This document is an Amendment of Solicitation/Modification of Contract for a BEQ Chiller Repairs MCAS New River project at Camp Johnson and Rifle Range. Amendment 0005 extends the proposal due date to September 16, 2025 at 3:00 PM EDT and addresses three key contractor questions:

  1. Factory disconnects are confirmed as required for new chillers. 2. Warranty specifications were clarified to ensure all new chillers, regardless of heat exchanger type, receive a 10-year comprehensive warranty covering parts, labor, and refrigerant. 3. As-built equipment schedules were referenced for contractors to verify field measurements, with the understanding that contractors are responsible for final field verification. The solicitation is issued by NAVFAC Mid-Atlantic, Resident Officer in Charge of Construction, located in Camp Lejeune, NC, with the project number 25-0440.

View the file

Other files

File Type Posted
AS4035.pdf PDF
Amend 0007.pdf PDF
Amend 0006.pdf PDF
RR-143-1.pdf PDF
M447.docx DOCX document
AS4030.PDF PDF
AS4208.pdf PDF
M446.pdf PDF
M448.docx DOCX document
AS4015.pdf PDF
AS4006-4007.pdf PDF
RR143.pdf PDF
AS4207.pdf PDF
M435.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
250443 SOW.pdf PDF
250437 Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
250443 Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
250437 25M061CN BEQ Chiller Repairs Phase II-MCAS New River PD.pdf PDF
25 0443 SPEC 23 24 00 - HYDRONIC PIPE CLEANING AND FLUSHING PROCEDURES.pdf PDF
250443Combined DIV 01 specs small projects.pdf PDF
250443 25M064CN BEQ RR143 Chiller Repairs PD.pdf PDF
250436 25M060CN BEQ Chiller Repairs-MCAS New River SR.pdf PDF
250436 25M060CN BEQ Chiller Repairs-MCAS New River PD.pdf PDF
250443 25M067CN BEQ Chiller Repairs Camp Johnson SR.pdf PDF
25-0437 SOW.pdf PDF
250436 SPEC 23 24 00 - HYDRONIC PIPE CLEANING AND FLUSHING PROCEDURES.pdf PDF
Amend 0002.pdf PDF
250437 25M061CN BEQ Chiller Repairs Phase II-MCAS New River SR.pdf PDF
250437 SPEC 23 24 00 - HYDRONIC PIPE CLEANING AND FLUSHING PROCEDURES.pdf PDF
250436 Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
250436 Combined DIV 01 specs small projects.pdf PDF
250437 Combined DIV 01 specs small projects.pdf PDF
250436 SOW.pdf PDF
Amend 0001.pdf PDF
Combined_D01_specs_small_projects.pdf PDF
25-0440 SOW.doc.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
SPEC 23 24 00 - HYDRONIC PIPE CLEANING AND FLUSHING PROCEDURES.pdf PDF
25M064CN BEQ RR143 Chiller Repairs SOW.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N40085-25-R-9023 Amendment 0005

CONTINUATION SHEET

1. QUESTION: Are factory disconnects required on the new chillers?

ANSWER: Yes, factory disconnects are required.

2. QUESTION: Warranty specifications only appear to pertain to chillers with Brazed Plate Heat Exchangers. Please confirm warranty requirements for all chillers?

ANSWER: All New Chillers, no matter the type of heat exchanger, must have a 10-year parts, labor, and refrigerant warranty the for the entire chiller.

3. QUESTION: Can as built schedules be sent out for the existing buildings so pumps and chillers can be sized to design instead off nominal tonnages

ANSWER: See the attached schedules for the equipment. It is the responsibility of the contractor for field verification.

4. All other terms and conditions remain unchanged.