About this file

This document is Amendment 0004 to Solicitation N4008524R2534 for Design-Bid-Build (DBB) construction services for B14, New Stair/Life Safety/Power Improvements at the Portsmouth Naval Shipyard in Kittery, Maine. The amendment provides Pre-Proposal Inquiry (PPI) responses, revised drawings, and an updated wage determination. The key details include:

The proposal due date remains May 30, 2024 by 2:00 PM EDT. The contract is for a complete interior renovation of the 22,705 square foot historic Building 14, including hazardous material abatement, structural upgrades, new stairs and an elevator addition, utility system overhauls, and historic restoration work. The project also includes site improvements such as paving, walks, and utility work. The amendment provides clarifications and revisions to various technical specifications and drawings. A revised wage determination is included.

View the file

Other files

File Type Posted
Amendment 0007.pdf PDF
Amendment 006 - attachment 2- J and A Toilet Accessories .pdf PDF
Amendment 0006 - B14.pdf PDF
Amendment 006 - attachment 1 - J and A Interior Finishes.pdf PDF
Amendment 0005 - Attachment 1 - M503.pdf PDF
Amendment 0005 B14.pdf PDF
Amendment 0004 Attachment 1 M-502 for PPI 153.pdf PDF
Amendment 0004 attachment 2 Amendment Dwgs.pdf PDF
Amendment 0003 - Enclosure (2) for PPI 17.xlsx XLSX spreadsheet
Amendment 0003 B14.pdf PDF
Amendment 0003 - Enclosure (3) for PPI 101.pdf PDF
Amendment 0002 B14.pdf PDF
Amendment 0001 B14.pdf PDF
Amendment 0001 - Attachment 1 - Revised Drawings Specs .pdf PDF
Amendment 0001 - Attachment G- Price Proposal Form REV .docx DOCX document
Amendment 0001 - Attachment 2 - Site Visit Sign-in Sheet.pdf PDF
B14 Drawings - Volume 2_SBD_03-28-24.pdf PDF
N4008524R2534 B14.pdf PDF
Attachment E-Small Business Participation Commitment Document.docx DOCX document
B14 Specifications_SBD_03-22-24.pdf PDF
Attachment H - PIEE Vendor Access Instructions.pdf PDF
Attachment F - Small Business Subcontracting Plan (SBSP) Template.docx DOCX document
Attachment D- Historical Small Business Utilization.docx DOCX document
B14 Drawings - Volume 1_SBD_03-28-24.pdf PDF
Attachment G - Price Proposal Form .docx DOCX document
Attachment K - SF 5512 site visit .pdf PDF
Attachment A - Pre-proposal Inquiry Form.xls XLS spreadsheet
Attachment B - Construction Experience Project data sheet.docx DOCX document
Attachment C - Past Performance Questionnaire (Form PPQ).docx DOCX document
Attachment J - DBIDS Access Request Form.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

DESIGN-BID-BUILD (DBB), B14 NEW STAIR/LIFE SAFETY/POWER IMPROVEMENTS PORTSMOUTH NAVAL SHIPYARD (PNSY), KITTERY, MAINE.

The proposal due date remains 30 May 2024 NLT 1400 (EDT)

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Sarah Lorkiew icz; Email: sarah.m.lorkiew icz.civ@us.navy.mil Phone: 757-341-0070

1. CONTRACT ID CODE PAGE OF PAGES

J 1 25

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-May-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008524R2534

X 9B. DATED (SEE ITEM 11)

28-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-May-2024

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008524R2534

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0004

The purpose of this amendment is to provide the following:

1. Pre-Proposal Inquiry (PPI) Responses

2. Revised Drawings

3. Updated Wage Determination

ATTACHMENTS:

1. Amendment 0004 – Attachment 1- M-502 for PPI #153

2. Amendment 0004 – Attachment 2 – Revised Drawings

Question # Reference

Page Section Paragraph

Question Government Response

Bid form Option 4 - security detail monitoring... Please confirm how the contractor complies with security detail monitoring if this requires payment to government employees directly.

On Sheet G-005, Site Constraints and Requirements Plan - Phase 1, in Security Note 6, delete "Pay Fees for the Security Detail."

"Government will handle payment of security monitoring fees, if incurred.

Given the size and complexity of this project, we request that

NAVFAC extend the proposal due date to 28 June 2024, to allow proposers adequate time to prepare their estimates and proposals.

Given the current active construction market in the region, this will provide the Govt. with the best opportunity for competition and awardable price/proposal.

Amendment 0003 provided an extension to May 30th, 2024. No additional extensions are anticipated at this time.

124 G-006 Please clarify between the 90-days and 42-days noted in the referenced Phase Note.

The outage to the railroad tracks and Phase 2 conditions will be limited to 42 days.

The Government will identify a 90-day window (during construction) during which the 42-day railroad outage and Phase 2 conditions can occur. The Contactor will determine the 42-day period during the identified 90-day window.

125 G-006

Please clarify the requirements in the referenced Phasing Note, relative to work that must be performed during a weekend vs.

the outage timeframes noted in

Phasing Note 1. It appears that the referenced work is outside of the Fire Department Access Lane.

There is work that extends outside of the Contractor

Staging and Storage area that must be completed during a weekend.

126 G-006 01 14 00.00 22

Drawing G-006 shows the Fire Department Access Lane at 30' wide. Specification Section 01 14 00.[00] 22, Par. 1.12.2.1, calls for a minimum 20' fire lane. Please confirm that a 20' minimum fire lane is acceptable to facilitate work.

