PRICE SCHEDULE
Provide line item prices, where indicated by blank underlines, for the following items:
| Line Item |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Sub-Total |
| Total Price |
| 0001 |
| BASE PRICE: Total Price for the entire work for NAVSTA Great Lakes WTP Clearwell Repair/Replacement in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item. |
| 1 |
| EA |
| 0001A |
| Subtotal of Base Price for the entire work for the New Clearwell Substructure complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 2 |
| EA |
| 0001B |
| Subtotal of Base Price for the entire work for the New Clearwell Superstructure complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 2 |
| EA |
| 0001C |
| Subtotal of Base Price for the entire work for the Existing Clearwell Modifications, complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 1 |
| EA |
| 0001D |
| Subtotal of Base Price for the entire work for the Transfer Pump Station Substructure complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 1 |
| EA |
| 0001E |
| Subtotal of Base Price for the entire work for the Transfer Pump Station Superstructure complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 1 |
| EA |
| 0001F |
| Subtotal of Base Price for the entire work for the Transfer Pump Station Interior Work, complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 1 |
| EA |
| 0001G |
| Subtotal of Base Price for the entire work for the Transfer Pump Station Backwash Pump, complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 2 |
| EA |
| 0001H |
| Subtotal of Base Price for the entire work for the Transfer Pump Station Transfer Pump, complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 4 |
| EA |
| 0001I |
| Subtotal of Base Price for the entire project sitework, outside the facilities 5-foot line, for Paving, Site Prep, and Landscaping, complete in accordance with the drawings and specifications, but excluding work described in another line Item. |
| 1 |
| EA |
| 0001J |
| Subtotal of Base Price for the entire project sitework, outside the facilities 5-foot line, for Mechanical Utilities and Yard Pipe, complete in accordance with the drawings and specifications, but excluding work described in another line Item. |
| 1 |
| EA |
| 0001K |
| Subtotal of Base Price for the entire project sitework, outside the facilities 5-foot line, for Environmental Mitigation, complete in accordance with the drawings and specifications, but excluding work described in another line Item. |
| 1 |
| EA |
| 0001L |
| Subtotal of Base Price for the entire project, for Instrumentation and Controls, complete in accordance with the drawings and specifications, but excluding work described in another line Item. |
| 1 |
| EA |
| 0001M |
| Subtotal of Base Price for the entire project sitework, outside the facilities 5-foot line, for Electrical Work, complete in accordance with the drawings and specifications, but excluding work described in another line Item. |
| 1 |
| EA |
| 0001N |
| Unit Price for providing Clearwell structural crack repair as identified per Detail C4 on S-507 complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 1000 |
| LF |
| $_____ |
| $_____ |
| 0001O |
| Unit Price for providing Clearwell delamination repair as identified per Details B4 on S-507 complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 100 |
| SF |
| $_____ |
| $_____ |
| 0001P |
| Unit Price for providing Clearwell delamination repair as identified per Details A1 and A2 on S-507 complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 100 |
| SF |
| $_____ |
| $_____ |
| 0002 |
| Option Item No. 1: Price for providing all work in connection with the replacement of Valve 596, complete and in accordance with the drawings and specifications, but excluding valve and work provided in another Priced line item. |
| 1 |
| EA |