26R0037 Amendment 0005 REV.pdf

PDF 811 KB Posted

Attached to
N4008526R0037 P1574/P1591/P1592 MCB CAMP LEJEUNE
Solicitation number
N4008526R0037
Issued by

About this file

This is a Standard Form 30 Amendment to Solicitation N4008526R0037, a Design-Bid-Build contract for construction at Camp Lejeune, North Carolina, issued by NAVFACSYSCOM Mid-Atlantic Contracting Core. The amendment extends the proposal submission deadline from February 26, 2026, not later than 1400 EST to March 3, 2026, not later than 1400 EST (note: one reference indicates 2:00 EST). This extension is final. The contract Point of Contact is Simone Arrington at simone.m.arrington.civ@us.navy.mil or 757-341-1224.

The amendment modifies three key areas: (1) the Price Proposal Form with updated Government Estimated FF&E (Furniture, Fixtures and Equipment) costs of $350,245.07 for P1574 and $341,463.96 each for P1591 and P1592; (2) amended bid notes clarifying award procedures, option item availability within 365 calendar days post-award, bonding requirements, and Handling and Administration Rate (HAR) procedures capped at 5 percent for FF&E procurement; and (3) responses to Pre-Proposal Inquiries addressing specification clarifications on ASTM C923 gasketed connections (required), FF&E budget allocations by building, Air Barrier Inspector requirements, cost-loaded scheduling specifications, sustainability and commissioning requirements, and various technical questions on mechanical systems, electrical components, and specialty inspections. The Government confirmed it intends to award all three base projects (P1574, P1591, P1592), with electronic bid bond submission accepted and no phasing required across the three operational support facilities.

View the file

Other files

File Type Posted
Amendment 0009.pdf PDF
1748123Amendment0006_Specs_030326.pdf PDF
1748122Amend0006dwg_CIVIL_030326.pdf PDF
1717488Amend0006dwg_ARCHITECTURAL_030326.pdf PDF
1748122Amendment0006_Specs_030326.pdf PDF
1717488Amendment0006_Specs_030326.pdf PDF
1717488Amend0006dwg_STRUCTURAL_030326.pdf PDF
1717488Amend006dwg_CIVIL_030326.pdf PDF
1748123Amend006dwg_CIVIL.pdf PDF
1717488Amend0006dwg_ARCHITECTURAL.pdf PDF
1748122Amendment0006.pdf PDF
1717488Amendment0006.pdf PDF
Amendment 0008.pdf PDF
1717488Amendment0006_Specs.pdf PDF
1748122Amendment0006_Specs.pdf PDF
1717488Amend0006dwg_STRUCTURAL.pdf PDF
1748123Amendment0006_Specs.pdf PDF
1748123Amendment0006.pdf PDF
1717488Amend006dwg_CIVIL.pdf PDF
1748122Amend0006dwg_CIVIL.pdf PDF
1717488Amendment0006_Specs.pdf PDF
1748122Amendment0006_Specs.pdf PDF
1717488Amend006dwg_CIVIL.pdf PDF
1748122Amend0006dwg_CIVIL.pdf PDF
1717488Amend0006dwg_ARCHITECTURAL.pdf PDF
1717488Amend0006dwg_STRUCTURAL.pdf PDF
Amendment 0007_.pdf PDF
1748123Amendment0006_Specs.pdf PDF
1748123Amend006dwg_CIVIL.pdf PDF
26R0037 Amendment 0006 REV.pdf PDF
Revised PRICE SCHEDULE_P1574 P1591 P1592. 25 Feb 2026 (00A).docx DOCX document
Revised PRICE SCHEDULE_P1574 P1591 P1592. 19 Feb 2026.docx DOCX document
26R0037 Amendment 0004 1 1(REVIEWED JB).pdf PDF
PRICE SCHEDULE BLANK.docx DOCX document
Notice of Intent -Manufacturer Brand Name.pdf PDF
26R0037 Amendment 0003 (AutoRecovered).pdf PDF
26R0037 Amendment 0002(FINAL).pdf PDF
Amendment 0001.pdf PDF
B_1748123spc01of01_1592.pdf PDF
A_1748122dwg01of01_COMBINED_1591.pdf PDF
B_1748122spc01of01_1591.pdf PDF
A_1748123dwg01of01_COMBINED_1592.pdf PDF
PPI Form.xlsx XLSX spreadsheet
B_1717488spc01of01_1574.pdf PDF
Attachment H - PIEE Vendor Access Ins..pdf PDF
WD NC260010.pdf PDF
MACC Coversheet Final.docx DOCX document
C_1717488_1748122_1748123_Hazardous Material Report_RTA.pdf PDF
A_1717488dwg01of01_COMBINED_1574.pdf PDF
PRICE SCHEDULE-BLANK.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID

CODE

PAG

E

OF PAGES

J 1 2

2. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE PROJECT NO. (If applicable) 0005 25-Feb-2026

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.)