"A 30-foot fire lane as shown on Sheets G-005 and G-006 is required.

In Specification Section 01 14

00.00 22, Paragraph 1.12.2.1, change "Twenty (20)" to "thirty (30)".

127 G-007 Please define timeframe for

"Heating Season".

Approximately 15-Sept through 15-May.

09 68 00 09 65 00 03 33 00

It is recommended that the DOR consider adding an admixture such as Specialty Products Group, Vapor Lock, to new concrete slabs that are to receive adhesive applied flooring, to mitigate potential residual moisture issues impacting flooring installation and project schedule.

Adding an admixture to new concrete slabs to mitigate potential moisture issues will not be part of the project. The project slab work consists of a series of patches on the ground floor in the existing building and new slabs in the addition. Having a patchwork of non-treated and treated slabs in the existing building would not be effective and the project schedule is long enough to not be a concern for slabs in the addition.

129 12 00 01.00 20 3.1.1.1 Please identify the A/E's Interior

Designer

Oak Point Associates of Biddeford, Maine and

Portsmouth, NH, provided the interior design.

130 21 12 00 1.7.1.7

We request that the first sentence "Within 36 days of contract award but no less than 14 days prior to commencing work on site, the

Contractor must submit the Preconstruction Submittals for review and approval." be removed.

The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement and installation, to support the project.

However, 36-days following contract award is not realistic, particularly given where Standpipe Systems work falls in the sequence of the project.

It should be understood that this clause is in regard to SD- 01 Preconstruction Submittals such as Fire Protection Engineer and equipment installer qualifications, etc. It is not the intent for SD-02 and subsequent submittals to be submitted within this timeframe.

131 21 13 13 1.6.1.1

We request that the first sentence "Within 36 days of contract award but no less than 14 days prior to commencing work on site, the

Contractor must submit the Preconstruction Submittals for review and approval." be removed.

The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement and installation, to support the project.

However, 36-days following contract award is not realistic, particularly given where Wet Pipe Sprinkler Systems work falls in the sequence of the project.

It should be understood that this clause is in regard to SD- 01 Preconstruction Submittals such as Fire Protection Engineer and equipment installer qualifications, etc. It is not the intent for SD-02 and subsequent submittals to be submitted within this timeframe.

132 21 13 16 1.6.1.1

We request that the first sentence "Within 36 days of contract award but no less than 14 days prior to commencing work on site, the

Contractor must submit the Preconstruction Submittals for review and approval." be removed.

The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement and installation, to support the project.

However, 36-days following contract award is not realistic, particularly given where Dry Pipe Sprinkler Systems work falls in the sequence of the project.

It should be understood that this clause is in regard to SD- 01 Preconstruction Submittals such as Fire Protection Engineer and equipment installer qualifications, etc. It is not the intent for SD-02 and subsequent submittals to be submitted within this timeframe.

133 23 03 00.00 20 1.10.1 Please provide ATFP Standard

Requirements.

The requirements can be found in UFC 4-010-01, DoD

Minimum Antiterrorism Standards for Buildings

134 23 05 48.00 40 1.2

We request that the first part of the first sentence "Within ten working days of Contract award," be removed. The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement and installation, to support the project.

However, 10-days following contract award is not realistic, particularly given where HVAC Piping and Equipment work falls in the sequence of the project.

"What is a reasonable time frame?

In Specification Section 23 05

48.00 40, Paragraph 1.2, in the first paragraph, change

"Within ten working days of Contract Award" to "sixty days prior to installation".

135 23 05 48.00 40 1.2

We request that the first part of the second to last paragraph "Five 30 working days," be removed. The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement and installation, to support the project. However, neither five nor 30-days following contract award are realistic, particularly given where HVAC Piping and Equipment work falls in the sequence of the project.

"This paragraph sets a timeframe for when submittals need to be provided prior to installation, not after contract award. That timeframe is 30 days.

48.00 40, Paragraph 1.2, in the second to last paragraph, delete "Five".

136 23 05 93 1.5.4.1

We request that the timeframes for the following submittals be modified:

- TAB Agency & Personnel

Qualifications: 45-days after contract award is not realistic, especially given when TAB work will occur in the project sequence.

We recommend this timeframe be removed. It is understood that this needs to be completed to facilitate successor activities.

- Pre-DALT/TAB Meeting: In lieu of 30 calendar days after qualifications approval, we recommend this be changed to 30-days prior to scheduled

DALT/TAB.

The timeframe for the submittals of qualifications will be modified as follows:

93, Paragraph 1.5.4.1, in the first sub-paragraph of the first paragraph, change "Within 45 calendar days after the date of contract award" to "No less than 90 calendar days prior to commencing DALT/TAB".

The time from for the Pre- DALT/TAB Meeting will remain as is.

137 23 05 93 1.5.4.1

It is not likely that a Season 2 TAB effort would fall within the

Contract Duration. Please confirm that simulation of alternate season conditions is allowable, given HVAC equipment capability.

"This is acceptable for TAB but not for commissioning.

System will need to be commissioned in season 2 seventh sub-paragraph of the second paragraph, add "or when Season 2 temperatures can be simulated," between "limits," and "accomplish".

138 23 05 93

Pre-Field DALT Preliminary Notification timeline in 1.5.4.3 differs from the notification period in 1.5.4.1. Please clarify.

For the pre-field DALT Preliminary Notification, notify the Contracting Officer in writing within 7 calendar days after completion.

fourth sub-paragraph of the first paragraph, change "5" to "7".

