This is a solicitation for an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) to provide new construction, repair, and renovation of airfield paving and heavy duty paving projects at various government installations located within the Naval Facilities Engineering Command (NAVFAC) area of operations. The solicitation seeks qualified contractors to compete for both small and large-scale task orders for a base period of one year with four one-year option periods. Task orders will be fixed price or cost reimbursement and will have individual minimum and maximum values between $100,000 and $5,000,000. The NAICS code is 237990 and the contract has a small business set-aside. Proposals are due within 60 days and awards will be made within 180 days after proposal receipt.

View the file

Other files

File Type Posted
Revised SF 1442 _ 3.25.2024.pdf PDF
Amendment 0008_3.25.2024.pdf PDF
Amendment 0007_11.15.2023.pdf PDF
RFI Log_Airfield Paving MACC 11.15.2023.xlsx XLSX spreadsheet
RFI Log_Airfield Paving MACC 11.14.2023.xlsx XLSX spreadsheet
Amendment 0006_ 11.9.23.pdf PDF
Specification 02 41 00 Demolition_Amendment 0006.pdf PDF
Specification 32 13 14.13 Concrete Paving for Airfields and Other Heavy Duty Pavements_Amendment 0006.pdf PDF
Specification 31 00 00 Earthwork_Amendment 0006.pdf PDF
Exhibit F_SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT (SBPCD)_Amendment 0006.docx DOCX document
Planset Amendment 0006.pdf PDF
RFI Log_Airfield Paving MACC 11.8.2023.xlsx XLSX spreadsheet
RFI Log_Airfield Paving MACC 11.7.2023.xlsx XLSX spreadsheet
Exhibit A_ OFFEROR TEAM COMPOSITION AND MANAGEMENT rev 1 _Amendment 0005.docx DOCX document
RFI Log_Airfield Paving MACC 11.2.23.xlsx XLSX spreadsheet
Specification 01 45 00.00 20_Quality Control_ Amendment 0005.pdf PDF
Amendment 0005 _ 11.2.23.pdf PDF
Planset_Amendment 0005.pdf PDF
RFI Log_Airfield Paving MACC 10.30.23.xlsx XLSX spreadsheet
Amendment 0004 _ 10.25.2023.pdf PDF
RFI Log_Airfield Paving MACC 10.16.23.xlsx XLSX spreadsheet
RFI Log_Airfield Paving MACC 10.4.23.xlsx XLSX spreadsheet
Amendment 0003 _ 10.4.2023.pdf PDF
MACC Frequently Asked Questions_ Amendment 0002.pdf PDF
Amendment 0002_9.27.2023.pdf PDF
Offerors Team Consent Form_ Amendment 0002.doc DOC document
Solicitation_N6247323R0408_Airfield Paving MACC._Amendment 0002.pdf PDF
RFI Log_Airfield Paving MACC 9.26.23.xlsx XLSX spreadsheet
Wage Determination 9.15.2023 Amendment 0001.pdf PDF
Repair Flightline Apron Planset 06.12.23.pdf PDF
RFP Part 1_ AIRFIELD MACC AIRFIELD.pdf PDF
Amendment 0001 _ 9.19.2023.pdf PDF
Section 00 45 00 - Representations and Certifications.docx DOCX document
RFI Log_Airfield Paving MACC 9.12.23.xlsx XLSX spreadsheet
Exhibit D_ SAFETY DATA SHEET.docx DOCX document
Surety Form_Airfield Paving MACC.doc DOC document
Exhibit A_ OFFEROR TEAM COMPOSITION AND MANAGEMENT.docx DOCX document
Exhibit F_SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT (SBPCD).docx DOCX document
Exhibit C_Past Performance Questionnaire.docx DOCX document
Exhibit E _HISTORICAL SMALL BUSINESS UTILIZATION.docx DOCX document
Instructions for Viewing Interested Vendors List.pdf PDF
Solicitation_N6247323R0408_Airfield Paving MACC_20230912.pdf PDF
Financial Questionnaire_Airfield Paving MACC.doc DOC document
Exhibit B_ CONSTRUCTION EXPERIENCE DATA SHEET _OFFEROR.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Final Submittal Specifications

