SOW_TGI_38KB312389A03_c1v1.pdf

PDF 206 KB Posted

Attached to
USS HIGGINS (DDG 76) 6C1 BUNDLE 3
Solicitation number
N6264926RA044
Issued by

About this file

This is a Task Group Instruction (TGI) document for ship maintenance work on the USS Higgins (DDG-76), prepared by the U.S. Navy. The instruction outlines inspection, repair, and preservation work on Ship Service Gas Turbine Generator (SSGTG) No. 3 dirty side intake system located in compartment 1-378-0-Q.

The work scope includes: visual inspection of current ship condition for corrosion, damage, and deterioration across decks, bulkheads, overhead surfaces, steel channels, stiffeners, penetrations, pipe hangers, and vibration damping; power tool cleaning to bare metal up to 300 square feet using SSPC-SP 11 surface preparation standards; ultrasonic thickness measurements at up to 50 locations with acceptance criteria per MIL-STD-2035; base metal buildup totaling 30 square inches (maximum 2-inch diameter per area, one-quarter inch thick); removal and installation of 10 square feet of deck, overhead, and bulkhead; removal and installation of 5 linear feet of stiffeners; vee out and welding of 2 linear feet of cracked or damaged welds; and coating application per SSPC Painting Manual Volume 2. Contractor work commences June 29, 2026, with completion by December 8, 2026. The instruction specifies that a non-flammable closure must be fabricated and staged per COMNAVDEASYSCOM requirements due to fire zone boundary work. Supporting reference materials include NSI and LI standard items, drawing packages, nondestructive testing procedures, and hull structure specifications. SRF-JRMC will provide ancillary services including crane operations, utilities, safety inspections, gas-free inspections, QA inspection, and on-site engineering support. The material list (Appendix M) is currently blank, with materials to be provided based on contractor condition reports.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926RA0440008 SF 30.pdf PDF
Solicitation Amendment - N6264926RA0440008 Conformed.pdf PDF
Solicitation Amendment N6264926RA0440005 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440004 SF 30.pdf PDF
Att IX HIG_6C1_B3_POP_List_R4.xlsx XLSX spreadsheet
Solicitation Amendment N6264926RA0440007 SF 30.pdf PDF
Attachment II Price Proposal Form N6264926RA044 (rev1).xlsx XLSX spreadsheet
Solicitation Amendment N6264926RA0440003 SF 30.pdf PDF
SOW_TGI_38KB312389A02_c0v0.pdf PDF
Solicitation Amendment N6264926RA0440002 SF 30.pdf PDF
Solicitation Amendment N6264926RA0440001 SF 30.pdf PDF
Exhibits - Contract Data Requirements List (CDRL).pdf PDF
Attachment (IV) Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
SOW_TGI_38KB313103A01_c1v0.pdf PDF
Attachment (VI) Source of Repair Instruction.pdf PDF
Attachment (V) Warranty Tracking Information.pdf PDF
Attachment (III) Request for Information Sheet.docx DOCX document
Solicitation - N6264926RA044.pdf PDF
Attachment (VII) Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment (II) Price Proposal Form N6264926RA044.xlsx XLSX spreadsheet
Attachment (VIII) Contracts Data Sheet.pdf PDF
SOW_TGI_38KB386501A01_c0v0.pdf PDF
SOW_TGI_38KB325102A01_c0v0.pdf PDF
SOW_TGI_38KB312389A01_c1v0.pdf PDF
SOW_TGI_38KB312388A01_c0v0.pdf PDF
SOW_TGI_38KB312387A01_c0v0.pdf PDF
SOW_TGI_38KB312386A01_c0v0.pdf PDF
Pre-Solicitation Notice N6264926RA044.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: AFT INTAKE AY A 0 1

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

DDG-76 USS HIGGINS KB3

CU PHASE TITLE:

F/O – INSPECT, REPAIR, AND PRESERVE IN SSGTG NO. 3 INTAKE

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

MISAKI KANEHIRA 231A 315-243-9883 30-APR-2026

APPROVED BY: CODE PHONE DATE

YUUJI NAKMURA 231A 315-243-6041 30-APR-2026

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

Need to revise task name.