23 05 93 23 30 00

Section 23 05 93, Par. 1.6, calls for a 2-year DALT/TAB Warranty plus a "2-year contractor installation warranty". Section 23 30 00 does not appear to include a requirement for a 2-year contractor installation warranty. Please clarify.

A 2-year contractor installation warranty will be required contractor mechanical systems installation.

93, add Paragraph 1.6 as follows:

1.6 WARRANTY

Furnish workmanship and installation warranty for the mechanical system installation work performed for a period not less than 2 years from the date of Government acceptance of the work; issued directly to the Government. Include provisions that if within the warranty period the system shows evidence of major performance defects, deterioration, or is significantly out of tolerance, the corrective repair or replacement of the defective materials and correction of the defective workmanship is the responsibility of the mechanical contractor.

Perform corrective action that becomes necessary because of defective materials and workmanship while systems are under warranty 7 days after notification, unless additional time is approved by the Contracting Officer.

Failure to perform repairs within the specified period of time constitutes grounds for having the corrective action and repairs performed by others and the cost billed to the mechanical contractor.

140 27 32 50 1.5.1.1

We request that the first part of the first sentence "Within 36 days of Contract award but not less than 14 days prior to commenting any work on site," be removed. The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement. 36-days for this activity is not realistic especially given where Elevator Landing

Two-Way Communication System work will fall in the project sequence.

"It should be understood that this clause is in regard to SD- 01 Preconstruction Submittals such as Fire Protection Engineer and equipment installer qualifications, etc. It is not the intent for SD-02 and proceeding submittals to be submitted within this timeframe. In this section, the qualifications of the Qualified

Professional Engineer are required to be approved prior to submitting design submittals.

In Specification Section 27 32 50, in Paragraph 1.4, prior to "SD-02 Shop Drawings", add

"SD-01 Preconstruction Submittals" with a sub-line that reads "Qualified Professional Engineer (QPE);

G", and in "SD-07 Certificates", delete

"Qualified Professional Engineer (QPE); G." In

Paragraph 1.5.1.1, in the first sentence, change "following" to "qualifications of the QPE"

141 27 32 50

Will the Qualified Professional Engineer (QPE) called for in 27 32

50 be permitted to also be the Registered Fire Protection

Engineer (FPQC) called for in 01 45 00.00 22 or the Qualified Fire

Protection Engineer (QFPE) called for in Section 28 31 76?

The QPE called for in Specification Section 27 32

50 must meet the qualifications required in that section. If they also meet the same qualifications required in the other sections, or vice versa, the one individual can be used.

142 28 31 76 1.11.1.1

We request that the first part of the first sentence "Within 36 days of Contract award but not less than 14 days prior to commenting any work on site," be removed. The balance of the clause is understood and it is understood that submittals must be provided in a timely manner to allow for review, procurement. 36-days for this activity is not realistic especially given where Fire Alarm System work will fall in the project sequence.

It should be understood that this clause is in regard to SD- 01 Preconstruction Submittals such as Fire Protection Engineer and equipment installer qualifications, etc. It is not the intent for SD-02 and subsequent submittals to be submitted within this timeframe.

143 31 23 00.00 22 1.5.2.a.14 Please identify the disposal facilities preapproved by Code 106.3.

Pre-approved Waste Management facilities for non-hazardous soils are Turnkey Landfill and

Norridgewock.

144 31 23 00.00 22 3.1.2.2

Given the limited site area, it is unlikely that groundwater that may be encountered will be able to be practically re-infiltrated within the project footprint. Please identify parameters for discharging groundwater into PNSY storm drain system.

Dewatering must be in accordance with Specification

Section 31 23 00.00 22, 3.1.2.2.

145 AE641

Please advise if coating of the elevator pit and/or walls is desired.

No, a coating in the elevator pit or shaft walls is not required.

146 AE442

Please advise if an elevator pit ladders is desired.

Yes, an elevator pit ladder is to be provided. See Keynote 8 on Sheet SB101 and Detail

C5/SB502.

147 HM101

Plan HM101 is note 18 - asbestos joint compound referring to all walls on the page or only where the note is pointing?

For the second floor it is basically both. The only wall that is to be removed on the second floor where Keynote

18 does not apply is the westernmost wall of Stair 002 (only Keynote 12 is pointing to this wall). On the first floor Keynote 18 only applies to the walls it is pointing to.

148 HM101

Plan HM101 the lead paint removal notes: Does all the paint get removed or just intacted?

Would you want the painter to perform this work?

It is not clear what is meant by "intacted" in the question, however, the HM sheets indicate where lead paint is to be removed on surfaces to remain. Lead paint on surfaces to be removed can be removed with the substrate.

See Specification Section 02 83 00.00 22, paragraph 1.2.8 for personnel qualification requirements.

149 AE104

Plan AE104, Room 402 calls for CPT-1 & SVT-1. However, there are no delineation lines. cannot locate a plan that shows the breakdown.

SVT 1 is to be provided in front of the galley/countertop area. See Sheet AE641, Room Finish Schedule Note 11 and plan detail B4/AE810.

150 AE101

Are all the cell phone lockers salvaged? Note #1 says to reinstall the salvaged cell phone lockers and Note 6 just list Cell phone lockers. Are these new lockers?

Note 10 – Recessed Storage Box – are these new items or salvaged?

