7488748_B.doc

DOC document 6 MB Posted

Attached to
PSA of USNS MATTEW PERRY (T-AKE 9) and USNS CHARLES DREW (T-AKE 10)
Solicitation number
N40442-10-R-3012
Issued by

About this file

associate drawing

View the file

Other files

File Type Posted
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS.doc DOC document
10-R-3012 amendment 5.doc DOC document
SM1000-01_A-REV.pdf PDF
SM1000-02_A-REV.pdf PDF
SM1000-03_A-REV.pdf PDF
350-000-01.pdf PDF
1INFORMATION DATA.doc DOC document
10-R-3012 amendment 4.doc DOC document
SM1000_TP.pdf PDF
0109_A_ Bilge Well Preservation.doc DOC document
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS.doc DOC document
0003_NSP_ APPROACH BERTH AND MOORING.doc DOC document
10-R-3012 amendment 3.doc DOC document
WI 560 Calcium Carbonate Dosing System.docx DOCX document
GFM List for WI Index Amend 3.xls XLS spreadsheet
References for WI Index T-AKE 9 PSA Amend 2.xls XLS spreadsheet
0003_NSP_ APPROACH BERTH AND MOORING.doc DOC document
10-R-3012 amendment 2.doc DOC document
0622_A_Second Deck Cargo Hold Modifications.doc DOC document
GFM List for WI Index T-AKe 9 PSA Amend 2.xls XLS spreadsheet
WI 501 Ref 2.4 Drew Technical Product Sheet MC-PD-46.pdf PDF
WI 501 Ref 2.5 Drew Removal of Corrosion Products T-AKE.doc DOC document
261-7488730_D 1.DWG DWG drawing
WI 0561 Senitec OWS Sys Installation.doc DOC document
Ref for WI Index T-AKE 10 PSA Amend 1.xls XLS spreadsheet
0547_A_HP Crossover to EDG Start Air System.doc DOC document
2.7 Attachment 7 Ball Valve Removal Photo.pdf PDF
0617_A_06 Lvl Vent Trunk Door Install.doc DOC document
261-7488730_D 2.DWG DWG drawing
7488951_L.pdf PDF
479-341-7012_--_SRD_Appendix A.DOC DOC document
GFM List for WI Index.xls XLS spreadsheet
8390078 Senitec OWS Installation .pdf PDF
7488736_D Distilled Water Transfer Sys Diagram.pdf PDF
T6435-CM-MMC-010.pdf PDF
261-7488730_D 3.DWG DWG drawing
7488736_D.pdf PDF
529-74 3.DWG DWG drawing
261-8389758 B - Mn Diesel Gen Remote Fuel Isolation Valve Install.pdf PDF
2.2 Attachment 2 471-342-7126_C-SRD_004.dwg DWG drawing
479-341-7012_--_SRD_Appendix D.xls XLS spreadsheet
2.6 Attachment 6 On Line and Recirc Manifold locations photos.pdf PDF
20001700 REV C Transmitter Installation Man.pdf PDF
479-341-7012_--_SRD_Appendix C.DOC DOC document
20002298REV C F-Series Meter Install Manual.pdf PDF
261-7488730_D 5.DWG DWG drawing
529-74 1.PDF PDF
WI 205 FO Meter Replacement.doc DOC document
9197402200E Senitec M1000 Assembling Instructions.pdf PDF
GFM List for WI Index.xls XLS spreadsheet
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

H-01 (HOLD UP)

ASSOCIATED MARK-UP WORK INSTRUCTIONS

IDENTIFYING FLUSHING PATHS PENDING

RECEIPT FROM NASSCO PRODUCTION DEPT.

H-02 (HOLD UP)

DETAILS OF FLUSHING REQ’TS FOR FM 200 SYSTEM PENDING SYSTEM DESIGN DEVELOPMENT

H-03 (HOLD-UP)

BOW THRUSTER L.O. SYSTEM (DIAGRAM 7128) FLUSHING MEDIA & CLEANLINESS CRITERIA PENDING VENDOR GUIDANCE.

478
TBD
NASSCO
477
TBD
NASSCO
476
TBD
NASSCO
475
TBD
NASSCO
1
474
TBD
NASSCO
473
TBD
NASSCO
472
SACAGAWEA
NASSCO
471
LEWIS AND CLARK
NASSCO
HULL NO
SHIP NAME
BUILDING YARD

ABS

SUBMITTED TO
DATE
APPROVED

DISTRIBUTION STATEMENT C - DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS; (CRITICAL). OTHER REQUESTS FOR THIS DOCUMENT WILL BE REFERRED TO COMNAVSEASYSCOM (PMS 325).

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC. 2751 ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED (TITLE 50, U.S.C., APP. 2401, ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATION IN ACCORDANCE WITH PROVISIONS OF OPNAVINST 5510.161.

DESTRUCTION NOTICE - FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.

NASSCO
NATIONAL STEEL AND SHIPBUILDING COMPANY

A GENERAL DYNAMICS COMPANY

2798 HARBOR DRIVE

SAN DIEGO, CA 92113

DRAWN:

C. Chen

DRY CARGO / AMMUNITION SHIP

T-AKE 1 CLASS

CHECKED:

M.R. Brooks

FLUSHING CRITERIA AND GUIDELINES

APPROVED:

K.M. Scott

DATE:

12/18/02

APPROVED

SUPSHIP, SAN DIEGO

CONTRACT NO.
NAVSEA DRAWING NUMBER
N00024-02-C-2300
505-7488748
SIZE
CAGE NO.
NASSCO DRAWING NUMBER
REV
A
81220
471-342-7138
B
DATE: ______________
SCALE: none
Page 1 of 94