CHANGE INSTRUCTIONS:

CH-1: Revised task name. (05/06/2026)

SPECIAL REQUIREMENTS:

SURFMEPP

This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: AFT INTAKE AY A 0

FOUO

SHIP: DDG-76 CHG/VER: 1/1

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-5 J1-2 M-1

1. SCOPE/PURPOSE

1.1 Title: Ship Service Gas Turbine Generator (SSGTG) No. 3 Dirty Side Intake; inspect, repair, and preserve

1.2 Location of Work:

1.2.1 SSGTG Intake Trunk (Dirty Side) (1-378-0-Q)

1.2.2 SSGTG Intake Trunk (Clean Side) (1-378-0-Q)

1.3 Identification:

1.3.1 Quantity (One EA), Dirty Side of SSGTG No. 3 Intake in 1-378-0-Q

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date: 29/JUN/2026

1.7 Contractor work completion date: 8/DEC/2026

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 MP LM23-

KB312389-

EM02ZBY2

2A /2B GTM & NR.2/NR.3 SSGTG

INTK SYS FOD PRTN FOR INTK

DIRTY SIDE PARTIALLY RPR

- Y AL

L

4 DWG 100-

6218944

UNIT STRUCTURAL ARR DWG

ASSY UNIT 3350

W Y SE

E N

OT

E

5 DWG 100-

6218943

UNIT STRL ARR DWG ASSY UNIT

AB Y 3-

6 TM

SYSTEMS &

SPECIFICAT

IONS

SSPC Painting Manual Volume 2 - N

7 TM T9074-

AS-GIB-

010/271

Requirements for Nondestructive Testing Methods

1 N

8 TM S9086-

DA-STM-

010/CH-100

Hull Structures 4 N

FOUO

SHIP: DDG-76 CHG/VER: 1/1

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

9 MIL MIL-

STD-2035

Nondestructive Testing Acceptable Criteria

A N

3. APPENDICES:

3.1. Appendix “J” TGI Job Summary Information Sheet

3.2. Appendix "M" TGI Material List

3.3. Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Accomplish the requirements of 2.3.

(V)(G) "GAS TURBINE MAINTENANCE PROCEDURE"

5.2 Accomplish a visual inspection of the current ship condition, listed in 1.3.1 and located in 1.2.1, using 2.4 and 2.5 for guidance.

5.2.1 Ensure to inspect each deck, bulkhead, overhead surface, steel channel, stiffener, penetration, pipe hanger and vibration damping.

5.2.2 Mark each corroded, damaged and/or deteriorated area.

5.2.3 Submit one legible copy, in hard copy or approved transferable media, of a report with a sketch listing results of the requirements of 5.2 to the SUPERVISOR.

5.3 Power tool clean to bare metal each location reported in 5.2.3, located in 1.2.1, to include each exposed longitudinal, vertical, and traverse stiffener, for up to 300 square feet. Accomplish each requirement of Surface Preparation Specification SSPC-SP 11 of 2.6, as designated by the SUPERVISOR.

5.4 Accomplish a visual inspection of each surface power tool cleaned to bare metal in 5.3, listed in 1.3.1, located in

1.2.1 for structural integrity, deterioration, pitting, each crack, and area of damage or distortion, using 2.4 and 2.5 for guidance.

5.4.1 Mark each corroded, damaged and/or deteriorated area.

5.4.2 Submit one legible copy, in hard copy or approved transferable media, of a report with a sketch listing results of the requirements of 5.4 to the SUPERVISOR.

5.5 Accomplish each ultrasonic thickness measurement (UTM) up to 50 locations in each location reported in 5.4.2, listed in 1.3.1, located in 1.2.1 in accordance with Paragraph 6.7 of 2.7 and 2.8, as designated by the SUPERVISOR, using 2.4 and 2.5 for guidance. The acceptance criteria must be in accordance with 2.9.

5.5.1 Submit one legible copy, in hard copy or approved transferable media, of a report listing results of the requirements of 5.5 to the SUPERVISOR.

FOUO

SHIP: DDG-76 CHG/VER: 1/1

5.5.2 Ensure a sketch showing each location of each UTM reading, original material thickness, existing material thickness, and percentage of material thickness reduction.

5.6 Accomplish the following repairs reported in 5.2.3, 5.4.2 and 5.5.1, listed in 1.3.1, located in 1.2.1 as designated by the SUPERVISOR, using 2.4 and 2.5 for guidance. See 5.9.5 and 5.9.6.