Repair Flightline Apron Naval Air Station Point Mugu Naval Base Ventura County

Ventura, California

June 12th, 2023

Submitted by:

NAVFAC SW In-House Design Design and Construction Core

Airfield and Geotechnical Group

PROJECT TABLE OF CONTENTS

DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS

00 01 15 LIST OF DRAWINGS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00 SUBMITTAL PROCEDURES

01 35 13 SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 20 QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 50 10 FOREIGN OBJECT DEBRIS (FOD) CONTROL & MANAGEMENT -

AIRFIELDS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

DI VI SI ON 31 - EARTHWORK

31 23 00.00 20 EXCAVATION AND FILL

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT

32 11 23 AGGREGATE BASE COURSE FOR FLEXIBLE PAVING

32 11 33 CEMENT STABILIZED BASE COURSE AT AIRFIELDS AND ROADS

32 12 15.13 ASPHALT PAVING FOR AIRFIELDS

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 13 73.19 COMPRESSION CONCRETE PAVING JOINT SEALANT

32 17 23 PAVEMENT MARKINGS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as indicated on the "Drawing Index/List". Refer to list for all sheet numbers, sheet titles, and NAVFAC numbers in this construction contract.

-- End of Document --

DOCUMENT 00 01 15 Page 2

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 CONTRACT DRAWINGS

1.4 EXISTING WORK

1.5 INSPECTION AND ACCEPTANCE OF NEW CONNECTIONS TO EXISTING

NAVY-OWNED UTILITIES AND NEW UTILITY EQUIPMENT

1.6 ON-SITE PERMITS

1.6.1 Borrow, Excavation, Welding, and Burning Permits

1.6.2 Air Quality Permit

1.6.3 California Air Resources Board Requirements

1.7 LOCATION OF UNDERGROUND UTILITIES

1.7.1 Coordination

1.7.2 Utility Location Coordination Report

1.7.3 Emergency Utility Repair Plan

1.7.4 Notification Prior to Excavation

1.8 SALVAGE MATERIAL AND EQUIPMENT

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Borrow Permits

Excavation Permits

Welding Permits

Air Quality Permit

California Air Resources Board Requirements ; G

Utility Location Coordination Report ; G

Emergency Utility Repair Plan ; G

Utility Service Connection application; including a construction plan for the utility service connection ; G

Salvage Plan ; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes Replace deteriorated airfield apron pavement to serviceable condition for air operations. The airfield pavement work primarily consists of Portland cement concrete (PCC) reconstruction. Minor AC replacement will also occur. Existing utility lines and structures shall be protected in place. Work shall include earthwork, demolition and all other incidental related activities.

1.2.2 Location

The work is located at the Naval Base Ventura, California , approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 CONTRACT DRAWINGS

Refer to Section 00 01 15 LIST OF DRAWINGS for drawings accompany this specification and are a part thereof.

Reference publications will not be furnished. Immediately check drawings

SECTION 01 11 00 Page 2 and notify the Government of any discrepancies.

1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 INSPECTION AND ACCEPTANCE OF NEW CONNECTIONS TO EXISTING NAVY-OWNED

UTILITIES AND NEW UTILITY EQUIPMENT

Prior to any construction of a utility connection, a Utility Service Connection application; including a construction plan for the utility service connection shall be submitted to and approved by PW Utilities Plan Reviewer. Each application shall include the relevant construction plans and specifications, following the standards of the applicable utility provider and regulatory agency that governs the utility where the project is located.