Code

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

9A. AMENDMENT OF SOLICITATION NO.

N4008526R0037

9B. DATED (SEE ITEM 11)

25-Feb-2026

10A. MODIFICATION OF

CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N4008526R0037, DESIGN-BID-BUILD, CAMP LEJEUNE, NORTH CAROLINA

The proposal due date of 26 February 2026 NLT than 1400 (EST) has hereby been extended to 03 March 2026 NLT 1400 (EST). This extension is final.

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Simone Arrington; Email: simone.m.arrington.civ@us.navy.mil; Office Phone: 757-341-1224

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE

SIGNED

16B. UNITED STATES OF AMERICA 16C. DATE

SIGNED

B Y

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30

(REV.1-83)

0224-3(10-90)

PREVIOUS EDITION

UNUSABLE

Prescribed by GSA

N40085-26-R-0037

SF 30 BLOCK 14 CONTINUATION PAGE

The purpose of this amendment is to provide the following:

1. Amendment to the Price Proposal Form

2. Provide Remaining Responses to Pre-Proposal Inquiries and provide clarification/corrections to previous responses

3. Extend Proposal Submission Deadline to 03 March 2026 NLT 2:00 EST This Extension is Final.

ATTACHMENTS:

The following information has been deleted and/or added/revised:

BLANK PRICE PROPOSAL FORM

1. Line items 0015-0017 The Government Estimated FFE is:

$341,463.96 for P1591, & P1592 $350,245.07 for P1574

2. Bid Note(s) amended to include the following in RED:

General Bid Notes:

1. Award will be made on the total sum of Contract Line Items CLINs) 0001-0004. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

2. The Government reserves the unilateral right to award CLINs 0006, 0007, 0010, 0011, 0013 and 0014 to the Contractor at the proposed price within 365 calendar days after the contract award. CLINs 0005, 0008, and 0012 may only be awarded at time of contract award. A firm fixed proposed price is required for CLINs 5, 7, 8, 11, 12, and 14. No provision is made for economic price adjustment. FAR 52.217-5, Evaluation of Options (Jul 1990) - Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interest, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

3. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

FF&E & AV Bid Notes

These notes apply to CLINs 0007, 0011, 0014, 0015, 0016, and 0017

1. The estimated amount for FF&E has been supplied by the Government, to provide offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the FF&E including freight and installation charges. The Government FF&E Estimate is only an estimated amount.

2. If awarded, line items will be funded separately after completion of FF&E design package review by the Government, and receipt of appropriate funding by the Government. Requirements and details are provided in Specification 12 00 01.00 20 Furniture, Fixtures and Equipment (FF&E) Package.

3. Bonding

i. No Bonding for FFE at Time of Construction Contract Award

FAR 28.102-1(a) requires that performance and payment bonds be included in all construction contracts exceeding the SAT, except under the conditions listed. Since the FF&E is not part of the original contract award, the Construction Contractor must not be required to secure bond for the FF&E at the time the basic contract is awarded

ii. Additional Bond at FF&E Option Item Award

FAR 28.102-2(d) requires the Government to secure additional bond from the Construction Contractor for any contract price increases. Therefore, an increase to the original contract bond is required at the time of the FF&E Option Items award, to protect the Government against the Construction Contractor not providing FF&E ordered and to ensure that the vendor(s) receive payment if the Construction Contractor goes out of business. The increased cost of the bond must come from the FF&E funding source and is not a part of the Construction Contractor’s HAR.

iii. Bonds Required by the Construction Contractor

If the Construction Contractor requires bonding from the FF&E subcontractor(s), the cost must be covered in the Construction Contractor’s HAR.

4. Offerors may propose a Handling and Administration Rate (HAR) for the FF&E not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E. The Contractor’s proposed HAR percentage will be incorporated into the contract award and will not be adjusted regardless of fluctuations from the estimate amount for the FF&E. The proposed HAR is a fixed rate.

5. The Government is not obligated to award the Option line item(s). Should the Government choose to award CLINs 0007, 0011, 0014, 0015, 0016, and/or 0017, the line items will be awarded as a negotiated modification to the contract/task order.

The Government reserves the unilateral right to award CLINs 0007 and 0015 within 180 days after the contact award and CLINs 0011, 0014, 0016 and CLIN 0017 prior to the last six months of the contract completion date. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E.

