Attachment I - NSGL FINAL SPECS.pdf
PDF 18 MB Posted
- Attached to
- DESIGN-BID-BUILD, WTP CLEARWELL REPAIR/REPLACEMENT, NAVAL STATION GREAT LAKES, GREAT LAKES, ILLINOIS
- Solicitation number
- N4008525R2543
About this file
This is a comprehensive set of final specifications for the Water Treatment Plant (WTP) Clearwells Repair/Replacement Project at Naval Station Great Lakes in Illinois. The project involves a design-bid-build contract to replace two 410,000-gallon wire- or strand-wound prestressed concrete finished water storage tanks (clearwells), construct a new 3,500 square foot transfer pump station building, install four transfer pumping units and two filter backwash pumping units, and implement associated mechanical, electrical, and telecommunications systems.
Key project components include demolishing existing process piping and equipment, constructing new clearwells and pump station, installing new process piping systems, implementing water control gates and stop logs, performing site work such as grading and fencing, and conducting comprehensive water system disinfection and testing. The project requires careful phased construction to maintain continuous water treatment plant operations, with specific requirements for utility outages, environmental controls, and waste management. The contract is being executed by the Naval Facilities Engineering Systems Command (NAVFAC) Mid-Atlantic Public Works Department, with a solicitation number of N4008525R2543 and an anticipated completion in December 2024.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO.
At the
PREPARED BY:
Architectural: Mechanical:
Civil: Electrical:
Structural:
APPROVED BY:
For Commander, NAVFAC:
Date:
Submitted By: Date:
nancy.wroten Line
THIS PAGE INTENTIONALLY LEFT BLANK
SPECIFICATIONS
DECEMBER 2024
Naval Station Great Lakes
Water Treatment Plant
Clearwells
Repair/Replacement Project
Prepared for:
Naval Facilities Engineering Systems Command Mid-Atlantic Public Works Department Great Lakes
SUBMITTAL STAGE: Final Specifications
LOCATION: NAVSTA Great Lakes
A/E CONTRACT NO.: N62470-19-D-2012
TASK ORDER NO.: N4008523F6246
ePROJECTS WORK ORDER NO.: 1704005
CONTRACT TYPE: Design Bid Build
WTP Clearwells Repair/Replacement, Naval Station Great Lakes Final Specifications December 2024
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 11/22, CHG 1: 02/23 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23, CHG 1: 02/24 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 17.00 20 11/23 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 35 26 11/20, CHG 4: 08/23 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 60 00 10/24 PRODUCT REQUIREMENTS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 88 19 03/24 TIGHTNESS TESTING PERFORMANCE
REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 61 13 02/10, CHG 1: 02/21 EXCAVATION AND HANDLING OF
CONTAMINATED MATERIAL
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION
02 83 00 11/18 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 01 00 02/18 REHABILITATION OF CONCRETE
03 30 00 02/19, CHG 7: 02/24 CAST-IN-PLACE CONCRETE
03 37 13 02/18 SHOTCRETE
03 45 33 05/16, CHG 1: 11/21 PRECAST PRESTRESSED STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
PROJECT TABLE OF CONTENTS Page 1
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 08/23 METAL RAILINGS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 08/23 BITUMINOUS DAMPPROOFING
07 19 00 08/23 WATER REPELLENTS
07 21 13 08/23 BOARD AND BLOCK INSULATION
07 22 00 08/23 ROOF AND DECK INSULATION
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 08/23 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 60 45 08/20 SKYLIGHTS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
DIVISION 09 - FINISHES
09 67 23.15 02/21 FUEL RESISTIVE RESINOUS FLOORING,