(1) For all new/repaired utility connections, FEAD or other utilities connection installer shall schedule a pre-outage coordination meeting. During this meeting the FEAD will coordinate a pre-connection inspection to be conducted after trenching and layout is completed, but before the proposed service has been connected, and a post-connection inspection conducted after the connection has been made and before the connection is buried. The pre- and post-connection inspections will typically be on the same or consecutive days and shall be scheduled with the PW Utilities Inspector 14 days prior to the proposed date of the work.

The PW Utilities Inspector shall be present during the inspections. The PW Utilities Inspector will verify that all new connections to utility systems are made properly based on applicable standards.

FEAD representative will ensure test results are noted in the daily CQC report.

(2) If deficiencies are found in the pre-connection inspection, the PW Utilities inspector will provide a list of deficiencies to the FEAD representative. The FEAD representative will determine if the requirements are within the contract. Items considered to be within the contract requirement will be given to the contractor for correction and documented in the contract files. Resolution of items considered outside of the contract by the FEAD but deemed required by PW Utilities shall be resolved prior to cutting in the connection. (This situation should be avoided by having prior approved PW Utilities connection applications/construction plans.)

(3) The PW Utilities Inspector shall be notified when all deficiencies have been completed to reschedule the pre-connection inspection. The repeated inspection will only cover items noted in the previous inspection.

SECTION 01 11 00 Page 3

(4) After post connection inspection is completed, the PW Utilities Inspector will authorize the system or equipment to be energized and/or placed into service.

(5) The Contractor shall provide as-built utility drawings, preferably in standard electronic format to FEAD showing the location of all utility lines, mains, laterals, and other appurtenances reference to a known location or in GPS Coordinates. The type, class, size of all piping and valves shall be indicated on the as-builts. For new sewers, as-built invert elevations shall be provided starting from the building going to the first pre-existing downstream manhole. The FEAD shall provide these to PW Utilities as soon as possible. The FEAD shall follow the requirements of BMS 1.6.11 NAVFAC RED ZONE to provide to PW Utilities utility record drawings.

(6) Any change(s) to storm water systems shall be coordinated with installation environmental staff, including providing as-built drawings to update storm water system networks for compliance with National Pollutant Discharge Elimination System (NPDES) permits.

(7) These guidelines are not a substitute for professional judgment as to when additional safe guards are needed to prevent improper connections to existing utility systems.

1.6 ON-SITE PERMITS

1.6.1 Borrow, Excavation, Welding, and Burning Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Borrow Permits 15 calendar days prior to work yes

Excavation Permits 30 calendar days prior to work yes

Welding Permits 15 calendar days prior to work yes

Post permits at a conspicuous location in the construction area.

Burning of trash or rubbish is not permitted on the Base .

1.6.2 Air Quality Permit

Contractor shall obtain an air quality permit for dust control and for off-road equipment vehicles. Coordinate and obtain permit with the base environmental department before any such work shall start.

1.6.3 California Air Resources Board Requirements

California Air Resources Board requires construction fleet owners to report and label their off-road construction vehicles for emissions control. Comply with these requirements. Provide documentation from the California Air Resources Board that the requirements have been complied with.

SECTION 01 11 00 Page 4

1.7 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.7.1 Coordination

After contract award and prior to commencement of any clearing and grubbing, trenching, boring, earthwork, or other operation that may damage underground utilities, the Contractor shall provide his own utility locator services. The Contractor shall review all available As-built Base Facility Drawings(s) for the area under construction. The Contractor shall coordinate the utility locating service with other applicable activities and agencies.

1.7.2 Utility Location Coordination Report

When utility location is furnished, the Contractor shall submit a report outlining the activities and agencies contacted. The DIG ALERT inquiry identification shall be provided in the report. No activity that could damage the underground utilities may begin until the Contracting Officer approves the coordination report.

1.7.3 Emergency Utility Repair Plan

The contractors shall be required to submit an Emergency Utility Repair Plan prior to being allowed to perform any excavation. Emergency shall be defined as the interruption of any and/or damage of any utility service.