6. The Government is not obligated to award the FF&E and A/V line items. Should the Government choose to award the FF&E and A/V, the line items will be awarded as a negotiated modification to the contract/task order. The contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E and A/V. The FF&E and A/V modifications shall be awarded at least six months prior to the contract completion date. A minimum of six months is required for the contractor to purchase, deliver and install the FF&E and A/V without impacting the overall completion date of the project. The contractor’s schedule should assume the award of the FF&E and A/V as a modification. No schedule extensions shall be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contract completion date, the contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the prime contractor demonstrates that accepted Final FF&E and A/V packages were submitted within the approved schedule deadlines and sufficient lead time for the FF&E and A/V is not available and the Government’s award of the modification is in the last six months of the contract.

FINAL PPI LOG:

Updated Responses:

2/11/26 General Bid Note #2

General Bid Note #2 states Government reserves the right to award CLINS 5-17 within 365 days after the award of contract. Can the Government concur the contractor will be fully compensated for all costs for any remobilization, demolition of any work in place and rework to accommodate the added tasks?

No, please bid per RFP.

Additionally, Amendment 0005, includes an updated price proposal form. See Attached.

2/12/26

The precast manufacturer will not price the structures if ASTM C923 standard requiring gasketed connections at all storms drain structures. Please confirm this standard will not be required.

Gasketed connections are required. Spec section 33 40 00 2.4.3 requires ASTM C923. Without historical knowledge of the project, watertightness may be needed to limit infiltration into the system (high groundwater). There is a portion of storm that runs directly under a sand filter, which may be triggering this need. Specifying ASTM C923 ensures the system is durable and reliable, and has a lower cost of ownership over its lifespan.

2/12/26 33 30 00: 2.2.3 & 33 40 00: 2.4.3

Please consider removing the ASTM C923 requirement as some of our precast providers are refusing to quote the project if this is truly required.

No amendments will be made for these requirements.

1/28/26 MACC Coversheet

Final Bond Requirements

The instructions state that a hard copy of the bid bond must be submitted within three (3) days after the date and time of receipt of proposals. Please confirm whether an electronic copy of the bid bond submitted with the bid package is acceptable, or if an original hard copy is strictly required. If an original hard copy is required, we request consideration of extending the submission window to five (5) days. This additional time would provide reasonable leeway in the event of inclement weather or unforeseen mail delivery delays, while still ensuring timely receipt.

An electronic copy is acceptable

1/29/26 Bid Form Line items 0015 0016 0017 are these for each building separate?

Provide price for FFE separately for each building. Use 0015 for P1574; 0016 for P1591; 0017 for P1592. See updated Price Proposal Form.

1/29/26 Bid Form what is the value of the FFE budget for each building? See updated Price Proposal Form.

1/29/26 Bid Form Line item 0004 is just the demo bid for all 3 sites? It is not to be included int the base bid.

Provide the demolition work for all three projects as a separate CLIN (CLIN 0004), which will be included in the award Base Price.

2/4/26 01 4500 QC will the QC specialist listed in 1.6.5 be required for this contract?

Yes, the QC specialists are required.

2/10/26 Bid form Do we add the three unit prices to the Base bid for each building

Yes, provide unit prices as shown for each base bid.

2/4/26 72710 will the air barrier inspector listed in 1.7 be required for this contract?

Yes, provide Air Barrier Inspector as described in section 072710.0010.

2/10/26 Drawing CD102 P1591 Drawings CD102 note 18 "Refer to electrical demo plans P1574/P1591" There is no demo plan with P1591 drawings, please advise?

There is electrical demolition work on sheet ES101 in the P1591 drawings.

2/10/26 Can the Government provide As-Builts for all structures be demolished?

No as-builts are available for this site.

2/10/26 12 00 01.00 20 3.1.2.8 Final FF&E Mock up. Are FF&E mock ups required for any or all of the buildings. If required can there be one mock up for all three buildings.

Each furniture manufacture must have a mock up to include all details in Technical Specification Div 12, 3.1.2.8.

Integration of communication lines and quality of constuction and appropriate finishes will be the focus of the mock up. If these aspects are the same for multiple buildings, then one mock up is acceptable. If there are ANY differences in comm lines or finishes among buildings, each building will require a mock up.

A mock up may be presented in a generic location to be submitted for multiple builings if the same manufacturer product and finishes are to be used. If mock up is accepted, it may be used in the final building or deconstructed.

2/10/26 Price schedule P1574: Do not see a CLIN for the preparation of the FF&E Package as noted in spec section 12 00 01.00 20. Will this be part of the lump sum of the base bid?