Keynote 1 on Sheet AE101 indicates that the four existing cell phone lockers that are to be salvaged from existing ATM Lobby 123 (See

Removals Keynote 27 on AD101) are to be reinstalled in Vestibule 116. Keynote 6 on Sheet AE101 indicates two new cell phone lockers are to be installed in ATM Lobby

119. Keynote 9 on Sheet AE101 and Detail B4/AE741 indicate that the ten salvaged storage boxes from existing Corridor 100 (See Removals Keynote 28 on AD101) are to be reinstalled in the east wall of Corridor 112. Keynote 10 on Sheet AE101 and Detail A1/B741 indicate that four new storage box units are to be installed in the west wall of Corridor 112.

On Sheet AE101, First Floor Plan, in Keynote 9, change

"4" to "10".

151 MP101

Drawing MP101, keynote 3 references drawing M503 detail C2. This detail is not included, please provide detail.

The correct detail reference is C2/M-502.

On Sheet MP101, First Floor Mechanical Piping Plan, in

Keynote 3, change "C2- M503" to "C2/M-502".

On Sheet M-502, Mechanical

Details 2, in Detail C2, change the detail call out bubble from "A4/M-502" to "C2/M-504".

152 MP101

Drawing MP101 indicates HPS from Mech 101 to Mech 104, but detail A2 on same drawing indicates LPS. Please advise.

The pressure reducing station is to be provided in Mech

101, so the steam piping will be low pressure (LPS) from

Mech 101 to Mech 104.

Detail A2/MP101 has the piping labelled correctly.

On Sheet MP101, First Floor Mechanical Piping Plan, in the First Floor Mechanical Piping Plan, in the piping shown between Mech 101 to Mech 104, change the two instances of "HPS" to "LPS", and the two instances of

"COND" to "PC".

153 MP101

Drawing MP101, please provide detail for exterior CHW pipe supports.

See Detail B5 on attached revised Sheet M-502.

On Sheet M-502, Mechanical

Details 2, add Detail B5, Ground Mounted Pipe

Support Detail.

Plumbing drawings in general, many pipe sizes are either not indicated or appear to be incorrect throughout. Please provide a riser diagram similar to the sanitary riser diagram to assist in determining missing pipe sizes, or potential incorrect sizes.

All piping size is initially identified. Assume pipe size remains as indicated until indicated otherwise. See part plans for piping sizes not indicated on larger plans.

PPI#[16] - Only one known person in the eastern united states has this certification. With the amount of professionals already associated it seems unnecessary to add an impossible requirement. Will the government please consider an alternate certification or qualification for this role?

A search on the ICC website found multiple individuals in the New England area with the required certification.

PPI#20 appears to be the reference for all 'delegated design' as is referenced in later PPI. What is meant by 'studs, or other product data for the items being submitted'?

The “studs or other products” listed in PPI 20 will be items as selected by the delegated designer to complete their design so that the submittal package can be reviewed in its entirety.

PPI#24 - 'SHPO approval which may require an extended review time'. What length of review can be expected for SHPO approval?

SHPO approval will take up to 45 days. Note however, that there is nothing in the current scope that requires further SHPO approval.

PPI#28, 29, 30 - Response indicates the contractor is responsible to be 'aware of any codes and ordinances that affects the completion of work'. Will this awareness include any scope not shown on the documents? Will the contractor be responsible for identifying missing scope found in a separate code or standard?

The documents follow applicable codes and ordinances, and no extra scope is expected to be required. However, if the contractor becomes aware of non-compliant or missing scope based on applicable codes and ordinances, this should be brought to the attention of the Contracting Officer.

PPI#36 - It is understood that B13 will have full ownership, however, this may severely impact the B14 contractor's ability to store materials, navigate, coordinate with FD and build. How should this contract plan for the breadth of this impact?

As described in the contract documents; other construction projects and/or Shipyard work in the vicinity of Building 14 will be ongoing concurrently with the Building 14 construction period and could impact Building 14 construction activities. Once the contract is awarded, construction schedules for these projects will be provided to the Contractor by the Government upon request;

Parking and laydown space on the site is limited to the area shown on the plans.

Manage the on-site work including equipment, storage trailers, material, material deliveries to allow the work to be completed within the specified Contract duration.

This may require the Contractor to locate suitable storage off-site and multiple equipment mobilizations to allow the work to be completed. Equipment or materials not used to complete the work must be removed from the site. If additional offsite storage, additional mobilization or demobilizations are required, all costs must be included in the base bid. Failure to plan the work based on the space limitations must not be the basis for any claim nor an equitable price or Contract time adjustment.

PPI#39 - Security Note 3 - Can the government confirm specific examples of the temporary measures acceptable to security operations?

Refer to UFC 4-022-03 for requirements.

G-005 Security Note 6 - How would the contractor pay a government employee for the security detail?

Government will handle payment of security monitoring fees, if incurred.

See response to PPI #79.

G-005 Security Note 7 - Can the government confirm these lighting levels exist currently at the pedestrian control points and clear zones?

Yes. Weekly inspections are conducted to monitor the perimeter and lighting levels.

PPI#57 - It is understood the contractor is required to provide an engineered system for fire alarm. Will the contractor be responsible for the overall code compliance of the system shown in the contract documents? Will the contractor be responsible for any scope required per code but not shown?

Yes, the contractor is responsible for the overall code compliance of the system. The Contractor is responsible for providing a full fire alarm/mass notification system complying with the applicable UFC and NFPA codes. This includes both design, installation, and system inspection and testing.

PPI#58 - 01 45 00 referers to FPQC and QFPE in the same paragraph (1.5.8.2). Are all references to UFC and QFPE to be replaced by 01 45 00 FPQC?