Including but not limited to the spill, or potential spill of any fuel oil, gas, potable water, sewage effluent, raw sewage, or storm water outside of system facilities.

The Emergency Utility Repair Plan shall include the following elements:

a. Equipment list of available pumps with sizes, excavation equipment, tools, and repair materials that are available onsite.

b. Labor force that will be available as a minimum to respond to emergencies.

c. Site-specific plan for locating, potholing, protecting, avoiding, and repairing any damage caused to existing, or newly installed utilities.

SECTION 01 11 00 Page 5

d. Include the same level of detail for any subcontractors that will be performing work involving excavation.

e. Include a description of any planned effort that would involve bringing in a subcontractor personnel to respond to emergencies.

f. The Plan shall be subject to approval by the Contracting Officer.

The Contractor shall demonstrate in his Emergency Utility Repair Plan that they are capable of responding to utility interruptions that could be caused by their construction operations or impacts from them. Immediately upon discovery of the situation, the Contractor shall react in a way that will minimize utility interruptions, releases, spills, impacts to utility customers, and potential for fines or notices of violations. In no case will repairs be left to be resolved the next day without the approval of the Contracting Officer.

The Contractor's Emergency Utility Repair Plan shall address the above items for each utility potentially impacted by construction, crossed by excavation, or known to be in the area but possessing properties that cause difficulties in identification of the exact location.

In the event that a utility is broken, all repairs will be the responsibility of the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.7.4 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.8 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 4 miles of the construction site.

Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 6

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SPECIAL SCHEDULING REQUIREMENTS

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

1.4.1.1 Identification Badges and Installation Access

1.4.1.2 No Smoking Policy

1.4.2 Working Hours

1.4.3 Work Outside Regular Hours

1.4.4 Exclusionary Period

1.4.5 Utility Cutovers and Interruptions

1.5 EXISTING AIRFIELD LIGHTING SYSTEMS

1.6 SECURITY REQUIREMENTS

1.6.1 Employment Restrictions For NAVFAC SW

1.6.1.1 Personnel List

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. Code (USC)

8 USC 1101 Definitions

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Personnel List ; G

Demolition Schedule ; G:

Construction/Demolition/Sequencing/Schedule And Plan

Construction/Demolition/Phasing/Schedule and Plan to be submitted for review and approved by the Contracting Office before any demolition or construction to begin. Submit schedule and plan 21 days before any work takes place. Also conform with Section

02 41 00 DEMOLITION.

1.3 SPECIAL SCHEDULING REQUIREMENTS

e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the CONSTR/DEMO/SEQ/SCHEDULE AND PLAN each factor which constitutes a potential interruption to operations.

Conform with Section 02 41 00 DEMOLITION.

Each work phase shall be ready for operation as approved by Contracting Officer before work is started on the next work phase which would interfere with normal operation. The following conditions apply:

(1) Refer to the Drawings for special scheduling and sequencing items required to complete construction of proposed demolition and new work.

(2) The airfield will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal

SECTION 01 14 00 Page 2 operations of the activity.

(3) Permission to interrupt any Activity roads and/or utility service shall be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.

(4) Attend weekly airfield construction project coordination meetings.

(5) Exclusionary Periods: No work shall be performed during Basewide annual security exercises for up to 5 days twice a year for each year (10 days total), inclusive, without prior written approval of the Contracting Officer. Such delays shall be incorporated into the Contractor's construction schedule and will be at no additional cost or time to the Government. 1.4 CONTRACTOR ACCESS

AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

Flightline Access:

The performance of work in the controlled zones of airfields shall be coordinated with the Contracting Officer and with the Flight Operations Officer. Verbal communications shall be maintained with the control tower before and during work in the controlled zones of the airfield. The control tower shall be advised when the work is completed. A radio for this purpose will be provided by the Government. The Contractor shall assume responsibility for the radio and shall reimburse the Government for repair or replacement of the radio if it is lost, damaged, or destroyed.