Cost of the preparation of the FF&E Package as noted in spec section 12 00 01.00 20 must be included in the base bid.

2/10/26 Price schedule P1591: Do not see a CLIN for the preparation of the FF&E Package as noted in spec section 12 00 01.00 20. Will this be part of the lump sum of the base bid?

Cost of the preparation of the FF&E Package as noted in spec section 12 00 01.00 20 must be included in the base bid.

2/10/26 Price schedule P1592: Do not see a CLIN for the preparation of the FF&E Package as noted in spec section 12 00 01.00 20. Will this be part of the lump sum of the base bid?

Cost of the preparation of the FF&E Package as noted in spec section 12 00 01.00 20 must be included in the base bid.

2/10/26 12 00 01.00 20 P1574: 3.1.2.11 Final FF&E, Please confirm that no hardcopy binders are required and only digital binders are required.

Hard copies and electronic copies are required as per technical spec section 12 00 01.00 20 paragraph 3.1.2.10 and 3.1.2.11 within FFE Meetings, presentaitons, and submittals for the interior design services.

2/10/26 12 00 01.00 20

P1591: 3.1.2.10 & 3.1.2.11 PreFinal FF&E Please confirm the number of binders that are required for Prefinal and Final Submittals. 3.1.2.11 is titled Prefinal, Please verify this is intended to be Final.

As per Div 12 00 01.00 20 paragraph 3.1.2.10, provide FIVE electronic copies to the specified recipients for Pre-Final FF&E Package Submittal. As per Div 12 00 01.00 20 paragraph 3.1.2.11, provide FOUR electronic copies to the specified recipients for Final FF&E Package Submittal. Paragraph

3.1.2.11 Heading should read

"Final FF&E Package Submittal". All mentions of "Pre-Final FF&E" in Paragraph

3.1.2.11 should also read "Final

FF&E"

2/10/26 12 00 01.00 20

P1592: 3.1.2.10 & 3.1.2.11 Please confirm the number of binders that are required for Prefinal and Final Submittals.

3.1.2.11 is titled Prefinal, Please verify this is intended to be Final

As per Div 12 00 01.00 20 paragraph 3.1.2.10, provide FIVE electronic copies to the specified recipients for Pre-Final FF&E Package Submittal. As per Div 12 00 01.00 20 paragraph 3.1.2.11, provide FOUR electronic copies to the specified recipients for Final FF&E Package Submittal. Paragraph

3.1.2.11 Heading should read

"Final FF&E Package Submittal". All mentions of "Pre-Final FF&E" in Paragraph

3.1.2.11 should also read "Final

FF&E"

2/10/26 12 00 01.00 20

P1574, P1591 & P1592 all have separate spec sections. Can any of the meetings be combined since it apprears all the FF&E is the same

The representative for the three builidings will be the same person therefor the three buildings may be presented at the same time for all the FFE meetings and requirements if it aligns with the GCs construction schedule. See Price Schedule- FF&E & AV Bid Note # 5 for anticipated award dates of FF&E packages. P1574 Design package will need to be completed, bid, BVD, and finalized no later than July 2026.

2/10/26 Price Schedule

CLIN 0015 Please provide Government Estimated FF&E Price. Please verify this CLIN is for P1574. Please verify this is for P1574 only.

See updated Price Proposal Form. Provide price for FFE separately for each building. Use CLIN 0015 for P1574

2/10/26 Price Schedule

CLIN 0016 Please provide Government Estimated FF&E Price. Please verify this CLIN is for P1591. Please verify this is foe P1591 only.

See updated Price Proposal Form.. Provide price for FFE separately for each building. Use CLIN 0016 for P1591

2/10/26 Price Schedule

CLIN 0017 Please provide Government Estimated FF&E Price. Please verify this CLIN is for P1592. Please verify this is foe P1592 only.

See updated Price Proposal Form. Provide price for FFE separately for each building. Use CLIN 0017 for P1592

2/11/26 Sheet C-005

Sheet C-005 shows a small laydown area on the north side of West Glove Rd.

A. Is there any additional laydown sites available near the project site? B. At any laydown area outside of the actual project site, the contractor will have to install a durable traffic surface. At the completion of the project will these areas have to be restored to pre-construction conditions?

A. Sheet C-005 indicates the laydown areas that have been provided for the project.

B. All offsite areas disturbed by construction, including the laydown area, must be restored to pre-construction conditions.

2/11/26 FF&E/AV Bid Notes #6

Six months seems a bit short for the entire FF&E process from start to completion of installation and punchlist. Can the time frame be lengthened/extended?

The GC will be authorized to begin design of the FFE package at construction kick off. This cost is included in the base bid.