Yes. Per the response to PPI#58, the QFPE references as outlined in Specification Sections 21 12 00, 21 13 13, 21 13 16, and 28 31 76, should be considered as references to the FPQC in Specification Section 01 45

00.00 22. It is not the intent to have multiple or redundant

FPQC and QFPEs. The UFC references still apply.

PPI#58 - 01 45 00 referers to FPQC and QFPE in the same paragraph (1.5.8.5) 'which must be signed and sealed by the QFPE'.

Are all references to UFC and

QFPE to be replaced by 01 45 00 FPQC? Who is the QFPE the

FPQC will submit this document for signature?

Per the response to PPI#58, the QFPE references as outlined in Specification

Sections 21 12 00, 21 13 13, 21 13 16, and 28 31 76, should be considered as references to the FPQC in Specification Section 01 45

00.00 22. It is not the intent to have multiple or redundant

FPQC and QFPEs. The UFC references still apply. The FPQC, who is part of the

Contractor’s team, will need to sign and seal the certification of successful

Pre-Final Acceptance testing and submit that to the

Government.

The specifications seem to be conflicted with the references to

DFPE, FPQC, QFPE, FPE

throughout. Can the government confirm who is responsible for providing these roles and what their responsibilities are?

The DFPE is the NAVFAC FPE. Other references to FPE’s, QFPE’s, FPQC’s, should be considered as references to the FPQC in Specification Section 01 45

00.00 22. It is not the intent to have multiple or redundant

FPQC and QFPEs.

PPI#59 - Response is the contractor is responsible to be

'knowledgeable of NFPA 101 as it affects the completion of the work'. How does the knowledge of NFPA 101 affect the completion of the work?

PPI #59 referenced Specification Section 26 51

00, Paragraph 3.3.1, Commissioning. The contractor is responsible to be knowledgeable of applicable codes (including NFPA 101) and standards when performing the commissioning of the lighting system. Lighting system scope is shown on the drawings and in the specifications.

PPI#62 - Response says to provide products IAW NECA, BICSI, TIA, NFPA and UL requirements.

Please confirm this statement should also include the following:

as specified and incorporated into the design documents.

Provide products per applicable NECA, BICSI, TIA, NFPA and UL requirements according to the scope of work indicated on the drawings and in the specifications.

PPI#62 - Response says to provide products IAW NECA, BICSI, TIA, NFPA and UL requirements.

Can the government confirm if any scope included in a code/standard and not shown on the documents will be the responsibility of the contractor?

Provide products per applicable NECA, BICSI, TIA, NFPA and UL requirements according to the scope of work indicated on the drawings and in the specifications.

PPI#69 - It is not recommended to provide flat panels without additional ribs to avoid unsightly oil canning. Can the government confirm if additional measures have been taken in the design to avoid this phenomenon?

Provide panels as specified.

The panels are insulated panels so they will be more rigid than a flat piece of metal. If manufactured and installed correctly, there should be no concern for oil canning.

PPI#91 - Response indicates the contractor is responsible for designing the supports. Will the government be revising their structural design documents to incorporate any changes to the girt system stemming from the contractor's evaluation? Will the contractor be responsible for the cost/time associated with this level of design coordination?

The backup wall system is designed to for the anticipated out of plane wind loads. The contractor is responsible for the design of the support system to attach to the CMU.

PPI#91 - Response indicates the contractor is responsible for designing the supports. Can the government confirm the current girt design meets or exceeds available manufacturer's structural attachment requirements?

See the response to PPI 91 above. The contractor is responsible for designing the girts. The specification section has been modified.

PPI#91 - Response indicates the contractor is responsible for designing the supports. Can the government confirm if the alignment tolerances have been coordinated in the design documents to accommodate larger tolerances such as ACI?

The backup wall system has been designed to meet the tolerances of the ACI. The contractor designed support system needs to be designed to accommodate those tolerances.

PPI-#92 - The government needs 30 days prior to working in the clear-zone and to 'coordinate with the contracting officer to obtain approval from the head of security operations (code 1122). How long after the 30 days will it take for contracting officer and head of security operations to approve the work?

The intent is for the work to be reviewed/approved within the 30-day window.

175 2-002

Photographic documentation is required for existing wood floor framing prior to the start of the

Jacking process. Will the contractor be required to be accompanied by a government / shipyard official during the photo documentation process?

No, an escort is not required, however a Shipyard photography pass must be obtained and all photography requirements therein must be followed.

176 AE516

Wall Section Detail A5/AE516 has material not specified under non-shrink grout. Please confirm if this is existing or what material is to be installed.

Non-shrink grout is specified in Specification Section 03 30

00, paragraph 2.4.2, and in Specification Section 05 12

00, paragraph 2.4.2.

177 AE601

Door schedule shows detail C3A/AE602. Please provide

Detail

"The correct detail for Doors E07 and E08 is A3/AE602.

On Sheet AE601, Door Schedule, in the Door

Schedule, for First Floor

Doors E07 and E08, change "C3A/AE602" to

"A3A/AE602", change "C3B/AE602" to

"A3B/AE602", and change "C3C/AE602" to

"A3C/AE602".

178 AE104

On AE104, only 2 of the 24 windows have Keynote 9 designating painting the interior wood window including jambs, casing, and trim. Do the remaining 22 windows on the 4th floor require paint as well?

No. The remaining windows were recently renovated in

2017.

AE103

AE104

On AE103, AE104, the elevator lobby references detail C4/AE502, C4 is not found on AE502.

The correct detail is

C3/AE502.