REVISION SHEET

REV
ITEM
SHEET
DESCRIPTION
DATE
APP'D
A
1
1
Added Hull 474 to list of applicable hulls.
2
9
Added flushing guidelines for Diagram (7103), FM 200 System, releasing Hold-Up H-02.
3
16
Diagram 7109: revised various maximum system pressures to reflect Rev. A of the diagram
4
17
Diagram 7110: revised maximum pressure to 56.3 psig to reflect latest Rev. A of the diagram.
5
19
Diagram 7112: added compressor discharge pressure and temp. to reflect latest Rev. A of the diagram.
6
26
Diagram 7122: added tank vent pressures for sea chests and non-aviation tank vents.
7
27
Diagram 7123: deleted incinerator ash removal system procedure to reflect deletion from Rev. A of the diagram.
8
29
Diagram 7124: revised system pressure to 99.5 psig to reflect latest Rev. A of the diagram and added FW drain tank piping pressure and temperature info.
9
30
Diagram 7126: revised system pressure for Distilling Plant Services SW feed system to 78 psig, distillate to 38 psig.
10
31
Diagram 7127: revised relief valve discharge piping maximum system pressure to 50 psig to reflect latest Rev. A of the diagram.
11
32
Diagram 7128: added bow thruster lube oil system flushing criteria - releases Hold-Up H-03 to Hydraulic Piping System. Revised glide slope system pressure to 1800 psig and temp. to 140(F to reflect latest Rev. A of the diagram.
12
35
Diagram 7132: revised maximum temp. to 113(F to reflect latest Rev. A of the diagram.
13
38
Diagram 7137: maximum temperature (for start air system) revised to 120(F to reflect latest Rev. A of the diagram.
14
44
Diagram 7156: added oily waste transfer maximum pressure of 72 psig.
15
46
Diagram 7158: added system pressures and temp. for transfer/purification and stripping outside of tanks of Aviation JP5 Transfer and Service systems to reflect latest Rev. A of the diagram.
16
50
Added flushing information for Diagram 471-342-7174, Local Water Based Fire Extinguishing System.
12/15/03
K.M.Scott

REVISION SHEET

REV
ITEM
SHEET
DESCRIPTION
DATE
APP'D
B
1
1
Extended applicability to Hull 478.

Aviation F-44 Systems- comments section to include hand wiping of Aviation Fuel Storage Tank. Change incorporated via ECN E-01.

3
27, 28, 29
Added requirements for the antenna dry air system per FMR 101.2 and ECN 471-342-7117 E-13.
4
ALL
Revised page numbers and Table of Contents to reflect revised page numbers.
5
13
L.O. Fill, Transfer & Purification System- deleted details of flushing setup due to potential conflict with detail flushing work instruction. Deleted mention of muslin bags under Cleanliness Criteria. Not required for work instruction setup.
6
19
Mach’y Space Bilge System- deleted air blow down for contaminate removal as impractical due to size of system piping.
7
17
High Temp FW Cooling System- deleted requirement to flush with emulsion containing Gotar DG per email from Angelo Mazzenga/FME dated 10 Feb 2005.
8
18
Seawater Cooling System- deleted requirement to jumper around the LT and HT FW coolers. Not needed on past ships and impractical due pipe size and space constraints.
9
20
Inert Gas SW System- revised scope of system flushing to reflect deletion of majority of system per FMR 045.2 and ECN 471-342-7111 E-01.
10
22
Incinerator & MHE Fueling System- modified text from “flush bags” to “filters”. Corrected system title.
11
26
SS & Control Air System- revised suggested setup for distribution piping to refer to work instruction.
12
30
Sludge Collection & Transfer System- changed procedure to call for testing with water in lieu of compressed air.
13
31
Vent, Sounds & Overflows- deleted reference to 50 psig from Suggested Setup due to potential conflict with Max. Pressure column.
14
32, 33
Aux. SW Services- Clarified flushing sequence under Suggested Setup based on Production guidance.
15
10
Firemain System- Clarified setup requirements.

REVISION SHEET

REV
ITEM
SHEET
DESCRIPTION
DATE
APP'D
B
16
11
FM200 System- Clarified sequence for installation of nozzles.
17
12
Cargo Hold Sprinkling System- Clarified blow down procedure as sequential, one grid section at a time.
18
15
MDG L.O. Service System- Revised recommended flushing flow rate, temperature and medium to suit available flushing rig equipment.
19
35
Distilling Plant Services- Clarified chlorination soak procedure.
20
36
Refrigeration Systems- Provided clarification regarding pumpout hoses and use of temporary flush rig.
21
41
MDG Wash System- Eliminated reference to flush rig, clarified that flush is performed using FW rather than distilled water, and that heater should also be bypassed.
22
42, 43
EDG Services- Revised flushing media for starting air system from fresh water to air to be consistent with past practice and with procedure used for MDG starting air system (System No. 12). Revised flushing procedure for cooling water system to specify more viable process successfully used previously for similar system on Sealift NC vessels.
23
44
A/C Chilled Water System- Deleted flush bags as not required. Temporary strainer baskets provide adequate filtration.
24
47
Foam Fire Fighting System- Added details for clarification.
25
48
Countermeasure Washdown System- Clarified that blow down may be performed segment by segment and that nozzles are not to be installed until completion of blow down.
26
52
Cargo Hold and Misc. OWT System- Clarified cleanliness criteria for main drainage vs OWT piping.
27
52
Cargo Fuel Systems- Eliminated requirement to hand wipe cargo tanks.
28
55
Local Water Based Fire Extinguishing System- Reduced number of nozzle locations requiring flushing indicator strainers.
4/26/05
MRB

TABLE OF CONTENTS

ITEM NO.