3-COAT SYSTEM
09 90 00 02/21 PAINTS AND COATINGS
09 96 00 11/14 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 33.00 40 11/20 ELECTRIC AND ELECTRONIC CONTROL SYSTEM
FOR HVAC
23 09 53.00 20 02/10, CHG 2: 08/17 SPACE TEMPERATURE CONTROL SYSTEMS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
PROJECT TABLE OF CONTENTS Page 2
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 83 00.00 20 04/06 ELECTRIC SPACE HEATING EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 10 00 02/21 SITE CLEARING
31 11 00 11/18 CLEARING AND GRUBBING
31 32 19.13 02/21 GEOGRID SOIL STABILIZATION
31 32 19.16 02/21 GEOTEXTILE SOIL STABILIZATION
31 62 50 11/20, CHG 1: 05/22 DENSIFIED AGGREGATE PIERS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.71 11/22 COLD MILLING ASPHALT PAVING
32 11 20 05/22 SUBBASE FOR FLEXIBLE PAVING
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 11 23.23 08/22 BASE COURSE DRAINAGE LAYERS
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
PROJECT TABLE OF CONTENTS Page 3
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 14 08/22 STOPLOGS
35 20 16.54 05/21 SLIDE GATES AND ACTUATORS
DIVISION 40 - PROCESS INTERCONNECTIONS
40 05 13 10/07, CHG 2: 02/20 PIPELINES, LIQUID PROCESS PIPING
40 60 00 05/20 PROCESS CONTROL
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE
EQUIPMENT
43 24 26.25 08/24 TRANSFER PUMPS (VERTICAL TURBINE PUMPS
FOR WET PITS)
43 24 26.35 08/24 BACKWASH PUMPS (VERTICAL TURBINE
SHORT-SET CAN PUMPS)
43 41 63 06/24 WIRE AND STRAND WRAPPED PRESTRESSED
CONCRETE TANK
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11, CHG 1: 08/14
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
Drawing Number NAVFAC Drawing Number Title
G-001 12918928 Cover Sheet
GI001 12918929 Sheet Index
GI002 12918930 General Notes, Legend, Abbreviations, and Symbols
GI003 12918931 Existing Process Flow Diagram
GI004 12918932 Process Flow Diagram
GI005 12918933 Hydraulic Profile
GI006 12918934 Area Classification Schedule
GI007 12918935 Materials Schedule
GI008 12918936 Life Safety Code Compliance
GI009 12918937 Life Safety Plan
GC001 12918938 Construction Phasing Plan I
GC002 12918939 Construction Phasing Plan II
GC003 12918940 Construction Phasing Plan III
GC004 12918941 Construction Phasing Plan IV
GC005 12918942 Construction Phasing Plan V
GC006 12918943 Construction Phasing Plan VI
GC007 12918944 Construction Phasing Plan VII
DOCUMENT 00 01 15 Page 1
Drawing Number NAVFAC Drawing Number Title
GC008 12918945 Construction Phasing Plan VIII
GC009 12918946 Construction Phasing Plan IX
GC010 12918947 Construction Phasing Plan X
GC011 12918948 Construction Phasing Plan XI
GC012 12918949 Construction Phasing Plan XIII
GC013 12918950 Construction Phasing Plan XIV
GC014 12918951 Construction Phasing Plan XV
GC015 12918952 Construction Phasing Plan XVI
GC016 12918953 Construction Phasing Plan XVII
GC017 12918954 Construction Phasing Plan XVIII
GC018 12918955 Construction Phasing Plan XIX
GC019 12918956 Construction Phasing Plan XX
GC020 12918957 Construction Phasing Plan XXI
GC021 12918958 Construction Phasing Plan XXII
GC022 12918959 Construction Phasing Plan XXIII
GC023 12918960 Construction Phasing Plan XXIV
GC100 12918961 Contractor Access, Staging, and Storage Plan I Clearwell Tank Construction
GC101 12918962 Contractor Staging and Storage Plan II
C-001 12918963 Abbreviations, Symbols, and Legend
C-002 12918964 General Notes
C-100 12918965 Existing Site Plan
CD100 12918966 Contractor Staging and Temporary Erosion Control Plan
CD101 12918967 Clearwell Site Demolition and Temporary Erosion Control Plan
CD102 12918968 Transfer Pump Station Site Demolition And Temporary Erosion Control Plan
CD103 12918969 Yard Piping Demolition
CS100 12918970 Clearwell Site Layout Plan
DOCUMENT 00 01 15 Page 2