Once the package is completed, if funding is available and ClIN option is awarded, it will be awarded to the GC for FFE procurement and installation at LEAST six months prior to CCD as per tech spec 12 00 01.00 20, paragraph 1.3.1d. A milestone schedule will be discussed at Construction KO/ID Orienation meeting which should align the FFE time line with the CCD. See Price Schedule- FF&E & AV Bid Note # 5 for anticipated award dates of FF&E packages. P1574 Design package will need to be completed, bid, BVD, and finalized no later than July 2026.

2/11/26 12 00 01.00 20

General question involving FF&E Packages, Each building has a separate spec sections for the FF&E packages, Will the three buildings be combined into one bid package or will each building be bid separately?

Each building will be a separate bid package as they are separate CLINs. Funding will need to be approved/obligated for each building's FFE package seperately. Fiscal years for each building may vary due to delays in construction.

2/11/26 12 00 01.00 20

Will the FF&E for the three buildings be installed consecutively

This is not a requirement of the contract. Milestones will be provided by the GC at the construction KO meeting but may change due to construction delays.

2/12/26 is it the governments intent to award all three projects. Yes

2/12/26 please confirm that if borrow source is selected that is a commercial entity from which soil material is directly purchased no analytical testing testing will be required per spec 31 00 00 par 3.2.1

All material brought from off- Base must have an Imported Fill Management Plan for review and approval per 01 57 19, Section

1.5.1.1.2 Imported Fill or Offsite

Soil. Will clarify by Amendment.

2/12/26 32 13 13.06

Section 1.3.4.2 Field Technicians - Will this be required for the concrete paving. This is not typical.

Yes

2/12/26 Is ½ inch conduit allowed on this project? Base usually does not allow this

½-inch conduit is acceptable for lighting and power circuits in accordance with specification section 26 20 00, paragraph 3.1.3

2/12/26 Is MC Cable allowed for 6ft lighting whips? MC cable is not permitted for 6-foot lighting fixture whips.

Provide flexible metal conduit (FMC) for these connections instead.

2/12/26 01 32 17 Spec Section 01 32 17 for P1574, P1591 and P1592 requires the contractor to provide a Cost-Loaded Network Analysis Schedule (NAS) for this project and that the purpose of the Cost-Loaded NAS is to report progress, evaluate time extensions, and provide the basis for progress payments.

Spec Section 01 20 00, Paragraph 1.3.1 for P1574, P1591 and P1592 further clarifies that a Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). A Cost-Loaded Network Analysis Schedule will be extremely expensive for the contractor to produce and update on monthly basis. Historically, the use of Cost-Loaded Network Analysis Schedules have not provided any value-added benefits to the Government or the Contractor on projects of this type. They only add another layer of complexity to complex MILCON projects. Also, the Government will have to appoint their own qualified scheduler to the project who is proficient in Primavera P6 just to analyze the Contractor’s Cost-Loaded NAS for justification of monthly progress payments from the Government to the Contractor. Can the requirements for the contractor-provided Cost-Loaded Network Analysis Schedule (NAS) and Earned Value Report be changed to a Non-Cost-Loaded Network Analysis Schedule and a Schedule of Prices by amendment?

Specifications must be followed.

2/12/26 01 30 00 Para 1.4 Spec Section 01 30 00, Paragraph 1.4 for P1574, P1591 and P1592 requires the contractor to provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in file format showing the sequence and progress of work. However, contractor personnel are prohibited from taking any pictures within the MARSOC compound area.

Can the requirement for monthly progress pictures be removed from the project by amendment?

No.

2/12/26 01 31 23.13 20 Spec Section 01 31 23.13 20 for P1574, P1591 and P1592 requires the contractor to utilize the Naval Facilities Engineering Systems Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents for the project. eCMS is a web-based program that should be available for the Government’s and Contractor’s use during the project’s normal working hours of 7AM to 3:30PM.

However, eCMS continues to have ongoing technical difficulties that cause the program to be periodically unavailable for use during normal working hours for the Government and the Contractor. In addition, there is no sense of urgency by the eCMS technical support team to restore service to eCMS when support tickets are submitted to them by contractor personnel. Can it be confirmed by Amendment that eCMS will be functional during normal working hours for this project after award?

Per eCMS POC: Please refer to the alternative submittal procedures including the specifications for periods when eCMS is not available. There's no way to predict or guarantee the availability of the application. 1.1

CONTRACT

ADMINISTRATION

Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional, or specifically requested in addition to electronic submission.