DIAGRAM
DIAGRAM NO.
SHEET NO.
1
WEATHER DECK DRAINS
471-342-7101
9
2
FIREMAIN SYSTEM
471-342-7102
10
3
FM 200
471-342-7103
11
4
SPRINKLING SYSTEMS
471-342-7104
12
5
LO, FILL AND TRANSFER
471-342-7105
13
6
MDG LUBE OIL
471-342-7106
15
7
CENTRAL FW COOLING SYSTEM
471-342-7107
16
8
DG HIGH TEMP FW COOLING SYSTEM
471-342-7108
17
9
CENTRAL SW COOLING SYSTEM
471-342-7109
18
10
BILGE & OWT SYSTEM DIAGRAM (M/C SPACE)
471-342-7110
19
11
INERT GAS SYSTEM DIAGRAM
471-342-7111
20
12
DIESEL GEN STARTING AIR SYSTEM DIAGRAM
471-342-7112
21
13
INCINERATOR & MHE FUELING SYSTEM
471-342-7113
22
14
FO, FILL, TRANSFER & PURIFICATION SYSTEM
471-342-7114
23
15
DIESEL GEN FUEL SERVICE SYSTEM DIAGRAM
471-342-7115
24
16
BALLAST SYSTEM DIAGRAM
471-342-7116
25
17
SHIPS SERVICE & CONTROL AIR SYSTEM DIAGRAM
471-342-7118
26
18
SLUDGE COLLECTION AND TRANSFER
471-342-7119
30
19
VENTS, SOUNDS & OVERFLOWS DIAGRAM
471-342-7122
31
20
SW SERVICES DIAGRAM
471-342-7123
32
21
DISTILLED WATER TRANSFER SYSTEM DIAGRAM
471-342-7124
34
22
DISTILLING PLANT SERVICES DIAGRAM
471-342-7126
35
23
REFRIGERANT & PURGE PUMPOUT SYSTEM DIAGRAM
471-342-7127
36
24
HYDRAULIC PIPING SYSTEM DIAGRAM
471-342-7128
37
25
HOT & COLD POTABLE WATER SYSTEM DIAGRAM
471-342-7131
39
26
VACUUM SEWAGE & PLUMBING DRAINS SYSTEM
471-342-7132
40
27
DIESEL GEN COLLECTION & WASH SYSTEM
471-342-7135
41

ITEM NO.

DIAGRAM
DIAGRAM NO.
SHEET NO.
28
EMERGENCY DIESEL GEN SERVICES DIAGRAM
471-342-7137
42
29
A/C CHILLED WATER SYSTEM DIAGRAM
471-342-7149
44
30
CARGO REFRIGERATION SECONDARY COOLANT CIRCULATION SYSTEM DIAGRAM
471-342-7150
45
31
FOAM FIREFIGHTING
471-342-7154
47
32
COUNTERMEASURE WASHDOWN SYSTEM DIAGRAM
471-342-7155
48
33
CARGO HOLD & MISC. OWT SYSTEM DIAGRAM
471-342-7156
49
34
CARGO POTABLE WATER SYSTEM DIAGRAM
471-342-7157
50
35
AVIATION F-44 TRANSFER AND SERVICE SYSTEMS DIAGRAM
471-342-7158
51
36
CARGO FUEL SYSTEM DIAGRAM
471-342-7159
52
37
HIGH PRESSURE AIR SYSTEM
471-342-7173
54
LOCAL WATER BASED FIRE EXTINGUISHING SYSTEM
471-342-7174
55

APPENDIX A - TURBULENT FLUSH CRITERIA

APPENDIX B – FME-MAN 48/60 ENGINE FLUSH CLEANLINESS CRITERIA

APPENDIX C – CATERPILLAR EDG FLUSH CLEANLINESS CRITERIA

APPENDIX D – YORK MARINE AB FLUSHING PROCEDURE

SYSTEM SPECIFIC NOTES

1. The body of this document follows in the tabular form, sorted on System Diagram Number for those systems requiring flushing.

2. The enclosed document provides suggested general guidance and cleanliness criteria for flushing and flowrates to achieve turbulent flow for hydraulic, fuel, lube and diesel oil systems. An associated system work instruction providing specific flushing loops is provided in the Livelink files, which is co-located in Livelink with this document.

3. Low flow volume or dead spots shall be minimized to the extent practicable during a system flush. Dead ended system lines shall be flushed .

4. Normally flush medium is specified except where safer, compatible or less expensive mediums are permissible. Lubricating/hydraulic system mediums are specified in Drwg. 471-342-4970 “List of Lubricants”.

5. No flush setup shall exceed a systems test pressure.

6. No flush setup shall exceed temperature restrictions shown on the system diagram. Heating shall only occur where internal preservation removal requires it, where reduction in flush medium’s viscosity is needed or where internal fluid friction heat is developed.

7. Components that have been purchased and certified clean shall be bypassed.

8. Components such as heat exchangers, control valves, regulating valves, orifices, solenoids and other equipment having in-line mechanisms capable of trapping or affected by carry-over of foreign matter shall be jumpered or removed to ensure that debris does not damage or become lodged during the flush, unless protected by a suitable strainer.

9. Mechanical vibrators shall be used judiciously as determined by flush supervisor and generally employed only for the lube oil systems.

10. For systems requiring only blow down, clean yard compressed air shall be applied. Prior to application, air hose shall be blown-out to remove any condensation accumulation.

11. Where ship's tanks are included in the flushing circuit, the tanks shall be opened and cleaned before and after flushing.

12. All muslim bags referred to in this document shall be nylon mesh type, 150 micron filtration, for all locations where used unless where otherwise specified.

13. After a flush is completed, system strainers shall be inspected to ensure no debris remains in the flushing loop.

14. The maximum permissible water content for hydraulic oil is 0.05% and for fuel oil is 0.2%.

15. Source of turbulent flow criteria specified in Appendix A charts is derived from SupShip San Diego Reference 224, “Flushing of Repaired, New or Disturbed Piping Sections” Rev. E, dated 28 May, 1992.

ITEM

No.

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Weather Deck Drains
7101
Fresh

water Static head for water

Amb.
Utilize deck drains as is.
Demo. unobstructed flow
System receives flow through all branches.

ITEM

No.