Drawing Number NAVFAC Drawing Number Title
CS101 12918971 Transfer Pump Station Site Layout Plan
CG100 12918972 Clearwell Site Grading Plan
CG101 12918973 Transfer Pump Station Site Grading Plan
CG400 12918974 Detention Basin Detailed Grading Plan
CU100 12918975 Overall Yard Piping Plan
CU102 12918976 Sanitary Sewer Plan
CU103 12918977 Stormwater Drainage Plan and Profile I
CU104 12918978 Stormwater Drainage Plan and Profile II
CU200 12918979 Yard Piping Profiles I
CU201 12918980 Yard Piping Profiles II
CU202 12918981 Yard Piping Profiles III
CU203 12918982 Yard Piping Profiles IV
CU300 12918983 Horizontal Control Tables I
CU301 12918984 Horizontal Control Tables II
CU400 12918985 Clearwell Enlarged Yard Piping Plan I
CU401 12918986 Clearwell Enlarged Yard Piping Plan II
CU402 12918987 Transfer Pump Station Enlarged Yard Piping Plan
C-501 12918988 Civil Site Details I - General
C-502 12918989 Civil Site Details II - General
C-503 12918990 Civil Site Details III - Erosion Control
C-504 12918991 Civil Site Details IV - Fence
C-505 12918992 Civil Site Details V - Swing Gate
C-506 12918993 Civil Site Details VI - Cantilever Gate
C-507 12918994 Civil Site Details VII - Yard Piping
C-508 12918995 Civil Site Details VIII - Yard Piping
C-509 12918996 Civil Site Details IX - Yard Piping
DOCUMENT 00 01 15 Page 3
Drawing Number NAVFAC Drawing Number Title
C-510 12918997 Civil Site Details X - Stormwater
B100 12918998 Boring Locations
B101 12918999 Boring Profiles
B102 12919000 Boring Profiles
B103 12919001 Boring Profiles
B104 12919002 Boring Profiles
B105 12919003 Boring Profiles
A-001 12919004 Architectural Notes, Symbols, Legends, and Abbreviations
A-002 12919005 Architectural Transfer Pump Station Isometrics
A-101 12919006 Architectural Transfer Pump Station Ground Floor Plan & Roof Plan
A-201 12919007 Architectural Transfer Pump Station Elevations
A-301 12919008 Architectural Transfer Pump Station Building Sections
A-401 12919009 Architectural Transfer Pump Station Wall Sections
A-402 12919010 Architectural Transfer Pump Station Wall Sections
A-501 12919011 Architectural Transfer Pump Station Wall Details
A-601 12919012 Architectural Transfer Pump Station Schedules
S-001 12919013 Structural Notes
S-101 12919014 Structural Transfer Pump Station Floor Foundation Plan
S-102 12919015 Structural Transfer Pump Station First Floor Plan
S-103 12919016 Structural Transfer Pump Station Roof Plan
S-104 12919017 Structural Filter Building Plan
S-105 12919018 Pump Room Structural Plan
S-301 12919019 Structural Sections
S-302 12919020 Structural Sections
S-303 12919021 Structural Sections
S-304 12919022 Structural Sections
DOCUMENT 00 01 15 Page 4
Drawing Number NAVFAC Drawing Number Title
S-305 12919023 Structural Sections
S-501 12919024 Structural Standard Concrete Details I
S-502 12919025 Structural Standard Concrete Details II
S-503 12919026 Structural Standard CMU Details I
S-504 12919027 Structural Standard CMU Details II and Metal Roof Deck Details
S-505 12919028 Structural Standard Stair and Crossover Ladder Details
S-506 12919029 Structural Standard Railing Details
S-507 12919030 Structural Standard Concrete Repair Details
S-508 12919031 Structural Details
S-509 12919032 Structural Details
S-601 12919033 Schedule of Special Inspections I
S-602 12919034 Schedule of Special Inspections II
M-001 12919035 Process Mechanical Legend, Abbreviations and Symbols
M-002 12919036 Process Mechanical General Notes
MH001 12919037 HVAC Symbols, Abbreviations & Notes
MH101 12919038 HVAC Floor Plan
MH301 12919039 HVAC Sections
MH501 12919040 HVAC Details
MH502 12919041 HVAC Airflow Diagrams and Control Sequences
MH601 12919042 HVAC Schedule
MD101 12919043 Process Mechanical Demolition Plan & Sections
- Filter Backwash Pumps
