N62470-20-R-4007 Amendment 8.pdf

PDF 459 KB Posted

Attached to
P-759, FAMILY HOUSING NEW CONSTRUCTION VILLAGGIO SW & CAMP EDERLE NORTH - VICENZA, ITALY
Solicitation number
N62470-20-R-4007
Issued by

About this file

This document is an amendment to a solicitation for family housing new construction at Villaggio Southwest and Camp Ederle North in Vicenza, Italy. The amendment provides responses to pre-proposal inquiries, revises the solicitation text to clarify that an offer guarantee is not required, and replaces the Schedule B price proposal form attachment with a revised version dated December 8, 2020. The proposal due date remains December 30, 2020 at 14:30 Eastern Time. The Naval Facilities Engineering Command is seeking to award a firm-fixed-price contract for construction of 79 housing units. Offerors should prepare their proposals in accordance with the solicitation revisions provided in this amendment.

View the file

Other files

File Type Posted
Attachment O - ENG-UXO Report Annex1.pdf PDF
Attachment N - Health and Safety Plan.pdf PDF
Attachment P - Demo Bldg As-Built.pdf PDF
N62470-20-R-4007 Amendment 11.pdf PDF
N62470-20-R-4007 Amendment 10.pdf PDF
N62470-20-R-4007 Amendment 9.pdf PDF
Attachment E - Revised Schedule B Price Proposal Form Dated 8 Dec 2020.pdf PDF
(M) 1595974_Amend0007_spc.pdf PDF
(L) 1595974Amend0007dwg.pdf PDF
N62470-20-R-4007 Amendment 7.pdf PDF
N62470-20-R-4007 Amendment 6.pdf PDF
N62470-20-R-4007 Amendment 5.pdf PDF
(J) Pre-Proposal Conference Presentation.pdf PDF
N62470-20-R-4007 Amendment 4.pdf PDF
(K) Pre-Proposal Conference Attendee Log.pdf PDF
N6247020R4007 Amendment 0003.pdf PDF
N62470-20-R-4007 Amendment 2.pdf PDF
ATTACHMENT I P759 PREPOSALCONFACCESSREQUESTFORM.docx DOCX document
N62470-20-R-4007 Amendment 1.pdf PDF
Attachment H - 1595974dwg27of43.pdf PDF
Attachment C - Construction Experience Project Data Sheet.pdf PDF
N62470-20-R-4007 Solicitation.pdf PDF
Attachment H - 1595974dwg11of43.pdf PDF
Attachment H - 1595974dwg38of43.pdf PDF
AFH JnA.pdf PDF
Attachment H - 1595974dwg21of43.pdf PDF
Attachment H - 1595974dwg5of43.pdf PDF
Attachment H - 1595974dwg16of43.pdf PDF
Attachment H - 1595974dwg28of43.pdf PDF
Attachment H - 1595974dwg33of43.pdf PDF
Attachment H - 1595974dwg15of43.pdf PDF
Attachment B - SEC-NAV_5512_1_11787 Form.pdf PDF
Attachment F - LRA Commercial Vehicle Inspection Procedures.pdf PDF
Attachment H - 1595974dwg43of43.pdf PDF
Attachment H - 1595974dwg9of43.pdf PDF
Attachment H - 1595974dwg4of43.pdf PDF
Attachment H - 1595974dwg12of43.pdf PDF
Attachment H - 1595974dwg10of43.pdf PDF
Attachment H - 1595974dwg13of43.pdf PDF
Attachment H - 1595974dwg18of43.pdf PDF
Attachment D - Past Performance Questionnaire (PPQ).pdf PDF
Attachment H - 1595974dwg3of43.pdf PDF
Attachment H - 1595974dwg39of43.pdf PDF
Attachment H - 1595974dwg22of43.pdf PDF
Attachment H - 1595974dwg24of43.pdf PDF
Attachment H - 1595974dwg29of43.pdf PDF
Attachment H - 1595974dwg30of43.pdf PDF
Attachment A - Pre-Proposal Inquiry Form.xls XLS spreadsheet
Attachment H - 1595974dwg34of43.pdf PDF
Attachment H - 1595974dwg40of43.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

P-759 FAMILY HOUSING NEW CONSTRUCTION VILLAGGIO SW & CAMP EDERLE NORTH - VICENCA, ITALY (Phase 1)

The proposal due date is unchanged and remains Wednesday, December 30, 2020, at 1430 (EST).

PLEASE SEE SF-30 BLOCK 14 CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6247020R4007

X 9B. DATED (SEE ITEM 11)

26-Oct-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0008

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Dec-2020

CODE

COMMANDER NAVFAC ATLANTIC

6506 HAMPTON BLVD

NORFOLK VA 23508-1278

N62470 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6247020R4007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 8

SF-30 CONTINUATION PAGE:

The purpose of this amendment is for the following items:

1. Responses to Pre-Proposal Inquiries (PPI’s)

2. Solicitation Revisions

3. Revised Attachment E – Schedule B Price Proposal Form Dated 8 Dec 2020

4. Separate Attachment List

1. Responses to Pre-Proposal Inquiries (PPI’s)

Question

No.

REFERENCE QUESTION

GOVERNMENT

RESPONSE

Page Section Para

57 1 ;44 item 13 (pag 1) clause

55.228.14 (pag. 44)

For the offer submission, please confirm that a Bid Bond is not required and that a signed Bank

Reference, demonstrating adequate financial resources, shall comply with Client's requirements.