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Firemain System Diagram
7102
Seawater
190 psig
95(F
Operational flush using system pumps and strainers checking the farthest hose points on ring type firemain, port and starboard for each cargo hold and deck level. As a minimum the following fire stations shall be opened during this procedure; 105,124, 201, 202, 301, 302, 304, 306, 394, and 396. Fire stations should be opened concurrently to the extent practical to maximize velocities in the mains. If flush is performed in port, water shall be led to a collection system as required.
Unobstructed flow at the farthest hose points.

Systems using seawater from the firemain may be flushed during this operation.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
3
FM 200
7103
Air
502 psig

distributionpiping

2062 psig actuation piping

130( F
For each FM 200 system, piping actuation and distribution system should be blown free of foreign material. Disconnect piping from downstream flange of FM200 cylinder. Connect air to FM 200 piping.

Repeat air blowdown for all compartments with FM 200 systems. System nozzles shall not be installed until after all flushing and pressure testing has been completed.

Unobstructed flow until clear discharge is attained.

Install FM 200 nozzles after pressure testing and air blow down is complete. Vendor shall install the nozzles.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Cargo Hold

Sprinkling Systems Diagram

7104
Air
190 psig
95( F
Prevent inadvertent operation of sprinkler control valve by isolating the magazine sprinkling hydraulic control system or shutting the firemain isolation valve to the sprinkler control valve.

Blow down each segment of the sprinkling grid piping using compressed air.

Repeat air blow down for all compartments with sprinkler systems, removing sprinkler heads during process.

Perform operational flush using system pumps during at sea operational system test.

Unobstructed flow until clear discharge is attained.

Reinstall sprinkler heads after air blow down is complete.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

LO Fill, Transfer & Purif.

System

7105
SAE 40 lube oil
140 psig Transfer

43.5 psig

Purification 185(F

Transfer

226(F

Purification

Use temporary flush rig. Use flushing loop recommendations shown on the corresponding work instruction.

Cleanliness criteria is NAS Class 10.

Upon completion of flush, all piping and components are to be completely drained of all flushing oil including any intermediate low points in the piping, unless system oil is being reused.

Tanks shall be hand wiped with lintless cloth.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

con’t

LO Fill, Transfer & Purif. System
7105
SAE 40 lube oil
140 psig Transfer

43.5 psig

Purif.

185(F

Transfer

226(F

Purif.

Fill system with oil and circulate the heated oil through the system piping. Piping on the purifier skid should be bypassed.

After completion of inspection and manual cleaning, all inspection and cleanout covers will be reinstalled.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
MDG LO Service Systems Diagram
7106
SAE 40

(preheated to 40-50(C) or as an alternative SAE 20 oil may be used for flush

If SAE 20 is used, system must be fully drained after flush.

127.6 psig
167(F
Follow flushing stages outlined in FME-MAN 48/60 Guidance and associated Nassco work instruction; first flushing stage covers piping outside of the engine. Second stage covers main engine and spray nozzles.

Use flush rig for main diesel generator engine supply and return piping (flush at minimum flowrate of 162 gpm based on flush with SAE 20 oil at 160(F), turbocharger run down tank and turbocharger outlet piping. Upon completion of flush, remove temporary flush equipment and reconnect piping.

Fairbanks Morse Guidance (Operating Media Systems Flushing and Cleaning) for Lube Oil, are contained in Appendix ‘B’.

NAS Class 10

Lube oil piping should be pickled prior to installation.

Note that the Main Engine L.O. service pumps are built into the engine and therefore can not be used for initial flush due to potential internal damage to the engine.

Final on board main engine lube oil system flush shall be called out w/ Fairbanks Morse present.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
FW Cooling System Diagram
7107
Fresh

water

100 psig
125(F
Operational flush using system pumps. Operate regulating valve bypasses during flush to flush bypass piping. A temporary flushing strainer is provided in the cooling pump suction header which is to be removed upon completion of flush operation.

Flush piping to equipment located in:

· HV Equipment Room

· EOS

· AMR

· Propulsion Motor Room.

Unobstructed flow, all strainers are visibly free of harmful contaminants.
Bypass plate heat exchangers, equipment, control valves during flush, except components provided with individual strainers located immediately upstream of supply inlet, need not be bypassed.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
High Temp. FW Cooling
7108
Fresh

water.

87 psig
208(F
Operational flush using system pumps. Temporary flushing strainers are provided in each jacket water cooler inlet, the strainer plates of which are to be removed upon completion of flush operations.

Prior to initial operation of the engine, system (including engine) is to be flushed with freshwater. See Appendix B for cleaning procedure.

Unobstructed flow, all strainers are visibly free of harmful contaminants.
Bypass plate heat exchangers, main DG engine.

Main DG engine need not be bypassed if normal system strainer at inlet to each engine is fitted.

Following the flushing operation, flush system with plain freshwater.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Seawater Cooling System Diagram

7109
Seawater
45.3 psig (Cu-Ni)

33.4 psig

(Sea suction/ discharge)

122(F
Operational flush using system pumps.

Line up two of the three SW pumps to take suction from the high and low seachests. Verify suction piping from main suction strainers to pumps is visually free of debris.

Unobstructed flow.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Bilge System Diagram (Machinery Space)

7110
Fresh

water

56.3 psig
95(F
Hydro piping with water and then air blow dry
Unobstructed flow during operational testing, during which pumps are protected by system strainers.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
11
Inert Gas System Diagram

(Vent piping)

7111
Air
4 psig
117(F
IG01 Piping

Blow down with compressed air.

Unobstructed flow.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Diesel Generator Starting Air System
7112
Air
450 psig @ piping other than compressor discharge

479 psig @ compressor discharge

149(F
Follow FME-Man 48/60 Standard, See Appendix B (Flushing and Cleaning) Compressed Air System.

Use air from the air compressor to blow piping clear prior to running through engine, bypassing the Diesel Engines, Turning gear.

Blow out piping using ships starting air compressors.