Conform with SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS.

1.4.1.1 Identification Badges and Installation Access

Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS), or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge.

Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.

a. NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.

SECTION 01 14 00 Page 3

The Government performs background screening and credentialing.

Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON). Information on costs and requirements to participate and enroll in NCACS is available at http://www.rapidgate.com or by calling 1-877-727-4342. Contractors should be aware that the costs incurred to obtain NCACS credentials, or costs related to any means of access to a Navy Installation, are not reimbursable. Any time invested, or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.

b. One-Day Passes: Participation in the NCACS is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation.

The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.

1.4.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours must consist of an 10 hour period established by the Contractor Officer, between 7 a.m. and 5:30 p.m., Monday through Friday, excluding Government holidays.

1.4.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.4.4 Exclusionary Period

No work shall be performed during Basewide annual security exercises for up to 5 days twice a year for each year (10 days total), inclusive, without prior written approval of the Contracting Officer. Such delays shall be incorporated into the Contractor's construction schedule and will be at no additional cost or time to the Government.

SECTION 01 14 00 Page 4

1.4.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, fire alarm, compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruptions are further limited to 4 hours. This time limit includes time for deactivation and reactivation.

1.5 EXISTING AIRFIELD LIGHTING SYSTEMS

Runway airfield lighting system shall remain in operating condition, and interruptions shall be avoided during the construction period. Where interruptions are necessary, they shall be scheduled as approved in writing by the Contracting Officer. Prior to the scheduled time for each interruption, all necessary materials and a sufficient labor force shall be assembled to permit completing the work within the scheduled time interval. Under no circumstances shall any of the existing airfield lighting circuits be left inoperative without making provisions for suitable temporary connections in the affected area or areas. Runway airfield lighting circuits covered under this Contract shall be replaced in such a manner that they will be operational at dusk each day. The Contractor shall submit to the Contracting Officer a plan for outages and maintaining lighting and lighting control. NB Ventura requires 30 day notice prior to each outage.

1.6 SECURITY REQUIREMENTS

Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," and the following apply:

1.6.1 Employment Restrictions For NAVFAC SW

The Contractor must not employ any person, for any work required by this contract, who: (1)is a non-immigrant as described in section 101(a)(15)(H)(ii) of the Immigration and Nationality Act 8 USC 1101 (a)(15)(H)(ii), (2)is an alien having a residence in a foreign country which he has no intention of abandoning and who is coming to the United States to perform temporary services or labor.

1.6.1.1 Personnel List

Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:

a. Name

b. Date and place of birth

SECTION 01 14 00 Page 5

c. Citizenship

d. Home address

e. Social security number

f. Current pass expiration date

g. Naturalization or Alien Registration number

The request for personnel passes must be accompanied with the following certification:

"I hereby certify that all personnel on this list are either born U.S.

citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."

Signature/Firm Name

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 6

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/ 20, CHG 2: 08/ 21

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SCHEDULE OF PRICES

1.3.1 Data Required

1.3.2 Payment Schedule Instructions

1.4 CONTRACT MODIFICATIONS

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

1.5.2 Submission of Invoices

1.5.3 Final Invoice

1.6 PAYMENTS TO THE CONTRACTOR

1.6.1 Obligation of Government Payments

1.6.2 Payment for Onsite and Offsite Materials

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 20 00 Page 1

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/ 20, CHG 2: 08/ 21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices ; G

1.3 SCHEDULE OF PRICES

1.3.1 Data Required

Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction Contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.

1.3.2 Payment Schedule Instructions

Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer.

For Fast-Tracked or Critical Path Submittals of construction projects, the Schedule of Prices must include detailed design and construction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.

Additionally, the Schedule of Prices must be separated as follows: Primary

Facilities Cost Breakdown: All work associated with repairs of airfield pavement within the project footprint shall be considered as being

SECTION 01 20 00 Page 2 associated with Primary Facilities.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the

EP 1110-1-8 .