MD104 12919044 Process Mechanical Demolition Plan & Sections
- Pump Room
MD105 12919045 Process Mechanical Demolition Plan - Filter Pipe Gallery
MD301 12919046 Process Mechanical Demolition Sections - Clearwells 4 & 5
MD901 12919047 Process Mechanical Demolition Photographs I
MD902 12919048 Process Mechanical Demolition Photographs II
DOCUMENT 00 01 15 Page 5
Drawing Number NAVFAC Drawing Number Title
MD903 12919049 Process Mechanical Demolition Photographs III
MD904 12919050 Process Mechanical Demolition Photographs IV
MP102 12919051 Process Mechanical Filter Building Piping Plan
MP103 12919052 Process Mechanical Filter Building Piping Plan Clearwells 4 & 5
MP104 12919053 Process Mechanical Transfer Pump Station Overall Plan
MP105 12919054 Process Mechanical Transfer Pump Station Enlarged Plans
MP106 12919055 Process Mechanical Intake Wetwell and Pump Room Piping Plan and Sections
MP107 12919056 Process Mechanical Pipe Gallery Plan and Sections
MP108 12919057 Process Mechanical Clearwells Piping Plan
MP109 12919058 Process Mechanical Clearwells Dome Plan
MP301 12919059 Process Mechanical Filter Building Piping Sections I
MP302 12919060 Process Mechanical Filter Building Piping Sections II
MP303 12919061 Process Mechanical Transfer Pump Station Sections I
MP304 12919062 Process Mechanical Transfer Pump Station Sections II
MP305 12919063 Process Mechanical Clearwells Sections and Details I
MP306 12919064 Process Mechanical Clearwells Sections and Details II
MP307 12919065 Process Mechanical Clearwells Sections and Details III
MP501 12919066 Process Mechanical Details I
MP502 12919067 Process Mechanical Details II
MP601 12919068 Equipment and Valve Schedules
P-001 12919069 Plumbing Abbreviations, Symbols and Schedules
P-101 12919070 Plumbing Floor Plan
P-501 12919071 Plumbing Details and Diagrams
F-101 12919072 Fire Protection Plan, Legend, Schedule and Notes
FA001 12919073 Fire Alarm General Notes
FA002 12919074 Fire Alarm Operational Matrix
DOCUMENT 00 01 15 Page 6
Drawing Number NAVFAC Drawing Number Title
FA101 12919075 Fire Alarm Device Layout
FA501 12919076 Fire Alarm Details
F-501 12919077 Fire Protection Details
T-001 12919078 Instrumentation Legend I
T-002 12919079 Instrumentation Legend II
T-601 12919080 Control System Architecture
T-602 12919081 Transfer Pumps P&ID
T-603 12919082 Backwash Pumps P&ID
T-604 12919083 Clearwells and Yard Piping P&ID
T-605 12919084 Standard Instrumentation Details I
T-606 12919085 Standard Instrumentation Details II
T-607 12919086 Standard Instrumentation Details III
T-608 12919087 PLC Panel Details I
T-609 12919088 PLC Panel Details II
T-610 12919089 Filter Building Network Cabinet Modification
E-001 12919090 Electrical Legend I
E-002 12919091 Electrical Legend II
E-003 12919092 Electrical General Notes
ED101 12919093 Electrical Site Demolition Plan
ED102 12919094 Electrical Backwash Pumps Demolition Plan
ED601 12919095 Electrical Demolition One Line Diagram
ES101 12919096 Electrical Site Plan I
ES102 12919097 Electrical Site Plan II
EP101 12919098 Electrical Transfer Pump Station Power Plan
EP102 12919099 Electrical Clearwell and Filter Building Power Plan
EG101 12919100 Electrical Transfer Pump Station Grounding Plan
DOCUMENT 00 01 15 Page 7
Drawing Number NAVFAC Drawing Number Title
EG102 12919101 Electrical Transfer Pump Station Lightning Protection System Plan
EG103 12919102 Electrical Clearwell Grounding Plan
EG104 12919103 Electrical Clearwell Lightning Protection System Plan
EL101 12919104 Electrical Site Lighting Plan
EL102 12919105 Electrical Site Lighting Photometrics
EL103 12919106 Electrical Transfer Pump Station Lighting and Receptacle Plan
EL104 12919107 Electrical Transfer Pump Station Photometrics
EL105 12919108 Electrical Transfer Pump Station Emergency Photometrics
E-601 12919109 Electrical One Line Diagram