Unobstructed flow, using air blowdown.
Continue blow out until discharges are visibly free of harmful contaminants

Upon completion of blow out- restore system.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Incinerator & MHE Fueling System Diagram
7113
T15 Hydraulic oil
88 psi
113(F
Use temporary flush rig

fitted with filters. Bypass installed pump, fuel recirculating control valve, fuel service tanks and hose reel assembly.

NAS Class 10

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Fuel Fill Transfer & Purif.
7114
T15 Hydraulic oil
Fuel transfer down-stream of standpipe & suction piping:

38 psig

Fuel fill & transfer piping upstream of standpipe:

200 psig

Fuel purification discharge:

45 psig

113(F
Use temporary flush rig to flush fuel oil purification piping on the fuel oil system (note for overflows, see item 18, VS & O procedures) following associated flush work instruction.

Fill lines (port and starboard double hose receiving stations) can be done when loading fuel with strainers prior to tanks to catch contaminants.

Transfer piping can be done with ship’s pumps with nylon (mesh type 150 micron) filters during operational test.

Muslin bags should be installed in transfer pump suction inlets.

Cleanliness criteria is NAS Class 10 for fuel purification system.

For other parts of the system, strainers are visibly free of harmful contaminants.

Purifier piping is considered most critical loop to flush, using flush rig.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Diesel Gen Fuel Service System
7115
T15 Hydraulic oil
DO pump discharge:

116 psi

122( F
Use temporary flush rig. Use flushing loop recommendations shown on corresponding flush work instruction.

Follow FME-Man B&W Standard Procedure (Operating Media Systems Flushing and Cleaning) Fuel Delivery System. See Appendix B.

Cleanliness criteria is NAS Class 10.
Bypass the FO Service pumps, FO coolers and Diesel Generator Engines during flush.

Load fuel prior to operation of engines.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Ballast System

Seawater

72.5 psig

95(F

Operational flush.

Verify suction piping from seachest to pump is visually free of debris.

Aft Ballast Tanks:

Operationally flush seawater through main header and branch piping to the aft ballast tanks. Dewater tanks using temporary pump when flush is complete and clean tanks.

Forward Ballast Piping:

Flush forward ballast piping utilizing system ballast pumps to flush seawater discharge to the ballast tanks. Dewater tanks using temporary pump after flush is complete and clean tanks.

Unobstructed flow, all strainers are visibly free of harmful contaminants

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Ship Service and

Control Air

7118
Air
140 psig
158 (F
1. Piping hydrostatic test

2. Air blowdown

Compressor/Receiver/ Dehydrator Piping:

Blowout drains in piping and receiver until discharge is visibly free of moisture and foreign matter.

Machinery Rooms, Cargo Holds, RAS/FAS Stations, Lines to all decks:

Blow out system mains and branches using dock air in accordance with the detail work instruction.

Unobstructed flow until clear discharge is attained.

Bypass or remove filters and lubricators.

Air blowdown until clear , dry discharge is attained.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

(cont.)

Ship Service and

Control Air

(continued)-

Antenna Dry Air System

7118
TSP/water solution
4 psig
180 (F
Antenna Dry Air System:

1. Clean in accordance with MIL-STD-1622B.

2. Before system cleaning, disconnect components subject to damage from cleaning fluids. Where feasible install temporary jumpers to provide circulation through dead ends.

3. Cleaning of the piping system shall be accomplished by the following methods: circulation of hot cleaning solution, filling and soaking dead end portions where circulation is not feasible, or by separate scrubbing or soaking or both, of components which cannot be cleaned by flushing.

Following installation and cleaning of Antenna Dry Air System, purge in accordance with NAVSEA SE-000-00-EIM-110.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

(cont.)

Ship Service and

Control Air

(continued)

7118
TSP/water solution
4 psig
180 (F
4. Circulate the hot (180 (F) solution for at least one hour after the pipe walls are heated to a constant temperature. The minimum flow rate shall be as required to ensure fully turbulent flow in the largest pipe in the portion of the system being flushed (flushing rate in GPM shall be at least six times the internal diameter of the pipe in inches). Use the following proportions for making the cleaning solution: a) trisodium phosphate, technical grade, anhydrous, Fed. Spec. 0-S-642, Type I (7 to 10 ounces to one gallon of clean freshwater), or b) trisodium phosphate, technical grade, dodecahydrate, Fed. Spec. 0-S-642 Type II (16 ounces to one gallon of clean freshwater).

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

(cont.)

Ship Service and

Control Air

(continued)

7118
TSP/water solution
4 psig
180 (F
5. After rinsing and thoroughly draining, the pipe shall be dried out by blowing with clean dry air, oil-free nitrogen Fed. Spec. A-A-59503, Type 1, Gr. A or B, or air meeting the same requirements as the rated outlet conditions of the system dehydrators. The blowdown gas may be warmed to speed up drying. Dryness shall be assured by testing with cobalt chloride paper, or other similar indicator such as a dewpoint meter. Acceptable dewpoint is 10 (F below ambient. Upon completion, the piping shall be immediately reconnected to final system configuration, taking care to maintain cleanliness.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Sludge Collection and Transfer System

7119
Water
100 psig

for sludge transfer pump discharge, 38 psig for gravity drain piping.

113(F

Gravity drains shall be operationally tested and proven clear with water.

Transfer piping will be tested in service with the sludge transfer pump protected by the installed suction strainer.

Unobstructed flow.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Vents, Sounds & Overflow Diagram

7122
Air
10 psig

(aviation tank vents) 35 psig

(tank vents)

50 psig

(sea connection) 95(F 95(F

95(F Remove vent screen from vent lines.

Blow down all vent lines on equipment and tanks with air.

Air blow down to verify no obstructions.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Auxiliary SW

Services:

Stern Tube

BowThruster & Incinerator

7123
Seawater
51 psig

87 psig

95(F

122(F

Stern Tube :

Operational flush using the firemain system. For initial flush, bypass filters and verify unobstructed flow at flange before the stern tube seal.

After initial flush, flush through system filters to ensure all piping is clear.

