This is a Naval Facilities Engineering Command solicitation (N4008525R2543) for a design-bid-build water treatment plant (WTP) clearwell repair and replacement project at Naval Station Great Lakes, Illinois. The base bid involves constructing two 375,000-gallon pre-stressed concrete finished water storage tanks, a 3,400 square foot pump station building, associated piping systems, mechanical and electrical infrastructure, and site work to maintain continuous drinking water production. The project is valued between $25-100 million, with a NAICS code of 237110 and a small business size standard of $45 million.
Key project details include a 1,095 calendar day completion timeline, with 15 calendar days allowed for initial mobilization, and a mandatory site visit scheduled for March 19, 2025. The solicitation requires a comprehensive proposal evaluated on multiple factors including corporate experience, management approach, safety performance, past performance, and small business utilization. Bidders must submit a bid bond of 20% of the total project bid price (not exceeding $3M), provide detailed technical and price proposals, and demonstrate experience with water treatment facility construction. An option line item exists for replacing Valve 596. The procurement will be conducted using a full and open competition approach with a tradeoff source selection methodology.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. N40085-25-R-2543 DESIGN-BID-BUILD, WTP CLEARWELL REPAIR/REPLACEMENT, NAVAL STATION GREAT LAKES, GREAT LAKES, ILLINOIS
All correspondence regarding this solicitation shall be directed via email to Ashlee Beggs ashlee.r.beggs.civ@us.navy.mil
ASHLEE R. BEGGS 757-341-1031
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
06-Mar-2025
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________1095 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________07 Apr 2025 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
N4008525R2543 70
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
N4008525R2543
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Each
BASE PRICE
FFP
Total Price for Line Items (0001a -0001p) for the entire work for NAVSTA Great Lakes WTP Clearwell Repair/Replacement in accordance with the drawings and specifications, complete, but excluding work provided in Line Item 0002.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 Each
OPTION OPTION ITEM NO.1
FFP
Total price for providing all work in connection with the replacement of Valve 596, complete and in accordance with the drawings and specifications, but excluding valve and work provided in Line Item 0001.
FOB: Destination
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
Section 00 21 00 - Instructions
INSTRUCTIONS TO OFFERORS
TABLE OF CONTENTS
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.2 GENERAL OVERVIEW OF CONTRACT
2. BASIS FOR AWARD
3. EVALUATION FACTORS FOR AWARD
4. PROPOSAL REQUIREMENTS
4.1 SITE VISIT
4.2 PROPOSAL SUBMISSION INSTRUCTIONS
4.3 PRE-PROPOSAL INQUIRIES (PPIs)
4.4 CONTRACT OPPORTUNITIES (SAM.GOV)
5. INCORPORATION OF TECHNICAL PROPOSAL
6. ATTACHMENTS: MAY BE LOCATED ON CONTRACT OPPORTUNITIES UNDER ATTACHMENTS
6.1 ATTACHMENT A – PRE-PROPOSAL INQUIRY LOG
6.2 ATTACHMENT B – PIEE SOLICITATION VENDOR ACCESS INSTRUCTIONS
6.3 ATTACHMENT C – CONSTRUCTION EXPERIENCE PROJECT DATA SHEET
6.4 ATTACHMENT D – PAST PERFORMANCE QUESTIONNAIRE
6.5 ATTACHMENT E – PRICE PROPOSAL FORM
6.6 ATTACHMENT F – SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT
6.7 ATTACHMENT G – INDIVIDUAL SMALL BUSINESS SUBCONTRACTING PLAN
6.8 ATTACHMENT H –HISTORICAL SMALL BUSINESS UTILIZATION
6.9 ATTACHMENT I – NSGL FINAL SPECS
6.10 ATTACHMENT J – 12_1704005_CLEARWELL_IFC DRAWINGS
6.11 ATTACHMENT K – NSGL CLEARWELL SLIDE PRESENTATION FINAL
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.1.1 This acquisition is being solicited on an unrestricted basis, with Full and Open Competition.
1.1.2 The NAICS code for this procurement is 237110 and the size standard is $45,000,000.
1.1.3 In accordance with DFARS 236.204(ii), the magnitude of construction for this project is between $25,000,000 to $100,000,000.