2/12/26 01 33 29 Spec Section 01 33 29 for P1574, P1591 and P1592 requires that the contractor provide sustainability documentation and reporting submittals per the federally mandated High Performance and Sustainable Buildings (HPSB) or HPSB "Guiding Principles" (GP). However, Executive Order 14154 (Unleashing American Energy) eliminated the mandatory requirement for High Performance and Sustainable Buildings via the elimination of Executive Orders EO14030 (Climate-Related Financial Risk), EO 14057 (Catalyzing Clean Energy Industries and Jobs Through Federal Sustainability) and EO 14082 (Implementation of the Energy and Infrastructure Provisions of the Inflation Reduction Act of 2022). These Executive Orders can be accessed at https://www.federalregister.gov/documents/2025/01/29/2025- 01956/unleashing-american-energy . Also, this requirement adds unnecessary costs to the project that have no value-added benefits? Can the requirements for Spec Section 01 33 29 be removed from the project by Amendment since this requirement is no longer mandatory?

No. Compliance with UFC 1- 200-02 was not eliminated. These requirements have their basis in law, as indicated in the executive order. EO 14154 (1/29/25) states:

"Sec. 2. Policy. It is the policy of the United States: ...(d) to ensure that all regulatory requirements related to energy are grounded in clearly applicable law"; "Sec. 3.

Immediate Review... (a) The heads of all agencies shall review all existing regulations," (UFC 1-200-02 c3 was published after EO 14154. No changes would have affected this project.) None of the cited EO's are in conflict with legal requirements for energy savings based on life-cycle cost effectiveness. All sustainability requirements for the project were subject to being life-cycle cost effective during the design process. The contract documents must be complied with.

2/12/26 01 45 00 Para 1.6.4 Spec Section 01 45 00, Paragraph 1.6.4 for P1574, P1591 and P1592 requires that the contractor provide Commissioning (Cx) in addition to the quality control requirements of this section and not as a substitute for quality control requirements. However, Spec Section 01 91 00, Paragraph

1.1 indicates that Government has hired an independent Commissioning Firm for the project. Can it be confirmed by Amendment that the requirements for Total Building Commissioning is the Government’s responsibility?

Commissioning is a process that must be accomplished as a Team.

Commissioning activities required of each member of the Cx Team (including the KTR, the Government hired Cx provider, the DOR and the Government's technical representatives) are assigned in UFGS 01 91 00.15 22 Total Building Commissioning.

An ammendment will be provided modifying UFGS 01 45 00 article 1.6.4 second paragraph sentence "Provide Cx in addition to the quality control requirements of this section and not as a substitute for quality control requirements." will be corrected to: "Provide Cx activities assigned in UFGS 01 91

00.15 22. Cx activities are in addition to the quality control requirements of this section and are not a substitute for quality control requirements."

2/12/26 07 05 23 07 27 10 07 27 26

Spec Sections 07 05 23, 07 27 10 and 07 27 26 for P1574, P1591 and P1592 require the contractor to provide an Air Barrier System and associated testing for the (3) new facilities required for the project. However, Executive Order 14154 (Unleashing American Energy) eliminated the mandatory requirement for High Performance and Sustainable Buildings via the elimination of Executive Orders EO14030 (Climate-Related Financial Risk), EO 14057 (Catalyzing Clean Energy Industries and Jobs Through Federal Sustainability) and EO 14082 (Implementation of the Energy and Infrastructure Provisions of the Inflation Reduction Act of 2022). These Executive Orders can be accessed at https://www.federalregister.gov/documents/2025/01/29/2025- 01956/unleashing-american-energy . Also, the additional costs to provide and install the required air barrier system will far exceed the cost savings achieved via energy efficiency over the total life cycle of these (3) facilities. Can the air barrier requirements for Spec Sections 07 05 23, 07 27 10 and 07 27 26 removed from the project by Amendment since this requirement is no longer mandatory?

No. Compliance with UFC 1- 200-02 was not eliminated. These requirements have their basis in law, as indicated in the executive order. EO 14154 (1/29/25) states:

"Sec. 2. Policy. It is the policy of the United States: ...(d) to ensure that all regulatory requirements related to energy are grounded in clearly applicable law"; "Sec. 3.

Immediate Review... (a) The heads of all agencies shall review all existing regulations," (UFC 1-200-02 c3 was published after EO 14154. No changes would have affected this project.) None of the cited EO's are in conflict with legal requirements for energy savings based on life-cycle cost effectiveness. All sustainability requirements for the project were subject to being life-cycle cost effective during the design process. The contract documents must be complied with.

2/12/26 09 97 13.27 Spec Section 09 97 13.27 for P1574, P1591 and P1592 references a requirement for HIGH PERFORMANCE COATING FOR STEEL STRUCTURES which requires the coating contractor to be SSPC QP1 certified? It is our understanding this requirement is only applicable exterior steel structures. Is our assumption correct?

Yes. 09 97 13.27 Para 3.2 states:

"Coat exterior surfaces of structure including steel roof, shell, legs, stair, railing, and other exterior appurtenances.

Refer to Section 09 96 00 HIGH-

PERFORMANCE COATINGS,

SUMMARY, for additional areas requiring high-performance coatings for steel, EXTERIOR

HIGH-PERFORMANCE

COATING SCHEDULE, and

INTERIOR HIGH

PERFORMANCE SCHEDULE"

2/12/26 12 00 01 Para 1.1 Spec Section 12 00 01, Paragraph 1.1 for P1574, P1591 and P1592 states that the Government will indicate the FF&E estimate in the FF&E Option Item in the Price Schedule based on the Concept FF&E Design. However, the FF&E estimate has been omitted from Project RFP Price Schedule.

Can the FF&E estimate(s) for the (3) Facilities be provided by Amendment?

Government estimated FF&E will be provided by Amendment which will be $350,245.07 for P1574, $341,463.96 for P1591 and $341,463.96 for P1592 . In addition, changes have been made to FFE&AV Bid Notes #5, and General bid notes #2. SEE

REVISED PRICE SCHEDULE.

2/12/26 CLIN Option 0007 CLIN Option 0011 CLIN Option 0014

CLIN Option Items 0007, 0011, 0014 on the Project Price Schedule states for the contractor to provide the Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications for the (3) facilities for the project. However, there is no Specification Section or budget for the required A/V equipment for the project. The project drawings for P1574, P1591 and P1592 only indicate the rough in locations for the A/V Equipment in the event that CLIN Option Items 0007, 0011, 0014 are awarded. Can the Specifications for the A/V equipment that may be required for the project be provided by Amendment?

The AV specification section is provided in 01 30 02.00 22. This section was included in P1591 and P1592, but omitted from P1574. The section also applies to that project. AV equipment to be installed is included in the TA series sheets.

2/12/26 13 34 19 Para 3.6 Spec Section 13 34 19, Paragraph 3.6 for P1574, P1591 and P1592 states for the contractor to conduct Special Inspections per structural steel inspections as indicated in the Schedule of Special Inspections. The only special inspections that will need to be performed on site are for inspection and documentation of the Bolted Connections for the Pre-Engineered Metal Building (PEMB) Components.

All welding of the required structural components for (3) PEMB’s will be performed offsite by the PEMB Manufacturer during fabrication process at the PEMB factory. Can the special inspection requirements for (3) PEMB’s be removed from the project by Amendment?

No, special inspections requirements can not be removed. Refer to Schedule of Special Inspections and the material specifications for Special Inspection requirements.

2/12/26 Will all Base Bids be awarded for this project? If so, please define how the time for completion should be addressed for each Base bid.

Yes, each operational support facility (OSF) does not have a specific need-by date, only the total project completion date is of importance.

2/12/26 Bldg P1574 on the mechanical legend (M001) it shows that a T circled is a thermostat but there is no reference to what a TH circled is ( both being referenced on MP101 ) ( my gut is telling me TH refernces thermostat ) If im correct then what does the T stand for?

T - Thermostat TH - Thermostat and Humidistat

2/12/26 Sheet PP102 shows 2 Gas Meters ( one outside building and one inside building) Why the two meters? and is it the contractors responsibility to install any gas meters

Contractor's responsibility to install the gas meter in the mechanical room.

2/12/26 Sheet MH102-C mirrors sheet MH102 Please identify the options on MH102-C

MH102-C is showing the bid option roof section above 123 Storage. In the Key Plan, section C of the building is present.

2/12/26 Sheet MH401-C mirrors sheet MH401 Please identify the options on MH401-C

MH401-C is showing ductwork going to 123 Storage room and that the wall on the plan east side of the mechanical room is not an exterior wall.

2/12/26 Will the contractor be responsible for permits? Provide all permits indicated by the Specifications. NCDEQ Erosion and Sediment Control, Stormwater and Water permits will be obtained prior to construction. Approval letters will be provided by Amendment.

2/12/26 Will power and water be available onsite, and will it be the contractors responsibilty for monthly fees?

Yes. Contractor will be responsible for monthly fees associated with their power and water usage.

2/12/26 Is this project to be phased per building? Project has no phasing.

2/12/26 01 30 00 Specs require 20 photos/week from ≥10 viewpoints and monthly submittals on CD/DVD. Can we instead provide monthly photo deliverables via eCMS or secure file share to avoid optical media?

The awarded contractor will be required to attend a security briefing with MARSOC Security prior to the commmencement of any construction activities.