Bow Thruster:

Use firemain system to flush through piping to bow thruster motor and thruster converter. Jumper bow thruster motor and thruster converter tying into the flushing water collection system. Overboard discharge piping will be flushed in the normal course of operational testing.

Unobstructed flow. No visible contaminants at the filter.

Unobstructed flow. No visible contaminants at the filter.

Bypass stern tube cavity.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

20 (con’t)

Auxiliary SW

Services:

Solid Waste Processng

7123
Seawater
87 psig
122(F

Solid Waste Processing Room:

Use firemain to flush through piping jumpering around CMU cooling unit and Pulper Assembly to the flushing water collection system. Overboard discharge piping will be flushed in the normal course of operational testing.

Unobstructed flow. No visible contaminants at system strainers.
Do not flush through CORD’S.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Distilled Water Transfer

7124
Fresh

Water:

(distilled water transfer piping)

Fresh Water:

(fresh water drain tank piping)

99.5 psig

140 psig 113 (F

113 (F

Use system pumps to perform operational flush or flush directly from shore side water main through system.

If flush uses dockside water, drain system at completion of flush.

Unobstructed flow, no harmful contaminants.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Distilling Plant Services

7126
Seawater

Feed

78 psig

(Sw feed) 38 psig

(distillate line) 113 (F 95 (F Operational flush for seawater feed piping. Isolate entire distilling plant from sw feed system. Use installed pump and discharge to brine overboard piping.

FW soak distillate piping from evaporator discharge to termination of lines in potable and distillate water tanks including Recirculation Brominator piping. Flush from evaporator distillate outlet valve to potable and distillate water tanks using shore side water main. At conclusion of flush, chlorinate distillate piping and tanks to:

100 ppm min in tanks

50 ppm min. in system. After min. concentration is achieved let stand for minimum of 4 hours. Take coliform sample.

No harmful or visible contaminants detected at discharge.

For the distillate piping, the pressure test period will be concurrent with the chlorination soak period.

Chlorination will be performed on the potable water supply piping only, and will not include the distilled water tank supply piping.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

A/C Refrigeration & Purge Pumpout System

Ship Stores Refrig. 1 & 2 & Cargo Refrig. & Purge Pumpout System

Relief Valve Discharge

R134A

R404A

Air High:

203 psig

Low:

150 psig

Low:

123.6 psi

High:

438 psi

< 50 psig 125.3(F

105.1(F

59(F

150(F

113(F Flush required- flush interconnecting yard piping with Castrol E 68 oil prior to being connected to the condensing unit or evaporator coils.

After interconnecting piping is flushed and installed, use nitrogen purge to prevent scale and oxidation of copper. Leak check unit and purge with nitrogen. Evacuate system and charge with applicable refrigerant and reclaim same fluid.

Evacuate system again, and recharge system with clean refrigerant.

Air blow down using compressed air.

Verify unobstructed flow.

Shipyard flushing rigs and filters will be used for this flush. Do not use system compressor for oil flush.

No flush is required for the pumpout systems as this all consists of vendor supplied hoses used for temporary hookup when needed.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Hydraulic Piping

7128
ISO 68

Hydraulic oil

ISO 46 Hydraulic oil

36 psig (handpump discharge line) 10 psig (head tank) 1000 psig

113(F

113(F

Bow Thruster Lube Oil:

Use a temporary flush rig to flush head tank supply line. Flush handpump suction and discharge lines.

Personnel Access Door:

Use a temporary flush rig fitted with a 3 micron filter to flush supply and return lines. Upon flush completion drain entire system Reassemble jumpered areas and refill w/ new medium.

ISO 4406

Grade 16/13

ISO 4406

Grade 17/14

During fab. of piping, pickle and oil steel piping. After flush, use 10 mic. or better filter when using new hyd. oil. Before filling system with oil, allow supplier to check system

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Hydraulic Piping (con’t):

7128
Air

MIL-H-22072 Hydraulic oil 450 psig

1800 psig 113(F

140(F Quick Closing Valves

Each pipe length shall be hand cleaned, deburred and blown out with dry compressed air before mounting.

Stabilized Glide Slope Indicator System:

Flush supply and return line by disconnecting lines at shutoff valves and forming loop with flush pump.

NA

ISO 4406

Grade

19/16 Flush at minimum flowrate of 9 gpm @ 130(F temperature

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Hot and Cold Potable Water
7131
FW
100 psi
113 (F
Operational test; use installed pumps. Clean potable water tanks, fill with FW and chlorinate to:

100 ppm min in tanks 50 ppm min. in system Flush system through each outlet.

After minimum concentrations is achieved in all legs of system, let stand for a min. of 4 hours. Flush clear with freshwater from tanks – take coliform samples.

Unobstructed flow, no visible contaminants.
Entry into potable water tanks is prohibited after disinfection.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Vacuum Sewage & Plumbing Drains System

7132
Potable Water
Normal system operation
113(F
Operational test in conjunction with potable water test.
Free, unobstructed flow

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
MDG Wash & Collection
7135
Fresh Water
44 psig
122 F
Flush piping using dockside fresh water following pressure testing. Jumper around MDG Engine Charge Air Coolers and Chemical Cleaning Heater.
No visible contaminants
Bypass MDG Engine Charge Air Coolers and Chemical Cleaning Heater.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Emergency Diesel Generator Services Diagram
7137
T15 Hydraulic

Oil

Fresh water Fuel:

38 psi

Jacket water:

54 psig

SCAC:

44 psig 120 (F.

215(F Use temporary flush rig and follow Caterpillar EDG flush guidance provided in Appendix C. Use flushing loop recommendations shown on flush work instruction.

Diesel Oil Piping:

Flush diesel oil supply (using T15 hydraulic oil) and return piping from connections to Emergency Diesel Generator Fuel Service Tank.

Fresh Water Cooling Systems:

Disconnect flanged joints and flush piping (including expansion tank piping) with FW hose using dockside water supply.