E-602 12919110 Electrical Panel and Lighting Schedules
E-603 12919111 Electrical Riser Diagrams
E-501 12919112 Electrical Details I
E-502 12919113 Electrical Details II
E-503 12919114 Electrical Details III
-- End of Document --
DOCUMENT 00 01 15 Page 8
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes: abate hazardous materials; demolish process piping systems, pumping units, buried piping systems, pavements, and miscellaneous items; provide two 410,000-gallon wire- or strand-wound prestressed concrete finished water storage tanks (i.e., clearwells);
provide a 3,500 square feet transfer pump station building with a 500 square feet vestibule to between the transfer pump station building and the existing filter building (i.e., Building 12A); provide four transfer pumping units and two filter backwash pumping units equipped with variable frequency drives inside the pump station building; provide chlorine analyzers, provide chlorine and fluoride solution piping systems; provide exposed process piping systems, provide buried process piping systems;
provide building mechanical fire protection, electrical and telecommunication systems for the transfer pump station; provide telecommunications system that automates the transfer pumping process to convey finished water into the clearwells; provide telecommunications system for the filter backwashing process; provide weir chamber that receives filter effluent from the filtration process and conveys the water to the wetwell of the transfer pumping units; provide water control gates and stop logs, provide site work such as grading, paving, fencing, and site restoration; flush, disinfect and conduct bacteriological sampling and analyses of potable water pipelines, water containing structures and clearwells to prepare them for drinking water service; provide tie-ins to existing water treatment processes while maintaining plant operations during construction so that there are no interruptions to drinking water production and supply; and incidental related work.
1.1.2 Location
The work is located at the Naval Station Great Lakes Water Treatment Plant in Great Lakes, Illinois, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Buildings will be occupied during performance of work under this Contract.
Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
SECTION 01 11 00 Page 1
a. Remove or alter existing work in such a manner as to prevent injury or damage to portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark utilities not indicated on the contract drawings within the area of work. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground and paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and other types of underground obstructions not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 1: 02/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA B300 (2018) Hypochlorites
AWWA B301 (2018) Liquid Chlorine
AWWA C651 (2023) Standard for Disinfecting Water Mains
AWWA C652 (2019) Disinfection of Water-Storage Facilities
AWWA C653 (2020) Disinfection of Water Treatment Plants
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. Provide buried sanitary sewers, water mains, valves and appurtenances to relocate and place these existing buried utilities into service as approved by the Contracting Officer before the existing buried sanitary sewers and waters main currently located beneath the transfer pump station are removed.
b. Remove buried sanitary sewers, water mains and appurtenances that are currently located within the footprint and vicinity of the transfer pump station before constructing the transfer pump station.
c. Remove chain link fence that is located between Building 10A and the surge tank to make space for constructing the transfer pump station.