SEE AMENDMENT

BELOW

An offer guarantee is NOT required

Please clarify the amount of the Offer Guarantee and please confirm if it can be provided either as an insuranace bond or as a bank bond.

SEE AMENDMENT

BELOW

An offer guarantee is NOT required

Solicit ation page 3 of

With reference to CLIN 0001AA, which is the price for the entire work to construct 79 housing units at Villaggio and Caserma Ederle, we ask if

"the 1.5 meter line outside of the building" includes the sidewalks.

CLIN 0001AB does not include the sidewalks or patios inside of the 1.5 meter line.

60 1 With reference to point 13.B of the solicitation, please clarify if the attached template for Offer

Guarantee is acceptable.

SEE AMENDMENT

BELOW

An offer guarantee is NOT required

With reference to point 13.B of the solicitation, please clarify in which binder the Tender Guarantee has to be included.

SEE AMENDMENT

BELOW

An offer guarantee is NOT required

UTILITY RELOCATION.

In the drawing CD 131, with the code “8” is identified the relocation of the utility tunnel and

SEE AMENDMENT

BELOW

heating pipes, please provide additional details about this activities and

13.A and

4.2.1

In section 13.A on first page, it is requested to send 1 Orignal and 4 Copies fo the Offer; in section 4.2.1 on page 22, paragraph "Non-Price Technical Binders" it is required to submit 1

Original and 5 Copies.

Please specify the exact number of copies required for "Price" and "Non-Price" factors.

SEE AMENDMENT

BELOW

This note has a typographical error, the note should read “Non-price Factors: The offeror shall submit one original, marker “Original”, four

(4) copies marked “copy”…”

64 1 13 B

With reference to section 13 on first page, at point B we read: "An offer guarantee IS required". We do not find any reference to a bid guarantee in the

Standard Form 1442, nor in its attachments.

Please specify if the bid-guarantee is required and eventaully provide a Sample Form.

SEE AMENDMENT

BELOW

An offer guarantee is NOT required

65 11 002100 2.1.8 Must the Prime Offeror maintain the Prevailing Work Category SOA OG01 Class V111 to be considered a qualified bidder ?

Bid in accordance with RFP;

Refer to Section 2.1.8.

CERTIFICATE OF

CLASSIFICATION:

SOCIETÀ ORGANISMI DI

ATTESTAZIONE (SOA)

CERTIFICATION.

66 11 002100 2.1.8

If the Prime Offeror is currently in the process of attaining the Prevailing Work Category SOA

OG01 Class V111, will the Prime Offeror still be considered a qualified bidder ?

Bid in accordance with RFP;

Refer to Section 2.1.8.

CERTIFICATE OF

CLASSIFICATION:

SOCIETÀ ORGANISMI DI

ATTESTAZIONE (SOA)

CERTIFICATION.

67 11 002100 2.1.8

Can a Prime Offeror use an Exclusive Teaming Agreement with a Partner that maintains the Prevailing Work Category SOA OG01 Class

V111 to satisfy this requirement?

Bid in accordance with RFP;

Refer to Section 2.1.8.

CERTIFICATE OF

CLASSIFICATION:

SOCIETÀ ORGANISMI DI

ATTESTAZIONE (SOA)

CERTIFICATION.

Due to Covid-19 emergency, we are experiencing some difficulties in carrying out an accurate and timely market research for this tender and we believe that the upcoming holidays season will worsen the situation. We feel therefore obliged to ask for another extension of the deadline for the submission of the bids of at least 20 days

See previous amendments extending the due date

69 1 SF1442 13.B

With reference to point 13.B of SF1442, an "Offer Guarantee" is required, which in our understanding is the "Bid Guarantee" referred to in FAR 28.001 and 28.101 .

Concerning the "Offer Guarantee" we sent inquiries on 17th and 18th of November in order

SEE AMENDMENT

BELOW

An offer guarantee is NOT required

2. Solicitation Revisions:

CURRENT:

B. An offer guarantee X is, ___ is not required.

REVISED TO:

B. An offer guarantee ___ is, X is not required.

CURRENT:

NON-PRICE TECHNICAL BINDERs:

Non-price Factors: The offeror shall submit one original, marker “Original”, five (5) copies marked “copy”, each in a separate three-ring or four-ring binder, and two (2) electronic copies on separate CDs, with the following characteristics:

REVISED TO:

Non-price Factors: The offeror shall submit one original, marker “Original”, four (4) copies marked “copy”, each in a separate three-ring or four-ring binder, and two (2) electronic copies on separate CDs, with the following characteristics:

3. Revised Attachment E – Schedule B Price Proposal Form Dated 8 Dec 2020 shall replace Attachment E – Schedule B Price Proposal Form.

4. Separate Attachment List:

The following attachments were included with Amendment 7

(L) 1595974Amend0007dwg

(M) 1595974_Amend0007_spc

SECTION 00 10 00 - SOLICITATION

The offer guarantee has changed from is required to is not required.

(End of Summary of Changes) to confirm the amount and the text, leaving understood that the beneficiary is the Government of the United States of America. The issue of the Offer Guarantee on our side depends on your clarifications.

Please clarify.

File details come from the government source that posted it. Updated .