1.1.4 This solicitation is formatted as a Request for Proposal in accordance with FAR Part 15.
This method permits evaluation of proposals based on price competition, technical merit and other factors; permits impartial and comprehensive evaluation of offerors' proposals; permits discussions if necessary; and ensures selection of the source whose performance provides the best value to the Government.
1.2 GENERAL OVERVIEW OF CONTRACT
Description of Work:
The Water Treatment Plant, located at Naval Station Great Lakes, Great Lakes, Illinois provides over 9,000,000 gallons of adequate drinking water per day.
Base Bid: The work includes: abate hazardous materials; demolish process piping-systems, pumping units, buried piping systems, pavements, and miscellaneous items; provide two nominal 375,000-gallon wire- or strand-wound pre-stressed concrete finished water storage tanks (i.e., clearwells); provide a 3,400 square foot pump station building with a 500 square foot breezeway to connect the pump station building to the existing filter building (i.e., Building 12A); provide four transfer pumping units and two filter backwash pumping units equipped with variable frequency drives inside the pump station building; provide two chlorine analyzers, provide chlorine and fluoride solution piping systems; provide exposed process piping systems, provide buried process piping systems; provide building mechanical fire protection, electrical and telecommunication systems for the pump station; provide telecommunications system that automates the transfer pumping process to convey finished water into the clearwells; provide telecommunications system for the filter backwashing process; provide weir chamber that receives filter effluent from the filtration process and conveys the water to the wet well of the transfer pumping units; provide site work such as grading, paving, fencing, and site restoration; flush, disinfect and conduct bacteriological sampling and analyses of potable water pipelines, water containing structures and clearwells to prepare them for drinking water service; provide tie-ins to existing water treatment processes while maintaining plant operations during construction so that there are no interruptions to drinking water production and supply; and incidental related work.
OPTION 1: The project scope of work is to provide all work in connection with the replacement of Valve 596, complete and in accordance with the drawings and specifications, but excluding valve and work provided in Line item 0001.
2. BASIS FOR AWARD
2.1 The Government reserves the right to eliminate from consideration for award any oral offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.
2.2 As stated in the solicitation, the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
2.3 The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
2.4 As stated in the solicitation, all technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined are approximately equal to price.
2.5 Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. An Unacceptable rating in any of the non-cost/price factors will result in an overall rating of “Unacceptable” for the non-cost/price factors, unless corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal.
The evaluation report must document the evaluation board’s assessment of the identified weakness(s) and the associated risk to successful contract performance resulting from the weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
3. EVALUATION FACTORS FOR AWARD
1. The solicitation requires the evaluation of price and the following non-cost/price factors:
Factor 1 – Corporate Experience Factor 2 – Management Approach and Schedule Factor 3 – Safety Factor 4 – Past Performance Factor 5 – Small Business Utilization and Participation
The distinction between corporate experience and past performance is corporate experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent relevant projects, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.
2. The relative order of importance of the non-price evaluation factors is the technical factors (Factors 1, 2, 3, and 5) are of equal importance to each other and, when combined, are equal in importance to the past performance evaluation/performance confidence assessment factor (Factor 4). When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.
The importance of price will increase if the Offerors’ non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.
3. Basis of Evaluation and Submittal Requirements for Each Factor.
(a) Price:
(1) Solicitation Submittal Requirements:
The offeror shall submit one (1) electronic copy via PIEE of the solicitation submittal requirements identified below.
The Price and Non-price proposals shall be submitted in separate files and submitted in Portable Document Format (PDF). In addition, non- price/technical information included in the price proposal will not be considered, likewise, price information included in the non-price/technical proposal will not be considered. All required proposal documents shall be submitted in accordance with FAR 15.208.
All submissions shall include the following:
1. Executed SF1442. Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, Offeror shall provide a cover page with solicitation number, solicitation title, Offeror name, address, phone number, fax number, Unique Entity Identifier (UEI), CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address with its proposal.
2. Completed Price Proposal Form. The Offeror is required to submit a complete Price Proposal
Form that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00 10 00 – Solicitation Contract Form in SF 1442.
3. Bid Bond (SF-24). Offeror shall submit a bid bond (SF-24) in the amount of 20% of total project bid price for the project or $3M, whichever amount is less. The bid bond shall be in the name of the offeror identified on the SF1442.
