading, original material thickness, existing material thickness, and percentage of material thickness reduction.

5.6 Accomplish the following repairs reported in 5.2.3, 5.4.2 and 5.5.1, listed in 1.3.1 through 1.3.4, located in 1.2.1 through 1.2.7 as designated by the SUPERVISOR, using 2.4 through 2.7 for guidance. See 5.9.5 and 5.9.6.

5.6.1 Base metal buildup, a total of 50 square inches.

5.6.1.1 Ensure each base metal buildup area does not exceed 2 inches in diameter.

5.6.1.2 Estimate the base metal buildup to be one quarter inch thick for pricing purposes.

5.6.1.3 Fill each local pit and groove with metal prior to the application of each principal build-up layer.

5.6.1.4 Each surface must be ground smooth to metal.

5.6.2 Remove existing and install new, a total of 15 square feet of deck, overhead, and bulkhead.

5.6.3 Remove existing and install new, a total of 10 linear feet of longitudinal, vertical, and transverse stiffener.

5.6.4 Vee out and weld a total of 4 linear feet of cracked, split, broken or damaged intake weld.

5.6.5 Chip and grind each surface flush in way of each repair.

FOUO

SHIP: DDG-76 CHG/VER: 0/0

5.6.6 Template exact size, configuration, and location from each existing shipboard condition.

5.6.7 Accomplish the requirements of 009-012 of 2.1, including Table 2, Columns A and D, Lines One through 7.

5.6.8 Accomplish the requirements 009-025 of 2.1 for an air hose test of each new weld seam. Allowable leakage:

None.

5.7 Accomplish the requirements of 009-032 of 2.1, including Table 3, Line(s) 20, located in 1.2.1 through 1.2.7, for coating removed in 5.3.

5.7.1 Power tool clean to bare metal for each area. Accomplish each requirement of Surface Preparation Specification SSPC-SP 11 of 2.8.

5.8 Accomplish the requirements of 009-032 of 2.1 for new and disturbed surface.

5.9 Notes:

5.9.1 Planner: Code 231A M. Kanehira, 243-9883

Planner: Code 231A R. Nanba, 243-6141

5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560.

5.9.3 This TGI meets the intent of DDG CSWT File No. 251-044.

5.9.4 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkhead normally used to control air flow in the event of a shipboard fire. A non- flammable closure is required in accordance with COMNAVDEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

5.9.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.

5.9.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.

5.9.7 WPC will copy the following pages in reference.

REF. 2.5: Sheets 5A-11, 6-11, 7B-11, and 3-11.

REF. 2.7: Sheets 5B-2, 5-4, 3-9, and 7B-7.

5.9.8 JCNs EM02-ZBY2, EM02-ZBY3, EM02-ZBY4, and EM02-ZBY5 are related to this TGI.

5.10 Government Furnished Material (GFM): None

5.11 SRF-JRMC will provide the following service work: (TGI No. 38KB312389S02)

5.11.1 [C740] Provide crane and crane rigging service.

5.11.2 [X99E] Provide utility service, electrical.

5.11.3 [X99M] Provide utility service, including low pressure air supply, water supply, and steam supply.

FOUO

SHIP: DDG-76 CHG/VER: 0/0

5.11.4 [C106.1] Provide safety inspection for SRF-JRMC employees.

5.11.5 [C106.2] Provide gas free inspection for SRF-JRMC employees.

5.11.6 [C133] Provide QA inspection for (G) symbol(s).

5.11.7 [C250] Provide on-site engineering support for front loading.

5.11.8 [C285] Provide inspection for (G) symbol(s).

FOUO

J-1

SHIP: DDG-76 CHG/VER: 0/0

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

AFT INTAKE AY A 0 0

CU PHASE TITLE:

F/O – INSPECT, REPAIR, AND PRESERVE IN NO. 2 GTM AND SSGTG NO. 2 INTAKE

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

#2B GTM INTAKE IT #2A GTM INTAKE IT CMPT 01-260-1-Q MS CMPT 02-284-0-Q

MS CMPT 02-275-0-Q MS CMPT 03-274-0-Q MS #2 SSGTG INTAKE IT

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

FUJINO ,YUUKI

JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:

38KB312389 A02

TOTAL MAT’L COST TOTAL DURATION:

CU PHASE DESCRIPTION:

The purpose of this TGI is to inspect, repair, and preserve in engine room No. 2 gas turbine module (GTM) and ship service gas turbine generator (SSGTG) No. 2 dirty side intake

Location of Work:

Intake Engine Room No. 2, Port (Dirty Side) (02-284-0-Q) Intake Engine Room No. 2, Starboard (Stbd) (Dirty Side) (02-284-0-Q) Intake Engine Room No. 2, Port (Dirty Side) (02-275-0-Q) Intake Engine Room No. 2, Stbd (Dirty Side) (02-275-0-Q) Intake Engine Room No. 2, Port (Dirty Side) (03-274-0-Q) Intake Engine Room No. 2, Stbd (Dirty Side) (03-274-0-Q) Ship Service Gas Turbine Generator (SSGTG) Intake (Dirty Side) (01-260-1-Q) Intake Trunk (A) Engine Room No. 2 (1-289-2-Q) Intake Engine Room No. 2, Port and Stbd (Clean Side) (02-284-0-Q) Intake Engine Room No. 2 (01-276-0-Q) Intake Engine Room No. 2, Port and Stbd (Clean Side) (02-275-0-Q) Intake Engine Room No. 2, Port and Stbd (03-274-0-Q) SSGTG Intake (Clean Side) (01-260-1-Q) SSGTG Intake Trunk (1-260-1-Q)

FOUO

J-2

SHIP: DDG-76 CHG/VER: 0/0

FOUO

M-1

SHIP: DDG-76 CHG/VER: 0/0

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

AFT INTAKE AY A 0 0

CU PHASE TITLE:

F/O – INSPECT, REPAIR, AND PRESERVE IN NO. 2 GTM AND SSGTG NO. 2 INTAKE

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

38KB312389 A02

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-76 AFT INTAKE AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

38KB312389 A02

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-76 AFT INTAKE AY A 0

File details come from the government source that posted it. Updated .