5.6.1 Base metal buildup, a total of 30 square inches.

5.6.1.1 Ensure each base metal buildup area does not exceed 2 inches in diameter.

5.6.1.2 Estimate the base metal buildup to be one quarter inch thick for pricing purposes.

5.6.1.3 Fill each local pit and groove with metal prior to the application of each principal build-up layer.

5.6.1.4 Each surface must be ground smooth to metal.

5.6.2 Remove existing and install new, a total of 10 square feet of deck, overhead, and bulkhead.

5.6.3 Remove existing and install new, a total of 5 linear feet of longitudinal, vertical, and transverse stiffener.

5.6.4 Vee out and weld a total of 2 linear feet of cracked, split, broken or damaged intake weld.

5.6.5 Chip and grind each surface flush in way of each repair.

5.6.6 Template exact size, configuration, and location from each existing shipboard condition.

5.6.7 Accomplish the requirements of 009-012 of 2.1, including Table 2, Columns A and D, Lines One through 7.

5.6.8 Accomplish the requirements of 009-025 of 2.1 for an air hose test of each new weld seam. Allowable leakage:

None.

5.7 Accomplish the requirements of 009-032 of 2.1, including Table 3, Line(s) 20, located in 1.2.1, for coating removed in 5.3.

5.7.1 Power tool clean to bare metal for each area. Accomplish each requirement of Surface Preparation Specification SSPC-SP 11 of 2.6.

5.8 Accomplish the requirements of 009-032 of 2.1 for new and disturbed surface.

5.9 Notes:

5.9.1 Planner: Code 231A M. Kanehira, 243-9883

Planner: Code 231A R. Nanba, 243-6141

5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560.

5.9.3 This TGI meets the intent of DDG CSWT File No. 251-044.

5.9.4 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkhead normally used to control air flow in the event of a shipboard fire. A non- flammable closure is required in accordance with COMNAVDEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

FOUO

SHIP: DDG-76 CHG/VER: 1/1

5.9.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.

5.9.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.

5.9.7 WPC will copy the following pages in reference.

REF. 2.4: Sheets 7-1, 3-11, 3A-11, 3B-11, 4-11, 5-11, and 6-11.

5.9.8 JCNs EM02-ZBY2, EM02-ZBY3, EM02-ZBY4, EM02-ZBY5, and EM04-ZAL8 are related to this TGI.

5.10 Government Furnished Material (GFM): None

5.11 SRF-JRMC will provide the following service work: (TGI No. 38KB312389S02)

5.11.1 [C740] Provide crane and crane rigging service.

5.11.2 [X99E] Provide utility service, electrical.

5.11.3 [X99M] Provide utility service, including low pressure air supply, water supply, and steam supply.

5.11.4 [C106.1] Provide safety inspection for SRF-JRMC employees.

5.11.5 [C106.2] Provide gas free inspection for SRF-JRMC employees.

5.11.6 [C133] Provide QA inspection for (G) symbol(s).

5.11.7 [C250] Provide on-site engineering support for front loading.

5.11.8 [C285] Provide inspection for (G) symbol(s).

FOUO

J-1

SHIP: DDG-76 CHG/VER: 1/1

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

AFT INTAKE AY A 0 1

CU PHASE TITLE:

F/O – INSPECT, REPAIR, AND PRESERVE IN SSGTG NO. 3 INTAKE

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

CMPT 1-378-0-Q MS #3 SSGTG INTAKE IT

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

FUJINO ,YUUKI

JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:

38KB312389 A03

TOTAL MAT’L COST TOTAL DURATION:

CU PHASE DESCRIPTION:

The purpose of this TGI is to inspect, repair, and preserve in ship service gas turbine generator (SSGTG) No. 3 dirty side intake

Location of Work:

SSGTG Intake Trunk (Dirty Side) (1-378-0-Q) SSGTG Intake Trunk (Clean Side) (1-378-0-Q)

FOUO

J-2

SHIP: DDG-76 CHG/VER: 1/1

FOUO

M-1

SHIP: DDG-76 CHG/VER: 1/1

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

AFT INTAKE AY A 0 1

CU PHASE TITLE:

F/O – INSPECT, REPAIR, AND PRESERVE IN SSGTG NO. 3 INTAKE

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

38KB312389 A03

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-76 AFT INTAKE AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

38KB312389 A03

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-76 AFT INTAKE AY A 0