4. SAM registration. Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by Section 00 45 00 of the RFP is not provided in SAM, include the representation or certification in your price proposal.
5. FAPIIS. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete, as required by FAR 52.209-7, Information Regarding Responsibility Matters.
6. VETS-4212 registration. Confirmation of filing of Veterans’ Employment and Training
(VETS-4212) for the 2024 filing cycle, if the Offeror is required to submit.. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal. If the Offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the Offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS- 4212 report and to request an email confirmation of submission.
7. Small Business Subcontracting Plan (Reference FAR 52.219-9 ALT II and DFARS 252.219-
7003).
In accordance with FAR 19.7, all offerors, other than small businesses, shall submit a Small Business Subcontracting Plan (SBSP) utilizing the template provided as Attachment G. Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB, but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the Offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.
NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract. These targets are based on a percentage of total planned subcontract dollars. These goals will be incorporated into the solicitation.
Small Business (SB) 40% Small Disadvantaged Business (SDB) 5% HUBZone SB 3% Woman-Owned Small Business (WOSB) 9% Service-Disabled Veteran-Owned Small Business (SDVOSB) 5%
The SBSP shall be consistent with the commitments offered in the Small Business Utilization and Participation factor. In accordance with DFARS 215.304(c)(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.
Please note that SBSP goals and the participation rates provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The participation rates within the SBPCD are provided as percentages of the total contract value; subcontract plan goals are provided as a percentage of planned subcontracting dollars. While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products/services identified in the SBPCD. Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD.
8. Bank Reference. One (1) Signed Bank Reference demonstrating adequate financial resources.
If offeror’s firm has a line of credit, provide information on how many figures the offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).
9. Financial Statements. The Offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies.
10. Facilities and Equipment. Provide a description of offeror’s facilities and equipment.
11. Other Work. Provide a list of offeror’s other work presently under contract.
(2) Basis of Evaluation:
The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items (See Attachment E- Price Proposal Form). The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in Section 00 21 16 of the solicitation. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s).
Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
Although required to be submitted with offeror’s price proposal, Items 3 through 12 above will not be evaluated as part of the price proposal. This information will be utilized by the Government in the responsibility determination and for considering responsiveness to the solicitation requirements.
(b): Non-cost/price Factors:
All submissions shall include the following:
The Offeror shall submit one (1) electronic copy via PIEE of the solicitation submittal requirements identified below. The Price and Non-price proposals shall be submitted in separate files and submitted in Portable Document Format (PDF). In addition, non- price/technical information included in the price proposal will not be considered, likewise, price information included in the non-price/technical proposal will not be considered. All required proposal documents shall be submitted in accordance with FAR 15.208.
Offeror shall provide a cover page with solicitation number, solicitation title, Offeror name, address, phone number, fax number, Unique Entity Identifier (UEI), CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address with its proposal.
Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated.
Note: If proposing as a Joint-Venture (JV), please submit the POC, UEI, and CAGE Code for each JV partner.
Factor 1, Corporate Experience:
(i) Solicitation Submittal Requirements:
Offerors shall submit a minimum of two (2) up to a maximum of five (5) relevant construction projects that best demonstrate their experience on relevant projects similar in size, scope, and complexity to this RFP.
Offeror must have performed as the Prime Contractor for each project submitted. Experience of proposed subcontractors will not be considered.
For purposes of this evaluation, a relevant project is further defined as:
Size: A final construction cost of $10,000,000 or greater.
Scope: Renovation or construction experience related to Water Treatment Facilities or Industrial Water Storage Facilities. For the purposes of this solicitation, Water Treatment Facilities shall include, but are not limited to, facilities that engage in: Potable Water Production, Wastewater or Sewage Treatment, Reverse Osmosis, Demineralization, Effluent Treatment.
Complexity: Relevant projects submitted shall, either collectively or individually, demonstrate experience with all of the elements listed below. Offeror does not need to demonstrate experience with every element for each project, experience may be demonstrated collectively through all projects submitted, provided that each submitted project individually demonstrates the required size and scope. Required elements are listed below:
Phased construction experience related to Water Treatment Facilities or Industrial Water Storage Facilities;
Construction work in existing utility plants or industrial buildings where facility operations remain active;
Hazardous Material Abatement and Disposal;
Project required Commissioning of system(s), by an independent party upon completion.