On Sheets AE101, First Floor Plan; AE102, Second Floor Plan; AE103; Third Floor Plan; and AE104, Fourth

Floor Plan, at the detail call out bubbles for where the exterior walls of the connector intersect with the exterior walls of the stair tower addition, change "C4" to "C3".

180 AE104

On AE104, Keynote 15 designating new metal studs where missing is indicated on the drawings in one locations only. Is this a typical note or is this only required at the location indicated?

It only required at the particular area where indicated (at window

14N4D/14N4C). The intent is to make this currently unfinished window area to match the window area which were renovated in the 2017 project.

Did the government take into consideration in the 582 days the potential schedule impact in jacking the floors as depending on the deflection it may take over a month per floor to level and avoid any cracking or damage?

Refer to the last sentence of General Bid Note b. on the price proposal form.

Please provide [an] estimate of how much deflection is in the floors to be jacked.

The floor deflection varies from as little as 1/2 inch to as much as 1-1/4 inch.

183 AE401 10 28 13

Toilet room accessory schedule on AE401 call out grab bars as 1-1/2" diameter, spec section 10 28 13, 2.2.1, calls for 1-1/4" dimater grab bars. Which is correct?

"1-1/2 inch is correct.

In Specification Section 10 28 13, Paragraph 2.2.1, change

"1-1/4" to "1-1/2".

184 01 35 26.00 22 1.7.1.5

Section 1.7.1.5 Dredging Contract Requirements in specification section 01 35 26.00 22 - Governmental Safety

Requirements references a Collateral Duty Safety Officer being required for any dredging work on site. It appears the only other section this individual is referenced is in 1.7.3.2 - Safety Meetings. Will the Government please confirm that this role is not required on this project?

There is no dredging in the project. There is no requirement for a Collateral Duty Safety Officer.

In Specification Section 01 35

26.00 22, delete Paragraph

1.7.1.5 and its subparagraphs in their entirety, and in Paragraph 1.7.3.2, in the third sentence, add "or" between

"supervisors," and "foremen", and delete ", or Collateral

Duty Safety Officer's (CDSOs)".

185 AE401

Detail A1 on AE401 has a missing wall type label behind the lavatory, what wall type is this?

"Wall Type NF. The intent is for metal studs with one layer of gypsum board be provide as a chase for the lavatory plumbing in front of the Type XA wall against the exterior.

Note that behind this plumbing chase wall the 2x3 wood furring, 1-1/2 inch mineral fiber insulation, and 5/8 inch gypsum board of the

Type XA wall type do not need to be provided.

On Sheet AE401, Enlarged

Toilet Room Plans and Interior Elevations 1, in

Detail A1, Men 209 Enlarged Floor Plan, in the wall type indicator at the lavatories along the east exterior wall, change "--" to "NF" and shorten the line of the indicator so that it ends at the middle line.

186 10 55 00

Specification section 10 55 00 references postal specialties, however, these are not identified on the plans. Where are the postal specialties found?

Specification 10 55 00 is for the storage box units to be provided in Corridor 112.

Please confirm this is not a Tax- Exempt project. If it is Tax-

Exempt, will the Government please provide any proper documentation or certification required for this status.

It is the responsibility of the KTR to confirm the State's requirements and acquire/complete the proper documentation for exemption.

The Government will sign the paperwork prepared by the

KTR.

Please define the requirements for masonry restoration, what is required, just tuckpointing?

Should only 20% of the brick be cleaned? This may cause noticeable discolorations between areas.

It is anticipated that 20% of the mortar joints will need repointing.

Please clarify CLINS. 001, 002, 003 and 004 shown on G-003A as well as with the keynotes do not align with the bid form. For example 002 in the drawings shows utility improvements and on the bid form it is FF&E

The bid form description column identifies which

CLIN option each item refers to and correlate to G-003A.

Drawings

These Revised drawings accompany this amendment.

SHEET G-004 – CONSTRUCTION SEQUENCE STRATEGY

1. In Electrical Service Sequence Notes 4 and 6, change “GATE” to “GATES”.

2. Replace Electrical Service Sequence Note 5 in its entirety with the following:

“A: AT MANHOLE AC 325, DISCONNECT EXISTING #4/0 CONDUCTORS (FEEDING B14) THAT

ARE TAPPED FROM EXISTING #500 KCMIL CONDUCTORS FEEDING B76S. THIS WILL

REQUIRE AN OUTAGE FOR B14 (AND ASSOCIATED PEDESTRIAN ACCESS POINTS, GATES,

AND POB) AND B76S. CIRCUIT BREAKER LC4-24 WILL NEED TO BE SHUT OFF. WHEN #4/0

CONDUCTORS SERVING B14 ARE DISCONNECTED, PROVIDE HEAT SHRINKABLE SPLICES

TO EXISTING B76S CONDUCTORS TO RESTORE CONTINUITY. CLOSE CIRCUIT BREAKER

LC4-24 TO RESTORE POWER TO B76S.

B: AT MANHOLE AC 325, DISCONNECT EXISTING 3 - #2 CONDUCTORS (FEEDING THE GATE)

TAPPED FROM EXISTING 4/0 CONDUCTORS. REMOVE EXISTING #2 CONDUCTORS FROM

MANHOLE AC 325 TO SUPPLY SIDE OF EXISTING GATE DISCONNECT SWITCH. REFER TO

SITE PLAN THIS SHEET FOR LOCATION OF GATE DISCONNECT SWITCH. PROVIDE 3 #2 + #2

G CONDUCTORS IN EXISTING 2-INCH UNDERGROUND DUCT FROM MANHOLE AC 325 TO

GATE DISCONNECT SWITCH.

