This document appears to be a Statement of Work (SOW) for a chiller replacement project at specific BEQ (Bachelor Enlisted Quarters) buildings. The contractor is required to replace two chillers: a 110 nominal ton chiller at AS4006/4007 and a 90 nominal ton chiller at AS4206. The contractor must verify chiller and disconnect sizes prior to installation.
The project requires minimal disruption to facility operations, with the contractor expected to conduct work to cause the least possible interference with normal activities. The contractor is responsible for moving furniture and objects in the room during the replacement. Notably, one person may serve in multiple roles as Superintendent, Quality Control Manager, and Safety & Health Officer, provided they are qualified for all three positions as specified in the project specification.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION
The responsibility of the contractor is to replace chillers at the following BEQ buildings.
1.AS4006/4007 is a 110 nominal ton chiller.
2.AS4206 is a 90 nominal ton chiller.
• Chiller and disconnect sizes should be verified by the contractor.
SPECIAL SCHEDULING
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/ activity. The furniture and other objects in the room are to be moved by the contractor.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.