Note: The Corporate Experience Factor shall be satisfied when relevant projects meet each Complexity element collectively. All elements do not have to be included under one project, experience may be demonstrated collectively through all projects submitted meeting size and scope.
For all submitted projects, ensure that the project description clearly provides the final construction cost and addresses how the project meets the scope/complexity requirements.
Projects submitted for the Offeror shall have been completed within the past ten (10) years from the date of issuance of this RFP. Projects which are not complete as of the date of issuance of this RFP will be considered “Not Relevant”. Additionally, projects completed prior to ten (10) years from the date of issuance of this RFP will be considered “Not Relevant.”
A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project;
rather, offerors shall submit the work performed under a task order as a project. The submission of a multiple award and/or indefinite delivery/indefinite quantity type contract as a whole will be considered Not Relevant.
The attached Construction Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider submissions via any other medium.
Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) pages. Information beyond this page limit will not be considered.
If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the individual Joint Venture members. Offerors are still limited to a total of five (5) projects. Offerors may submit experience where a member of the JV performed as a JV with another entity but must clearly demonstrate how its work on that project met size, scope, and complexity as defined above. Likewise, Offerors that are not submitting as a JV may submit a project where it performed as a JV with another entity but must clearly demonstrate how its work on that project met size, scope, and complexity as defined above. Offerors are still limited to a total of five (5) projects.
For a JV, the offeror shall submit the signed JV agreement. For an 8(a) Mentor-Protégé Joint Venture, the offeror shall submit the signed U.S. Small Business Administration (SBA) Mentor-Protégé approval letter and signed JV agreement.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement and clearly describe the role that firm will have in the performance of the contract. If meaningful involvement is not demonstrated, experience of the affiliate/subsidiary/parent firm will not be considered.
(ii) Basis of Evaluation:
The basis of evaluation will include the offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects for construction experience. Any projects submitted in excess of five (5) will not be considered. An offeror that does not submit a minimum of two
(2) relevant projects as defined above will receive a rating of “Unacceptable” and will not be eligible for award.
Relevant projects demonstrating a final construction cost of over $15 000,000 may be considered more favorably.
Relevant projects demonstrating construction of water storage facilities great than 150,000 gallons may be considered more favorably.
Relevant projects demonstrating construction of potable water pumping or storage facilities may be considered more favorably.
Factor 2 – Management Approach and Schedule:
The offeror shall submit a narrative and schedule for this factor. The narrative shall not exceed ten (10) pages, 8- 1/2" x 11" size. Provide the schedule, documenting any multiple critical paths, in 11" x 17" pages and in an Adobe PDF file. There is no page limit on the schedule.
The narrative shall include, but not limited to:
1. Describe the proposed approach to management, for both subcontractors and your workforce, to ensure schedule adherence, early detection and correction of problems and the execution of the base work and all options, as referenced in the RFP;
2. Describe how your firm will handle technical complexities relating to:
Hazardous Materials Testing, Abatement, and Disposal Environmental Compliance with federal state and local regulations
Equipment (Tanks/Pumps/Valves/VFDs) start-up and commissioning Clearwell tank foundation type and design assumed Utility cut-overs and phasing from existing Piping & Instrumentation process flow to the proposed Piping & Instrumentation process flow;
3. Off-site scope: Design, Deliver, and Fabrication of Clearwell tank and parts;
4. Acknowledge project work restrictions, including the following important events:
The schedule shall include, but not be limited to:
1. Provide a Critical Path Method (CPM) construction schedule that illustrates your ability to achieve the schedule and meet all the requirements of the RFP (1095 calendar days, including 15 days for insurance and bond approval). The schedule shall be based on a contract award date of July 2025. This date is for proposal purposes only and is not intended to indicate an anticipated/planned award date.
Any proposed duration shorter than the RFP requirements will be incorporated into the contract award.
The basis of evaluation will include the Offerors demonstrated understanding of the RFP, narrative, and schedule as defined in the solicitation submittal requirements.
A narrative work plan that identifies areas of risk in logistics and resource management, and provides a comprehensive contingency plan that addresses mitigation of any identified risks with potential solutions, may be considered more favorably.
A schedule that proposes a realistic shorter contract duration than the duration indicated in the RFP may be considered more favorably.
