N62470-20-R-4007 Amendment 10.pdf
PDF 28 KB Posted
- Attached to
- P-759, FAMILY HOUSING NEW CONSTRUCTION VILLAGGIO SW & CAMP EDERLE NORTH - VICENZA, ITALY
- Solicitation number
- N62470-20-R-4007
About this file
This document is an amendment to a solicitation for the design and construction of family housing at Villaggio SW and Camp Ederle in Vicenza, Italy. The amendment revises the solicitation in several ways. It establishes a new response due date of April 7, 2021 for offerors to submit revised pricing on Attachment E - Schedule B Price Proposal Form if desired. The statutory cost limitation is increased to $82,802,000 and applies to the base CLIN and all options. The contracting officer point of contact is changed. Clarification is provided on the scope of CLIN 0001AA to exclude sidewalks and patios inside the 1.5 meter line. The contractor performance period is increased by 50 days to 800 days total.
View the file
Other files
Show 40 more
Latest 50 of 71 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
P-759 FAMILY HOUSING NEW CONSTRUCTION VILLAGGIO SW & CAMP EDERLE NORTH VICENZA, ITALY (Phase 1)
PLEASE SEE SF 30 BLOCK 14 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Mar-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247020R4007
X 9B. DATED (SEE ITEM 11)
26-Oct-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Mar-2021
CODE
COMNAVFACSYSCOM ATLANTIC
6506 HAMPTON BLVD
NORFOLK VA 23508-1278
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247020R4007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0010
The purpose of this amendment is for the following items:
1. Solicitation Revisions
2. Establish amendment response due date: Wednesday, April 7, 2021 at 1430 (EST)
3. Change Contracting Officer Point of Contact
4. Clarify responses to Pre-Proposal Inquiries (PPI’s)
5. Provide Attachment E – Schedule B Price Proposal Form Dated 8 Dec 2020
This amendment is applicable to ONLY THOSE OFFERORS that previously submitted a proposal in response to the solicitation by the original proposal due date of December 30, 2020. Those offerors are invited to revise their existing Attachment E – Schedule B Price Proposal Form, if necessary, in response to this amendment. Offerors are NOT required to provide a revised Attachment E – Schedule B Price Proposal Form; however, all Offerors are required to provide an acknowledged copy of this amendment.
The scope of proposal revisions is limited to the areas directly impacted by this amendment;
thus, offerors are permitted only to revise their existing Attachment E – Schedule B Price Proposal Form, if necessary. Offerors are not permitted to make any changes to the previously submitted non-price technical binders or to the previously submitted price proposals with the exception of the Attachment E – Schedule B Price Proposal Form. Changes to non-price technical binders, other portions of the price proposals, or any other change not specifically requested in this amendment will not be accepted.
If an offeror submits any changes other than those requested in this amendment, the proposal may be disqualified at the Government’s discretion.
Acknowledgement of this amendment and, if desired, revised Attachment E – Schedule B Price Proposal Form shall be submitted electronically and directly to the Government’s point of contact, Crystal Carter, via email at crystal.r.carter@navy.mil prior to the amendment response due date established by this amendment. Offerors shall not submit hard copy responses.
1. Solicitation Revisions:
CURRENT:
CLIN 0001
BASE PRICE - IN ACCORDANCE WITH SEPARATE BID SCHEDULE. Price includes the following: CLIN 0001AA. Price for the entire work to construct 79 housing units at Villaggio and Casserma Ederle complete to the 1.5 meter line outside of the building, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs)CLIN 0001AB. Price for the entire project Site Work at Villaggio and Casserma Ederle, outside each buildings 1.5 meter line, complete in accordance with the drawings and specifications, and excludes all other contract line items (CLINs)CLIN 0001AC. Price for the design and construction of the off- installation gas main at Ederle, and excludes all other contract line items (CLINs). The gas main is to be designed and installed by SAR. Includes the pressure reducing valve, all SAR fees and General Contractor mark-up and coordination.