Cleanliness criteria is NAS Class 10 for diesel oil piping.

No visible contaminants in water piping.

During fabrication of piping, pickle and oil steel piping. Wash piping with suitable solvent and dry thoroughly. No flush required for EDG exhaust. Bypass control valves.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

28 (con’t)

Emergency Diesel Generator Services Diagram

7137
15W40 lube oil

Air

Atm.

435 psig 150(F

120(F.

Lube Oil System:

Flush lube oil piping (utilize 15W40 CG-4 lube oil) bypassing the EDG and the Generator.

Start Air System:

Use air from the air compressor and/or flasks to blow piping clear prior to running through engine.

Cleanliness criteria is NAS Class 10 for lube oil piping.

Unobstructed flow. Continue blow out until discharges are visibly free of harmful contaminants.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
A/C Chilled Water System
7149
Fresh water
LT CW

150 psig

HT CW

100 psig

LT CW

55(F

HT CW

90(F Use installed pumps. Install temporary strainers on suction side of pumps.

Low temperature loop serves the Accommodation and Cargo Space HVAC.

High temperature loop serves the Machinery Space pre-cooling coils.

Flush until no visible harmful contaminants are detected.
Bypass chillers, air handling units, and regulating valves.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Cargo Refrigeration Secondary Coolant Circulation System

7150
Air, Refrig. SecondaryCoolant

99.4 psig

Ambient

Follow York Marine AB Installation, Blowing and Flushing Procedure, Appendix D. Procedure calls for air blowdown, pressure test, vacuum suction and fill and flush with Refrig. Secondary Coolant. Temporary flush strainer can be installed in downstream bypass of Defrost pump (referred to as Main Pump No. 3 in York procedure).

Flush until no visible harmful contaminants are detected in strainer.
Bypass equipment and system regulating valves.

Note:

piping referred to as X, Y and H in York procedure correspond to system diagram as follows:

· X: chill piping

· Y: freeze piping

· H: defrost piping

· Constant pressure overflow valves:

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

30 (con’t)

Cargo Refrigeration Secondary Coolant Circulation System

7150
Air, Refrig. SecondaryCoolant
99.4 psig
Ambient
.
referred to in section 2/e:

RA-V-210, RA-V-211

Pneumatic operated stop valve referred to in section 2/e:

RA-V-209.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Foam Fire Fighting Systems Diagram
7154
SW
190 psig
95(F
All foam piping shall be flushed after installation. With aft foam proportioner isolated, utilize seawater supply from firemain system to flush each segment of the foam piping to Helicopter Hangar, Flight Deck/Hangar hose reels and Main Machinery Room Bilge Sprinkling.

With fwd foam proportioner isolated, utilize seawater supply from firemain system to flush each segment of the foam piping to Cargo Pump Room Bilge and the forward hose reel stations.

Use countermeasure washdown system to flush flight deck sprinkling piping (see Item 32,Countermeasure Washdown System).

No visible harmful contaminants are detected.

Remove sprinkler nozzles during flush. Complete flush prior to installation of nozzles and operational test of system piping.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Counter-Meaure Washdown System
7155
Air
190 psi
95(F
Blow down each segment of each countermeasure zone with air. Prevent inadvertent operation of countermeasure control station by shutting firemain isolation valves.

Remove actuating and drain lines and blow down with air.

Unobstructed flow until clear discharge is attained.
When zone is complete, reconnect piping. Nozzles are not to be installed until after the associated piping is blown down.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Cargo Hold and Misc. OWT System

7156
Fresh

water 58 psig

(Bilge, MD designator) 72 psig

(oily waste transfer, OW designator)

95(F
Hydro piping with water and then air blow dry
Unobstructed flow. Blow down oily waste transfer system piping until no harmful contaminants are observed. For main drainage piping, this criterion need not be applied - impractical due to size of piping and pump suction strainers adequately protect system during subsequent operational testing.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
34
Cargo Potable Water System
7157
Water
Manifolds & fill lines:

200 psig

Pump discharge:

189 psig 113(F

113(F Operational test; use installed pumps. Clean potable water tanks, fill with FW and chlorinate to:

100 ppm min in tanks 50 ppm min. in system Flush system through each outlet.

After minimum concentrations is achieved in all legs of system, let stand for a min. of 4 hours. Flush clear with freshwater from tanks – take coliform samples.

Unobstructed flow, no visible contaminants.
Entry into potable water tanks is prohibited after disinfection.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

Aviation

F-44 Transfer and Service Systems

7158
T15 Hydraulic oil

148.4 psig

(transfer /purifier outside of tanks)

7.3 psig (transfer /purifier inside of tanks)

55.9 psig

(stripping outside of tanks

7.3 psig

(stripping inside of tanks) 113 (F 113 (F

Use flush rig and follow flow paths shown in associated work instructions bypassing service, transfer and stripping pumps. Also bypass aviation fuel service tank.
NAS Class 10
Thoroughly drain all piping at conclusion of flush.

Aviation Fuel Service Tank and Aviation Fuel Storage Tank to be hand wiped clean.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
Cargo Fuel Systems
7159
Seawater
200 psig
122 F
Visually ensure that suction piping is free of foreign matter for Main Cargo, Auxiliary and Stripping pumps.

Gravity fill each cargo oil tank with seawater.

Perform operational flush of system; utilize F-76/F-44 Main Cargo Transfer pumps, flush fill and transfer lines for each tank and recirculate back to same tank by opening Sta. nos. 3, 4, 5A, 7A during flush and jumpering stations together to complete flush loop that returns seawater back to tank via the 200 mm fill lines at Sta. 5A and 7A.

Use temporary pumps to empty seawater from cargo oil tanks when flush is complete.