Factor 3, Safety
The Offeror shall submit the following information: The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative, as described further below. For a partnership or joint venture, the Offeror shall submit separate DART rates and TCR for the specified five (5) CY for each contractor who is part of the partnership/joint venture; however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.
NOTE: DART and TCR shall not be submitted for subcontractors
1. DART Rate: Submit five (5) previous complete calendar years’ [CY2020, CY2021, CY2022, CY2023, CY2024] worth of data (not an overall average). If the Offeror has no DART rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.
a. DART cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.
b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.
Number of DART Incidents x 200,000
Total Number of Employee Labor Hours Worked
2. TCR Rate: Submit five (5) previous complete calendar years [CY2020, CY2021, CY2022, CY2023, CY2024] worth of data (not an overall average). If the Offeror has no TCR rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.
a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.
b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.
Number of TCR Incidents x 200,000
Total Number of Employee Labor Hours Worked
3. Technical Approach to Safety: Submit a narrative that addresses the following:
1. Describe the Offeror’ s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the
SMS.
2. Describe the evaluation of subcontractor’s safety performance in the Offeror’s selection process.
3. Describe the processes of how the Offeror will oversee safety compliance of subcontractors at all levels throughout performance of the contract (to include the Offeror’s own in-house workforce).
4. The Technical Approach to Safety narrative shall be limited to two (2) pages.
4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
(ii) Basis of Evaluation:
The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR rate, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR rates to determine if the Offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
1. DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the Offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk
(HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the DART rate to the level of risk:
Risk DART Rate
Very Low Risk Less Than 1.0 Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0
2. TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the Offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the TCR rate to the level of risk:
Risk DART Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49 Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0
3. The Technical Approach to Safety Narrative. To determine the degree to which the Offeror:
a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.
c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.
d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages. Information on pages beyond this will not be considered.
4. The Government reserves the right to review other available sources (public/Government internal) of information.
These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
Factor 4 - Past Performance
If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 1. The offeror shall include all completed CPARS evaluations (interim and final) for a project. If there is not a completed CPARS evaluation, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1 Corporate Experience. AN OFFEROR
SHALL NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS AVAILABLE
If a CPARS evaluation is not available, completed PPQs should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ (Attachment D), which will provide contract and client information for the respective project(s). Offerors should ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Ashlee Beggs, via email at ashlee.r.beggs.civ@us.navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs.
However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Corporate Experience. Offerors may also address any adverse past performance issues.
Such explanations shall not exceed four (4) pages in total. Information beyond this page limitation will not be considered.
Sources of Past Performance Information for evaluation that may be used are as follows:
Past performance information provided by the offeror, as solicited;
Past performance information obtained from questionnaires tailored to the circumstances of the acquisition; and Past performance information obtained from any other sources available to the Government, to include, but not limited to, Contractor Performance Assessment Reporting System (CPARS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; the Defense Contract Management Agency; and interviews with Program Managers, Contracting Officers, and Fee Determining Officials.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
A copy of the blank Past Performance Questionnaire to be used for requesting client references is included as Attachment D.
The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the Offeror’s references or the references’ unwillingness to provide the information requested may affect the Government’s evaluation of this factor.
(ii) Basis of Evaluation:
This evaluation focuses on how well the Offeror performed on the projects submitted under Factor 1 – Corporate Experience and past performance on other projects currently documented in known sources. The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in Contractor’s performance. In the case of Offerors for which there is no information on past performance, or where past performance information is not available or so sparse that no meaningful assessment can be performed, the Offeror may not be evaluated favorably or unfavorably, and will instead receive a “Neutral” rating (See FAR 15.305(a)(2)(iv)).
The Government will consider the degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., CPARS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance considering:
A pattern of successful completion of tasks;
A pattern of deliverables that are timely and of good quality;
Pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); and Recency of tasks performed that are identical to, similar to, or related to the task at hand.
Factor 5 – Small Business Utilization and Participation:
It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Small Disadvantaged Business (SDB), Woman-Owned Small Business (WOSB), Historically Underutilized Business Zone Small Business (HUBZone SB), Veteran-Owned Small Business (VOSB), Service-Disabled Veteran-Owned Small Business (SDVOSB), and other small business concerns. Further, it is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance.