d. The two nominal 410,000-gallon clearwells, weir chamber, vestibule, transfer pump station, transfer pumping units, filter backwash pumping units, filter backwash header piping, chlorine solution piping, fluoride solution piping, and the building mechanical, fire
SECTION 01 14 00 Page 1 protection, telecommunications, and electrical systems associated with the transfer pump station and filter backwash pumps, and the buried 16-inch, 18-inch, 20-inch, and 24-inch yard piping, valves and appurtenances must be ready for operation as approved by Contracting Officer before work is started on clearwell 1, clearwell 4, clearwell 5, the valve chamber, and connecting yard piping to the suction piping of the high lift pumping units inside the pump room which would interfere with normal operation of the water treatment plant.
e. Remove the buried 16-inch water pipe that exits the north wall of the valve chamber and runs north along the east side of Building 12 and then turns west into the basement of Building 12 into the Pump Room, as well as the 16-inch CWE CI pipe that is located beneath the concrete floor of the Pump Room just up to its connection with the exposed suction header of the high lift pumps in the pipe trench covered with checked plate before work is started on clearwell 4, clearwell 5, valve chamber, and connecting to the suction piping of the high lift pumping units inside the pump room which would interfere with normal operation.
f. Provide a temporary 16-inch potable water pipeline from new Clearwells 1 and 2 and connect it to the temporary connection Points A and B shown on the Drawings before the first partial shutdown of the high lift pumping units in the Pump Room. This temporary 16-inch pipeline will be used to feed finished water to the high lift pumping units when the 16-inch pipe beneath the low- and high-lift pump room floor is replaced with new 16-inch piping. Connect the temporary 16-inch pipeline to the suction piping at the two points on the high lift suction header where indicated on the drawings.The 16-inch temporary pipe may also be used to convey finished water from the new clearwells 1 and 2 to the high lift pumps when work is being performed in existing clearwell 1.
g. The construction activities that require partial shutdown of plant operations to cut over new to existing work are listed below and are shown on the drawings. The portion of the water treatment plant that is taken out of service for the cut-over operation must be returned to service within the duration specified on the drawings. The construction activities are listed in the order that allows the Contracting Officer to maintain drinking water plant production operations during construction and cut overs. Whenever cleaning, disinfecting and bacteriological testing are specified in a partial shutdown, these combined activities will consume a minimum of 72 hours of the allowable duration of the partial shutdown. Also, whenever cleaning and disinfecting is specified in a partial shutdown it requires cleaning and disinfecting new piping and equipment and existing adjacent piping and equipment to make sure that affected surfaces are cleaned, disinfected and free of pathogenic microorganisms. Whenever a seasonal restriction is identified for a partial shutdown on the drawings, it means that the associated construction activity cannot be conducted between May 1 and October 1 unless noted otherwise on the drawings.
(1) Partial Shutdown No. 1
(2) Partial Shutdown No. 2
(3) Partial Shutdown No. 3
SECTION 01 14 00 Page 2
(4) Partial Shutdown No. 4
(5) Partial Shutdown No. 5
(6) Partial Shutdown No. 6
(7) Partial Shutdown No. 7
(8) Partial Shutdown No. 8
(9)Partial Shutdown No. 9
(10) Partial Shutdown No. 10
(11) Partial Shutdown No. 11
(12) Partial Shutdown No. 12
(13) Partial Shutdown No. 13
(14) Partial Shutdown No. 14
(15) Partial Shutdown No. 15
(16) Partial Shutdown No. 16
(17) Partial Shutdown No. 17
(18) Partial Shutdown No. 18
(19) Partial Shutdown No. 19
(20) Partial Shutdown No. 20
(21) Partial Shutdown No. 21
h. Clean and disinfect the clearwells, transfer pump station wetwell and piping, weir chamber, 18-inch filter effluent headers, filter backwash piping, and influent and effluent piping from the clearwells. Conduct flushing and bacteriological sampling and testing of these structures and pipelines to confirm that bacteriological tests pass and these structures and pipelines are safe for drinking water service to the public.
i. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:
(1) Partial Shutdown No. 1
(2) Partial Shutdown No. 2
(3) Partial Shutdown No. 3
(4) Partial Shutdown No. 4
(5) Partial Shutdown No. 5
(6) Partial Shutdown No. 6
SECTION 01 14 00 Page 3
(7) Partial Shutdown No. 7
(8) Partial Shutdown No. 8
(9) Partial Shutdown No. 9
(10) Partial Shutdown No. 10
(11) Partial Shutdown No. 11
(12) Partial Shutdown No. 12
(13) Partial Shutdown No. 13
(14) Partial Shutdown No. 14
(15) Partial Shutdown No. 15
(16) Partial Shutdown No. 16
(17) Partial Shutdown No. 17
(18) Partial Shutdown No. 18
(19) Partial Shutdown No. 19
(20) Partial Shutdown No. 20
(21) Partial Shutdown No. 21
c. The water treatment plant will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations, as well as the construction activities specified in Subparagraphs 1.3.a through 1.3.g, inclusive of the partial shutdowns specified in Subparagraph 1.3.g.
The following conditions apply:
(1) Complete the construction activities specified in Subparagraphs 1.3.a through 1.3.f before starting Partial Shutdown No. 1 specified in Subparagraph 1.3.g.
(2) Secure access to the installation as the Contracting Officer is not responsible and will not be available to provide an escort.
SECTION 01 14 00 Page 4
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
1.4.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Additional Personnel Requirements
1.4.1.2.1 General Construction and Finish Work
General construction and finish work of the secure area must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Finish Work includes construction activities such as insulation, floor, partition, and ceiling systems; cabinet work; conveyor systems;
specialties; building furnishings, fixtures, and equipment; and mechanical and electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.
1.4.1.2.2 Electronic Security Systems Equipment
Electronic Security Systems equipment such as processing control units, workstations, field panels, sensors, high security locks, card readers, cable installation, and system programming, testing and training must be performed by U.S. companies using U.S. citizens who have been subjected to a trustworthiness determination.
1.4.1.3 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.4.1.3.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
SECTION 01 14 00 Page 5
Procedure includes:
a. Present a letter or official award document (i.e., DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.4.1.3.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.4.1.3.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.4.1.3.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
SECTION 01 14 00 Page 6
1.4.1.4 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.4.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., excluding Government holidays.
1.4.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 21 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.4.4 Exclusionary Period
No work associated with the partial shutdowns that are seasonally restricted as specified in Subparagraph 1.3.g may be performed during the period May 1 to October 1 of a calendar year throughout the duration of the contract, inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.
1.4.5 Occupied Buildings
The Contractor shall be working in existing buildings, around existing buildings, and on a site that are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the Building 12A, Building 12, Clearwell 1, Clearwell 2, Clearwell 3, and the Pump Room during the construction period.
1.4.6 Utility Cutovers and Interruptions
a. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
b. Interruption to water, sanitary sewer, storm sewer, telephone service, plant supervisory control and data acquisition system service, electric service, air conditioning, heating, ventilating, fire
SECTION 01 14 00 Page 7 suppression, fire alarm, compressed air, and filter backwash, filter surface wash water, filter effluent water, water supply to the high lift pumps, and influent and effluent water to and from clearwells are considered utility cutovers, pursuant to the paragraph WORK OUTSIDE
REGULAR HOURS.
c. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.
1.5 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II apply.