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.

a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.

b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 4330/54 furnished by the Government. Use NAVFAC Form 4330, unless otherwise directed by the Contracting Officer, on NAVFAC Contracts when a Monthly Estimate for Voucher is required.

c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.

d. Monthly Work-hour report.

e. Updated Construction Progress Schedule and tabular reports required by the contract.

f. Contractor Safety Self Evaluation Checklist.

g. Updated submittal register.

h. Solid Waste Disposal Report.

i. Certified payrolls.

j. Updated testing logs.

k. Other supporting documents as requested.

1.5.2 Submission of Invoices

If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph

SECTION 01 20 00 Page 3

CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.

Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

1.5.3 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR FAR

32.103 Progress Payments Under Construction Contracts:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

SECTION 01 20 00 Page 4

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Pricesrequirement of this Contract.

Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.

g. Materials in transit to the job site or storage site are not acceptable for payment.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 5

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/ 20, CHG 1: 08/ 21

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 VIEW LOCATION MAP

1.4 PROGRESS AND COMPLETION PICTURES

1.5 MINIMUM INSURANCE REQUIREMENTS

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

1.6.2 Minimum Communication Requirements

1.6.3 Duties

1.6.4 Non-Compliance Actions

1.7 PRECONSTRUCTION MEETING

1.7.1 Attendees

1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

1.8.1 Red Zone Checklist

1.8.2 Meetings

1.9 PARTNERING

1.9.1 Team-Led (Informal) Partnering

1.10 MOBILIZATION

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/ 20, CHG 1: 08/ 21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 10 digital photographs each week throughout the entire project from a minimum of 5 different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date.

Indicate photographs demonstrating environmental procedures where applicable . Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

SECTION 01 30 00 Page 2

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by law.

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.6.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.6.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRECONSTRUCTION MEETING

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including

SECTION 01 30 00 Page 3 but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.8.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.8.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

SECTION 01 30 00 Page 4

1.9 PARTNERING

To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.9.1 Team-Led (Informal) Partnering

a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.

b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.

c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.

d. The Partners will determine the frequency of the follow-on sessions.

e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

1.10 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days after contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 5

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 31 23.13 20

ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM

05/ 17, CHG 8: 02/ 23

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

1.1.1 Format Naming Convention for Files Uploaded Into eCMS

1.1.2 Uploading Documents Processed Outside of eCMS

1.2 USER PRIVILEGES

1.3 SUBMITTALS

1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY

1.4.1 General

1.4.2 Contractor Personnel List

1.5 SECURITY CLASSIFICATION

1.6 ECMS UTILIZATION

1.6.1 Information Security Classification/Identification

1.6.2 Markings on CUI documents

1.7 QUALITY ASSURANCE

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 31 23.13 20 Page 1

SECTION 01 31 23.13 20

ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM

05/ 17, CHG 8: 02/ 23

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional, or specifically requested in addition to electronic submission.

1.1.1 Format Naming Convention for Files Uploaded Into eCMS

Include the identification number of the document, the type of document, the name/subject or title, and for daily reports, the date (day of work) with format YYYY/MM/DD in the filename. For example, for RFI's, 0011_RFI_Roof_Leaking.doc; for submittals, 0032a_Submittals_Light_Fixture.pdf; for Daily Reports, 0132_Daily_Report_20190504.xls. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.

1.1.2 Uploading Documents Processed Outside of eCMS

When specifically requested to provide documents outside of eCMS, upload all final project documentation (e.g., documents that are signed and/or adjudicated by the Government) mentioned in Table 1 into eCMS by creating a record in the module associated with that document type and uploading the document(s). Subject/title of the record should include the type of record i.e., RFI/Submittal/Other, the identification number(s), and the statement "Processed Outside of eCMS". For example, "RFI 001-012 Processed Outside of eCMS".

1.2 USER PRIVILEGES

The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval.