Amend 0005.pdf
PDF 1 MB Posted
- Solicitation number
- N4008525R9023
About this file
This document is an Amendment of Solicitation/Modification of Contract for a BEQ Chiller Repairs MCAS New River project at Camp Johnson and Rifle Range. Amendment 0005 extends the proposal due date to September 16, 2025 at 3:00 PM EDT and addresses three key contractor questions:
- Factory disconnects are confirmed as required for new chillers. 2. Warranty specifications were clarified to ensure all new chillers, regardless of heat exchanger type, receive a 10-year comprehensive warranty covering parts, labor, and refrigerant. 3. As-built equipment schedules were referenced for contractors to verify field measurements, with the understanding that contractors are responsible for final field verification. The solicitation is issued by NAVFAC Mid-Atlantic, Resident Officer in Charge of Construction, located in Camp Lejeune, NC, with the project number 25-0440.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N40085-25-R-9023 Amendment 0005
CONTINUATION SHEET
1. QUESTION: Are factory disconnects required on the new chillers?
ANSWER: Yes, factory disconnects are required.
2. QUESTION: Warranty specifications only appear to pertain to chillers with Brazed Plate Heat Exchangers. Please confirm warranty requirements for all chillers?
ANSWER: All New Chillers, no matter the type of heat exchanger, must have a 10-year parts, labor, and refrigerant warranty the for the entire chiller.
3. QUESTION: Can as built schedules be sent out for the existing buildings so pumps and chillers can be sized to design instead off nominal tonnages
ANSWER: See the attached schedules for the equipment. It is the responsibility of the contractor for field verification.
4. All other terms and conditions remain unchanged.