REVISED TO:
CLIN 0001
BASE PRICE - IN ACCORDANCE WITH SEPARATE BID SCHEDULE. Price includes the following: CLIN 0001AA. Price for the entire work to construct 79 housing units at Villaggio and Casserma Ederle complete to the 1.5 meter line outside of the building, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs)CLIN 0001AB. Price for the entire project Site Work at Villaggio and Casserma Ederle, outside each buildings 1.5 meter line, complete in accordance with the drawings and specifications, and excludes all other contract line items (CLINs)CLIN 0001AC. Price for coordinating the design and construction of the off- installation gas main at Ederle by local gas utility purveyor “SAR”, and excludes all other contract line items (CLINs). The gas main is to be designed and installed by SAR. Includes the pressure reducing valve, approximately 385-meters of off-installation pipeline, all SAR fees and General Contractor mark-up and coordination.
PAGE 8-9 OF 60
CURRENT:
1.1.4 This acquisition will result in a firm fixed price contract for design-bid-build construction services. In accordance with FAR 36.205, the statutory cost limitation is $69,000,000 USD for P759 Army Family Housing Villaggio SW and Camp Ederle, North Vicenza, Italy. Award will be made in U.S. Dollars. Statutory cost limitation applies to the Base CLIN.
REVISED TO:
1.1.4 This acquisition will result in a firm fixed price contract for design-bid-build construction services. In accordance with FAR 36.205, the statutory cost limitation is $82,802,000 USD for P759 Army Family Housing Villaggio SW and Camp Ederle, North Vicenza, Italy. Award will be made in U.S. Dollars. Statutory cost limitation applies to the Base CLIN and all options.
CURRENT:
2.1.5 The Government intends to award a contract to a single contractor for CLIN 0001, with CLINs 0002 through 0007 as priced options. The Government reserves the unilateral right to award CLINs 0002 through 0007 to the Contractor at the proposed price at the time of award or within 270 calendar days after the contract award. A firm fixed proposed price is required for ALL CLINs (CLINS 0001 through 0007). No provision is made for economic price adjustment.
The award of one or more options will extend the contract completion date by 40 days (regardless of the number of the options awarded). Offerors not submitting pricing for all CLINs will be considered nonresponsive to the solicitation and will not be evaluated.
REVISED TO:
2.1.5 The Government intends to award a contract to a single contractor for CLIN 0001, with CLINs 0002 through 0007 as priced options. The Government reserves the unilateral right to award CLINs 0002 through 0007 to the Contractor at the proposed price at the time of award or within 270 calendar days after the contract award. A firm fixed proposed price is required for ALL CLINs (CLINS 0001 through 0007). No provision is made for economic price adjustment.
Offerors not submitting pricing for all CLINs will be considered nonresponsive to the solicitation and will not be evaluated.
2. Establish amendment response due date: Wednesday, April 7, 2021 at 1430 (EST)
3. Change Contracting Officer Point of Contact from Vivienne Moore
(vivienne.moore@navy.mil) to Rebecca Douglas (rebecca.douglas@navy.mil)
4. Clarify Responses to Pre-Proposal Inquiries (PPI’s)
Amendment 0008 previously addressed the following PPI #59, please disregard previous response #59 and see below:
5. Attachment E – Schedule B Price Proposal Form Dated 8 Dec 2020 remains unchanged.
Question No.
REFERENCE QUESTION
GOVERNMENT
RESPONSE
Page Section Para
Solic itatio n page 3 of
With reference to CLIN 0001AA, which is the price for the entire work to construct 79 housing units at Villaggio and Caserma Ederle, we ask if "the 1.5 meter line outside of the building" includes the sidewalks.
CLIN 0001AA does not include the sidewalks or patios inside of the 1.5 meter line.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 30-Dec-2020 02:30 PM to 07-Apr-2021 02:30 PM.
The contractor period of performance end date has increased by 50 days from 750 days to 800 days.
(End of Summary of Changes)