C: AT MANHOLE AC 325, PROVIDE 3-#2 + #2G CONDUCTORS AND TAP THE FIRST SET OF

#500 KCMIL CONDUCTORS FEEDING B14. CONNECT TAP CONDUCTORS TO THE #2

CONDUCTORS FEEDING THE GATE DISCONNECT SWITCH.”

3. In Electrical Service Sequence Note 9, after the last sentence, add the following sentence:

“PROVIDE 3-#2 + #2G CONDUCTORS AND TAP THE SECOND SET OF #500 KCMIL

CONDUCTORS FEEDING B14. CONNECT TAP CONDUCTORS TO THE #2

SHEET G-009 – OUTAGE SCHEDULE

1. In Row E2 of the Outage Schedule, add “AND GATES” after “(POB)” in the Item column and after

“POB” in the Purpose column.

2. In Row E4 of the Outage Schedule, add “SETS OF” between “NEW” and “CONDUCTORS” in the

Purpose column.

3. In Row E5 of the Outage Schedule, delete “ONE CONTRACTOR FEDERAL” and add

“CONDUCTORS” after “(TAPPED)” in the Purpose column.

SHEET E-001 – ELECTRICAL SYMBOLS, ABBREVIATIONS AND GENERAL NOTES

1. In the Receptacles Electrical Symbols, change “PLUG MOLD” to “STEEL MULTI-OUTLET

ASSEMBLY, RECEPTACLES SPACED AT 6” ON CENTER.”

SHEET ED101 – FIRST AND SECOND FLOOR ELECTRICAL REMOVALS PLANS

1. Add General Sheet Note 2 to read “REFER TO MECHANICAL AND PLUMBING DRAWINGS FOR

EXISTING HVAC AND PLUMBING EQUIPMENT BEING REMOVED. REMOVE ASSOCIATED

DISCONNECT SWITCHES, STARTERS, WIRING, AND CONDUIT BACK TO THE SOURCE.”

2. In Keynote 2, add “, DROP BAR ARM GATES, SLIDE GATES,” between “POINTS” and “AND”.

3. In Keynote 10, add “, DROP BAR ARM GATES, SLIDE GATES,” between “POINTS” and “AND”.

SHEET ED102 – THIRD AND FOURTH FLOOR ELECTRICAL REMOVALS PLANS

1. Add General Sheet Note 2 to read “REFER TO MECHANICAL AND PLUMBING DRAWINGS FOR

EXISTING HVAC AND PLUMBING EQUIPMENT BEING REMOVED. REMOVE ASSOCIATED

DISCONNECT SWITCHES, STARTERS, WIRING, AND CONDUIT BACK TO THE SOURCE.”

SHEET ED501 – ONE-LINE DIAGRAM - REMOVALS

1. Add Removals Keynote 3 to read “DISCONNECT EXISTING 3 - #2 CONDUCTORS (FEEDING THE

EXISTING GATE) TAPPED FROM EXISTING 4/0 CONDUCTORS. REMOVE EXISTING #2

CONDUCTORS FROM MANHOLE AC325 TO SUPPLY SIDE OF EXISTING GATE DISCONNECT

SWITCH. REFER TO ES101 FOR LOCATION OF GATE DISCONNECT SWITCH.”

2. In Detail A2, One-Line Diagram – Removals:

a. At Manhole AC 325, add Removals Keynote 3 to and indicate the removal of the existing tap conductors to the gate disconnect switch.

b. At Panel 2A, add Removals Keynotes 1 and 2 at the Line Tap between Panel 2A and Panel 2, and indicate that Panel 2A feeds gates and 208V POB circuit.

3. In Keynote 1, add “PROVIDE A 30A, 2P CIRCUIT FOR GATES AND A 30A, 2P CIRCUIT FOR 208V

POB CIRCUIT.” between the third and fourth sentences.

SHEET ES101 – ELECTRICAL SITE PLAN

1. In Phasing Notes 6 and 8, change “GATE” to “GATES”.

2. Replace Phasing Note 7 in its entirety with the following:

“7A: AT MANHOLE AC 325, DISCONNECT EXISTING #4/0 CONDUCTORS (FEEDING B14) THAT

ARE TAPPED FROM EXISTING #500 KCMIL CONDUCTORS FEEDING B76S. THIS WILL

REQUIRE AN OUTAGE FOR B14 (AND ASSOCIATED PEDESTRIAN ACCESS POINTS, GATES,

AND POB) AND B76S. CIRCUIT BREAKER LC4-24 WILL NEED TO BE SHUT OFF. WHEN #4/0

CONDUCTORS SERVING B14 ARE DISCONNECTED, PROVIDE HEAT SHRINKABLE SPLICES

TO EXISTING B76S CONDUCTORS TO RESTORE CONTINUITY. CLOSE CIRCUIT BREAKER

LC4-24 TO RESTORE POWER TO B76S.

7B: AT MANHOLE AC 325, DISCONNECT EXISTING 3 - #2 CONDUCTORS (FEEDING THE

GATE) TAPPED FROM EXISTING 4/0 CONDUCTORS. REMOVE EXISTING #2 CONDUCTORS

FROM MANHOLE AC 325 TO SUPPLY SIDE OF EXISTING GATE DISCONNECT SWITCH. REFER

TO SITE PLAN THIS SHEET FOR LOCATION OF GATE DISCONNECT SWITCH. PROVIDE 3 #2 +

#2 G CONDUCTORS IN EXISTING 2-INCH UNDERGROUND DUCT FROM MANHOLE AC 325 TO

GATE DISCONNECT SWITCH.