Strainers shall be visibly free of foreign matter.
Wash down all cargo oil tanks after flushing is complete and pump down water and any residue with portable pumps.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments

36 (con’t)

Cargo Fuel Systems
7159
Seawater

Fresh water

Air 200 psig

87 psig

140 psig 122 F

122 F

122 F Utilize Aux. Cargo F-44 pumps to perform similar operational flush of smaller 65mm Sta. nos.3, 4 ,5 & 6, jumpering stations together and connecting to 65 mm flushing connections at Sta. 3 & 4 leading back to the slop tank.

Use temporary pumps to empty seawater from slop tanks when flush is complete.

Flush cargo oil monitor piping (bypassing CO monitor and pump).

Blowdown CO air piping.

Strainers visibly free of foreign matter

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
High Pressure Air System Diagram
7173
Air:

High Pressure

Low Pressure 3200 psig

110 psig 176(F

120(F

1. Piping hydrostatic test

2. Air blowdown

Compressor/Receiver Piping:

Blowout drains in piping and receiver until discharge is visibly free of moisture and foreign matter.

UNREP Ram Tensioner, Accomodation Ladders, Pilot Ladder Reels:

Blow out each air connection. Start at the Auxiliary Machinery Room and blow out through each air connection and drain to the air bank piping, bypassing the air bank charge station assembly.

Unobstructed flow until clear discharge is attained.
Bypass or remove filters and lubricators.

ITEM

System
Diagram
Flush Medium
Max. Pressure
Max

Temp

Suggested Setup
Cleanliness Criteria
Comments
38
Local Water Based Fire Extinguishing System
471-342-7174
Fresh water
Fire System:

241 psig

Distilled Water Tank Ppg:

50 psig

113(F
Directly flush from shore side water main, flushing piping from Pump/Section Valve -Unit connections (01-06) to nozzles. Nozzles must be removed during flush.

Also flush suction piping from distilled water tanks to pump suction.

Unobstructed flow. After a minimum of 10 minutes of water flow, strainers fitted at end nozzle connection in each branch run are to be visibly free of contaminants.
Pump/

Section Valve -

Unit should be bypassed during flush.

APPENDIX A

TURBULENT FLUSHING CHARTS

MINIMUM TURBULENT FLOWRATE FOR WATER (GPM)

Pipe Dia. (mm)
60(F
70(F
80(F
90(F
100(F
110(F
8
13 gpm
12 gpm
11 gpm
9 gpm
8 gpm
7 gpm
15
22
21
18
17
14
12
20
29
27
24
22
19
16
25
37
35
32
27
24
20
32
49
46
42
36
32
27
40
58
54
47
43
37
32
50
74
69
61
58
48
41
65
88
83
78
65
58
49
80
110
103
97
82
72
61
100
145
136
121
108
97
80
150
218
205
180
160
141
121
200
287
269
240
211
185
159
250
361
338
300
270
235
200
300
430
403
360
320
280
238

MINIMUM TURBULENT FLOWRATE FOR ISO 15 HYDRAULIC OIL (GPM)

Pipe Dia (mm)
100(F
120(F
140(F
160(F
15
25 gpm
17 gpm
13 gpm
10 gpm
20
38
25
19
14
25
51
33
25
19
32
63
42
32
24
40
76
50
38
29
50
101
67
51
38
65
127
83
63
48
80
152
100
76
57
100
203
133
101
76
150
304
200
152
114
200
405
266
203
152
250
507
333
253
190
300
608
399
304
228
350
709
466
355
266

MINIMUM TURBULENT FLOWRATE FOR ISO 32 HYDRAULIC OIL (GPM)

Pipe Dia. (mm)
100(F
120(F
140(F
160(F
15
20 gpm
14 gpm
10 gpm
7 gpm
20
30
21
15
10
25
41
28
20
14
32
51
35
25
18
40
61
42
30
21
50
81
56
41
28
65
101
70
51
35
80
122
84
61
42
100
162
112
81
56
150
243
167
122
84
200
324
223
162
112
250
405
279
203
139

MINIMUM TURBULENT FLOWRATE FOR ISO 46 HYDRAULIC OIL (GPM)

Pipe Dia (mm)
100(F
120(F
140(F
160(F
10
19 gpm
12 gpm
8 gpm
6 gpm
15
27
17
12
9

MINIMUM TURBULENT FLOWRATE FOR SAE 20 HYDRAULIC OIL (GPM)

Pipe Dia (mm)
100(F
120(F
140(F
160(F
15
38 gpm
22 gpm
16 gpm
10 gpm
20
57
33
24
15
32
95
55
40
25
40
114
66
47
30
50
152
89
63
41
100
304
177
127
81
200
608
355
253
162
250
760
443
317
203
350
1064
621
443
284

MINIMUM TURBULENT FLOWRATE FOR SAE 40 HYDRAULIC OIL (GPM)

Pipe Dia (mm)
100(F
120(F
140(F
160(F
15
108 gpm
60 gpm
35 gpm
22 gpm
20
161
90
52
33
32
269
150
87
55
40
323
180
104
66
50
431
241
139
89
100
861
481
279
177
200
1723
963
557
355
250
2153
1203
697
443
350
3014
1685
975
621

APPENDIX B

FME-MAN 48/60

ENGINE FLUSHING CLEANLINESS CRITERIA

APPENDIX C

CATERPILLAR EDG FLUSHING CLEANLINESS CRITERIA

APPENDIX D

YORK MARINE AB

BLOWING AND FLUSHING PROCEDURE

� EMBED Word.Picture.8 ���

B

B

PAGE

Dry Cargo / Ammunition Ship

T-AKE 1 Class Flushing Criteria and Guidelines

NAVSEA Dwg. No. 505-7488748

NASSCO Dwg. No. 471-342-7138, Rev. B Sheet 2

_1132552566.doc

_1132552825.doc

_1132553059.doc

_1132559660.doc

_1132552800.doc

_1132552398.doc

_1132552481.doc

_1132552520.doc

_1132552436.doc

_1132552319.doc

_1132552395.doc

_1132552345.doc

_1132552212.doc

_1132552285.doc

_1132550474.doc

File details come from the government source that posted it. Updated .