1.6 DISINFECTION REQUIREMENTS
Perform disinfection in accordance with the requirements specified in this Article whenever disinfection is specified elsewhere in the Specifications and required on the Drawings.
a. Provide labor, materials, equipment, tools, and incidentals required to disinfect the new Clearwell No. 1, new Clearwell No. 2, and new filter effluent, filter backwash, transfer pump discharge, clearwell influent, clearwell effluent, and potable water piping systems furnished and installed on this project.
b. Provide hypochlorites meeting AWWA B300 requirements.
c. Provide liquid chlorine meeting AWWA B301 requirements.
d. Perform bacteriological analyses in accordance with AWWA C652 and
AWWA C653.
e. Keep interior of clearwells, pipes, fittings, pumps, equipment, and appurtenance that will be in contact with filtered water, clearwell influent water, clearwell effluent water, filter backwash water, and potable water free of dirt, debris and foreign matter.
f. Clean the interior of clearwells, pipes, fittings, pumps, equipment, and appurtenance that will be in contact with filtered water, clearwell influent water, clearwell effluent water, filter backwash water, and potable water by flushing with potable water prior to conducting disinfection work.
g. Contracting Officer will provide water for flushing, however, Contractor to provide the necessary temporary piping, hoses, fittings, and appurtenances to connect to the Contracting Officer's water sources and those facilities to be cleaned and disinfected.
h. Coordinate with Contracting Officer on the cleaning, disinfecting and sampling of piping and facilities to be disinfected so that the Contracting Officer has ample time to prepare for the bacteriological testing. Notify the Contracting Officer a minimum of 5 days prior to planned disinfection work.
i. Clean and disinfect piping in accordance with the applicable sections of AWWA C651. The specific method used must be approved by the Contracting Officer.
SECTION 01 14 00 Page 8
j. Clean and disinfect clearwells in accordance with the applicable section of AWWA C652. The specific method used must be approved by the Contracting Officer.
k. Rinse interior surfaces of Clearwells 1 and 2 with special attention given to crevices, corners and other areas where solid material may collect. Convey rinse water to an onsite sanitary sewer.
l. Disinfect the clearwells in conjunction with leakage testing using a method specified in AWWA C652 and approved by the Contracting Officer.
Disinfection of the clearwells may be performed using either of the three methods contained in AWWA C652.
m. Collect water samples for bacteriological testing in the presence of the Contracting Officer. Store, handle and transport samples as instructed by the laboratory to protect the integrity of the samples.
Deliver samples to the laboratory and ensure that samples are analyzed within allowable hold times. Should initial disinfection not pass the Contracting Officer's bacteriological testing, then repeat the disinfection until passing results are obtained as determined by the Contracting Officer. Bacteriological testing must pass at least two consecutive tests on samples taken 24 hours apart. Provide testing results to the Contracting Officer immediately upon receiving results from the laboratory.
n. Clean and disinfect interior surface of the Clearwells 1 and 2, including floors, sumps, walls, ceiling, piping, pipe encasement, ladders, baffle walls, diffusion walls, access ways, hatches, and other appurtenances interior to the tanks.
o. Provide a written plan for disinfection on the project to the Contracting Officer for its review and approval prior to commencing disinfection.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 14 00 Page 9
SECTION 01 14 00 Page 10
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 3: 02/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This Contract requires the use of a cost-loaded Network Analysis Schedule (NAS). Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). Use Earned Value Report derived from cost-loaded NAS. Within 15 calendar days of Contract Award, prepare and deliver to the Contracting Officer a Earned Value Reportas directed by the Contracting Officer.Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.
1.3.2 Payment Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer.
Additionally, the Earned Value Report must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes
SECTION 01 20 00 Page 1 attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
1.3.3 Schedule Requirements for HVAC TAB
The field work requirements in Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC must be broken down in the Earned Value Report from the cost-loaded NAS by separate line items which reflect measurable deliverables. The value for each pay item listed below will be established on a case by case basis for each Contract. The line items are as follows:
a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. Submit the resulting findings to the Government to allow correction of the design. The progress payment will not be issued until the report is reviewed and approved.
b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.
c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).
d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.
e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.
f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. Compile this data into a report and submit to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.
SECTION 01 20 00 Page 2
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Earned Value Report from the cost-loaded NAS.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
i. Certified payrolls.
j. Updated testing logs.
k. Other supporting documents as requested.
1.5.2 Submission of Invoices
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
SECTION 01 20 00 Page 3
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR
32.103 Progress Payments Under Construction Contracts:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to…