7C: AT MANHOLE AC 325, PROVIDE 3-#2 + #2G CONDUCTORS AND TAP THE FIRST SET OF

#500 KCMIL CONDUCTORS FEEDING B14. CONNECT TAP CONDUCTORS TO THE #2

3. In Phasing Note 11, after the last sentence, add the following sentence: “PROVIDE 3-#2 + #2G

CONDUCTORS AND TAP THE SECOND SET OF #500 KCMIL CONDUCTORS FEEDING B14.

CONNECT TAP CONDUCTORS TO THE #2 CONDUCTORS FEEDING THE GATE DISCONNECT

SWITCH.”

4. In the Electrical Site Plan, add the location of existing gate disconnect switch and transformer near the southeast corner of Bldg 45.

SHEET EP101 – FIRST FLOOR POWER PLAN

1. Add Keynote 25 to read “REFER TO SHEET CX101 FOR LOCATIONS OF EXISTING DROP-BAR

ARM GATES.”

2. Add Keynote 26 to read “REFER TO SHEET ES101 FOR LOCATION OF POB.”

3. In the First Floor Power Plan:

a. Add Keynote 25 and a circuit for Drop Bar Access Gates at the north side of the building.

b. Add Keynote 26 and circuit for 208V POB circuit located at the north side of the building.

c. Move panelboard P1A north on the west wall of Elec 110 to avoid steel column interfering with required clear space in front of the panel.

4. In Detail A4, Option 3 First Floor Power Plan:

a. Add an area of base bid work boundary line.

b. Add a receptacle to the north wall of Office 128.

SHEET EP501 – ONE-LINE DIAGRAM

1. Add Keynote 15 read “TAP EACH SET OF #500 KCMIL CONDUCTORS FEEDING B14 TO FEED

THE GATE DISCONNECT SWITCH. REFER TO SHEET ES101 FOR LOCATION OF DISCONNECT

SWITCH.”

2. Add Wire Tags 15 and 16 to the Wiring Schedule.

3. In Detail A2, One-Line Diagram:

a. At Manhole AC 325, add Keynote 15, Wire Tag 16, and provide tap conductors to gate disconnect switch.

b. Delete “Building Addition” and leader arrow from above Mech 408, and add “Building Addition” and leader arrow to point to building addition at Elevator 133 & 003.

SHEET EP601 – PANELBOARD SCHEDULES – 1

1. Panelboard P1A: Add 30A 2P circuit for gates and 30A 2P circuit for POB.

2. Revise Load totals for Panelboard P1A and MDP.

SHEET EP604 – PANELBOARD SCHEDULES - 4

1. Panelboard TEMP: Add 30A 2P circuit for gates and 30A 2P circuit for POB.

SHEET ET101 – FIRST FLOOR TECHNOLOGY PLAN

1. First Floor Technology Plan, add 2” conduit from Network Room to Storage 109.

---End of Amendment 004---

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

WAGE DETERMINATION

"General Decision Number: ME20240019 04/19/2024

Superseded General Decision Number: ME20230019

State: Maine

Construction Type: Building

County: York County in Maine.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. |

|contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2024 1 03/15/2024 2 04/19/2024

* CARP0349-001 03/01/2024

Rates Fringes

CARPENTER

Includes Drywall Hanging and Metal Stud Installation.$ 28.72 19.38

* CARP0352-008 03/01/2024

Rates Fringes

CARPENTER (Includes Drywall Hanging, Form Work, and Metal Stud Installation)...............$ 28.72 19.38

ELEC0490-009 01/01/2024

Rates Fringes

ELECTRICIAN (Includes Low Voltage Wiring)..................$ 34.49 22.49

ELEV0004-006 01/01/2023

Rates Fringes

ELEVATOR MECHANIC................$ 68.38 37.335+a+b

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Christmas Day and the Friday after Thanksgiving.

b. VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service; 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.

* IRON0007-034 03/16/2024

Rates Fringes

IRONWORKER (ORNAMENTAL AND

REINFORCING).....................$ 31.37 24.79

LABO0976-007 12/01/2020

Rates Fringes

LABORER: Common or General (Industrial Work Only)...........$ 21.76 20.07

* PLUM0131-002 06/05/2023

Rates Fringes

PLUMBER (Includes HVAC Pipe Installation)....................$ 40.36 25.34

* SUME2014-028 01/31/2017

Rates Fringes

BRICKLAYER.......................$ 30.42 2.94

CEMENT MASON/CONCRETE FINISHER...$ 17.65 5.01

INSULATOR - MECHANICAL

(Duct, Pipe & Mechanical System Insulation)...............$ 20.14 2.29

IRONWORKER, STRUCTURAL...........$ 24.16 17.25

LABORER: Common or General......$ 15.29 ** 4.67

LABORER: Demolition.............$ 18.20 5.05

LABORER: Mason Tender - Brick...$ 19.16 3.56

MILLWRIGHT.......................$ 22.17 7.75

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 39.38 8.55

OPERATOR: Crane.................$ 23.33 0.00

PAINTER (Brush and Roller).......$ 15.38 ** 2.95

PAINTER: Spray..................$ 17.47 2.22

ROOFER...........................$ 20.22 2.09

SHEET METAL WORKER, Includes HVAC Duct Installation...........$ 17.30 2.35

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.20) or 13658 ($12.90). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published…