Photos are typically uploaded to eCMs.

2/12/26 Can the Superintendent also serve as QC Manager on this project? If yes, please confirm minimum qualifications and whether the Government intends to approve a dual‑hat staffing plan.

The Superintendent may not serve as the QC Manager.

2/12/26 01 20 00 Confirm if TAB Season I testing will occur before BOD and Season II after BOD.

If all testing can happen before BOD that is preferable. 23 05

92.00 22 Appendix C outlines the requirements.

2/12/26 Does this project require commisioning? Yes.

2/12/26 Confirm the scope/interface between Div‑27, whether NMCI/USMC will furnish any network electronics, or if we furnish all passive only.

Base communications office will provide switches. contractor will provide all equipment shown on sheet TT502.

2/12/26 Section 07 05 23 mandates whole‑building air‑tightness testing. Please confirm the required allowable leakage rate, and whether an interim test is required prior to finishes.

Building air leakage rate not exceeding 0.25 cfm/ft2 under a pressure differential of 0.3 inches of water. Refer to specification 07 05 23 section 3.3 for testing guidance. Interim testing before the final test is not required.

2/12/26 Confirm whether any existing facilities to be impacted contain lead or PCB‑containing ballasts/mercury lamps.

Building RR515 contained four

(4) fluorescent light fixtures with a total of 8 T8 mercury containing lamps. Building SRR514 contained six (6) fluorescent light fixtures with a total of 18 T8 mercury containing lamps. T8 fluorescent fixtures use electronic ballasts.

2/12/26 Confirm whether Boiler 121 and/or Mechanical 122 require 1‑hr fire barriers and self‑closing doors

Per the Life Safety drawings, only the interior walls of Boiler 121 requires a 1-hr fire barrier.

Per the door schedule and door hardware spec, the doors for Boiler 121 and Mechanical 122 are specified to be provided with closers.

2/12/26 Will this project require formal partnering meetings? Provide partnering as indicated in Section 01 30 00, Section 1.9.

2/4/26 P1574 Drawing

AE541

1. Detail C1; Keynote #3: request to move the 1/8” silicone sealant to the floor of the shower pan floor. at bottom of panel. This will reduce construction costs in the field and the cost of manufacturing.

2. A1; detail 16: Request to eliminate concrete curb with backerboard to reduce construction cost in the field.

3. A1, A2: Request to use a FRP perimeter 3/8” (thin) flange

vs. the full ½” thick Corian as the flange to reduce construction costs in the field.

4. C1, A1 & A2, Detail #10: request to remove cove perimeter and have the wall panel go straight to the floor;

allow the FRP flange to free-float between the studs and the ½” Corian Linen decorative panel.

1. Provide 1/8" silicone sealant as directed by drawings

2. Provide concrete curb as specified

3. Provide 1/2" corian flange as specified

4. Install all components as specified

2/4/26 P1591 Drawing

AE541

1. Detail C1; Keynote #3: request to move the 1/8” silicone sealant to the floor of the shower pan floor. at bottom of panel. This will reduce construction costs in the field and the cost of manufacturing.

2. A1; detail 16: Request to eliminate concrete curb with backerboard to reduce construction cost in the field.

3. A1, A2: Request to use a FRP perimeter 3/8” (thin) flange

vs. the full ½” thick Corian as the flange to reduce construction costs in the field.

4. C1, A1 & A2, Detail #10: request to remove cove perimeter and have the wall panel go straight to the floor;

allow the FRP flange to free-float between the studs and the ½” Corian Linen decorative panel.

1. Provide 1/8" silicone sealant as directed by drawings

2. Provide concrete curb as specified

3. Provide 1/2" corian flange as specified

4. Install all components as specified

2/4/26 P1592 Drawing

AE541

1. Detail C1; Keynote #3: request to move the 1/8” silicone sealant to the floor of the shower pan floor. at bottom of panel. This will reduce construction costs in the field and the cost of manufacturing.

2. A1; detail 16: Request to eliminate concrete curb with backerboard to reduce construction cost in the field.

3. A1, A2: Request to use a FRP perimeter 3/8” (thin) flange

vs. the full ½” thick Corian as the flange to reduce construction costs in the field.

4. C1, A1 & A2, Detail #10: request to remove cove perimeter and have the wall panel go straight to the floor;

allow the FRP flange to free-float between the studs and the ½” Corian Linen decorative panel.

1. Provide 1/8" silicone sealant as directed by drawings

2. Provide concrete curb as specified

3. Provide 1/2" corian flange as specified

4. Install all components as specified

*** Orange indicates updates to previous PPI(s)