This Factor assesses both the historical achievements in utilizing small business concerns and the proposed small business participation commitment for this requirement. The offeror is required to demonstrate its previous commitment to SBs through its record of past utilization of SBs and the level of commitment to small business if awarded a contract under this solicitation.
(i) Solicitation Submittal Requirements:
1. All Offerors (large, non-profits, AND small businesses) shall use Attachment H (Historical Small Business Utilization) to demonstrate their historical utilization of SBs. Each project submitted under Factor 1, Corporate Experience, shall be included on Attachment H. Failure to include each project submitted under Factor 1, Corporate Experience, on Attachment H, or the failure to fully complete Attachment H for each project may result in a deficiency. Only complete Attachment H. Information provided in a different format and/or on a form created by the offeror will not be evaluated. Attachments or addendums to Attachment H will not be evaluated. Offerors are permitted to expand portions of the form, as needed, to provide sufficient response. Instructions regarding how to complete Attachment H are included at the beginning of the attachment.
2. All Offerors (large, non-profits, AND small businesses) shall use Attachment F (Small Business Participation Commitment Document (SBPCD) to submit the following required information for evaluation of this factor:
To demonstrate commitment to use small business concerns in the performance of this contract, identify by name the subcontractors that will be used to support each small business category, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSBs. Identify the type and complexity of product/service to be subcontracted, and the type of commitment (i.e., teaming agreement, joint venture agreement, mentor protégé agreement, letter of commitment, etc.) with each subcontractor.
o If subcontractors are not identified by name, offerors shall provide a detailed explanation why subcontractors are not identified. If firm written commitments with SBs are not in place, offerors shall provide an explanation and rationale on the ability to achieve the proposed participation. (See Attachment F, paragraph 5) o If a LB offeror does not intend to subcontract, provide a detailed explanation why subcontracting would not result in efficient contract performance. SBs intending to
100% self-perform are not required to provide an explanation. (See Attachment F, paragraph 6)
To demonstrate maximum practicable participation of small businesses, identify (in terms of dollar value and percentage of the total contract value) the offeror’s proposed small business participation. The minimum required small business participation (i.e. work to be performed by small business as the prime contractor and/or work to be performed by small business subcontractors) is 25%. Offerors who are not able to meet the minimum total small business participation requirement of 25% (of the total contract value) shall provide a detailed explanation why the minimum total small business participation requirement cannot be achieved.
Only complete Attachment F. Information provided in a different format and/or on a form created by the offeror will not be evaluated. Attachments or addendums to Attachment F will not be evaluated.
Large business offerors may achieve the minimum total small business participation requirement through subcontracting to small businesses.
Small business offerors may achieve the minimum total small business participation requirement through their own performance/participation as a prime as well as through a joint venture, teaming arrangement, and/or subcontracting with other small business concerns.
The Government will evaluate the likelihood of success in achieving the small business objectives of this acquisition based on the following:
1. The extent to which the offeror is able to demonstrate a history of supporting Government policies concerning the utilization of small business concerns, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSB and the success in achieving goals established by subcontracting plans on prior contracts. For projects submitted for Factor 1, Corporate Experience, that did not have established small business goals, consideration will be given to the utilization of the small business concerns and the degree of usage of small business relative to the total contract value. Historical Small Business Utilization will only be evaluated if performed by the offeror.
2. The extent to which the offeror has demonstrated an achievable commitment to use small businesses, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSB in the performance of this contract within the SBPCD.
The minimum small business participation requirement, through work performed by the small business prime and/or subcontracting with small businesses, shall meet or exceed 25% of the total contract value, unless the offeror provides a reasonable and well-documented explanation for why the minimum 25% small business participation requirement cannot be achieved.
o Offerors that demonstrate a commitment to providing maximum practical opportunity to small businesses may be rated higher.
o Proposing less than 25% total small business participation requirement may result in a deficiency.
o Offerors that do not demonstrate commitment to providing maximum practical opportunity to small businesses may result in a deficiency.
The SBPCD will be evaluated to determine the extent to which small business concerns are specifically identified by name and socioeconomic category in the document and the degree to which small business concerns, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSB will participate relative to the total contract value. The complexity and variety of the work small business concerns will perform and the degree of commitment to use named sources through formal teaming agreements, joint venture agreements, mentor protégé agreements, written/signed letters of /commitment, etc. will be evaluated to assess achievability of the commitment.
o…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .