Amendment 0003 - Enclosure (2) for PPI 17.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
DESIGN-BID-BUILD (DBB), B14 NEW STAIR/LIFE SAFETY/POWER IMPROVEMENTS PORTSMOUTH NAVAL SHIPYARD (PNSY), KITTERY, MAINE
Solicitation number
N4008524R2534
Issued by

About this file

This document is an Amendment 0003 - Enclosure (2) for PPI 17.xlsx, which appears to be a Contractor Quality Control Program Audit Checklist for a federal construction contract.

The checklist covers various quality control requirements for the contractor, including having an accepted QC plan, QC manager qualifications, conducting coordination and QC meetings, maintaining QC reports, and addressing items such as submittals, RFIs, safety, environmental management, and as-built documentation. The checklist indicates the contract is utilizing eCMS, though no other details about the specific contract are provided.

The related federal contract opportunity is for a Design-Bid-Build construction project at the Portsmouth Naval Shipyard in Kittery, Maine for Building 14. The project involves a total interior renovation, including hazardous material abatement, structural upgrades, new stairs and an elevator, exterior envelope repairs, and overhauling the mechanical, electrical, and fire protection systems.

View the file

Other files

File Type Posted
Amendment 0007.pdf PDF
Amendment 006 - attachment 2- J and A Toilet Accessories .pdf PDF
Amendment 0006 - B14.pdf PDF
Amendment 006 - attachment 1 - J and A Interior Finishes.pdf PDF
Amendment 0005 - Attachment 1 - M503.pdf PDF
Amendment 0005 B14.pdf PDF
Amendment 0004 Attachment 1 M-502 for PPI 153.pdf PDF
Amendment 0004 B14.pdf PDF
Amendment 0004 attachment 2 Amendment Dwgs.pdf PDF
Amendment 0003 B14.pdf PDF
Amendment 0003 - Enclosure (3) for PPI 101.pdf PDF
Amendment 0002 B14.pdf PDF
Amendment 0001 B14.pdf PDF
Amendment 0001 - Attachment 1 - Revised Drawings Specs .pdf PDF
Amendment 0001 - Attachment G- Price Proposal Form REV .docx DOCX document
Amendment 0001 - Attachment 2 - Site Visit Sign-in Sheet.pdf PDF
B14 Drawings - Volume 2_SBD_03-28-24.pdf PDF
N4008524R2534 B14.pdf PDF
Attachment E-Small Business Participation Commitment Document.docx DOCX document
B14 Specifications_SBD_03-22-24.pdf PDF
Attachment H - PIEE Vendor Access Instructions.pdf PDF
Attachment F - Small Business Subcontracting Plan (SBSP) Template.docx DOCX document
Attachment D- Historical Small Business Utilization.docx DOCX document
B14 Drawings - Volume 1_SBD_03-28-24.pdf PDF
Attachment G - Price Proposal Form .docx DOCX document
Attachment K - SF 5512 site visit .pdf PDF
Attachment A - Pre-proposal Inquiry Form.xls XLS spreadsheet
Attachment B - Construction Experience Project data sheet.docx DOCX document
Attachment C - Past Performance Questionnaire (Form PPQ).docx DOCX document
Attachment J - DBIDS Access Request Form.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR CHECKLIST Revised

WORKSHEET REV: 12/23/21CONTRACTOR QUALITY CONTROL PROGRAM AUDIT
CONTRACT #
CONTRACTOR:CONTRACT% COMPLETE:
CONTRACT TITLE:QC MANAGER: SINGLE HAT , DUBBLE HAT , TRIPLE HAT ((para 1.5.1.1) anything other than single hat must be approved by PWD Supervisor)
NAVFAC REP:IS THIS CONTRACT UTILIZING eCMS Yes ________ NO________
DATE:
SCORING: Mark an X in appropriate box for each attribute. For "% Yes", divide sum of "Yes" by sum of ("Yes" + "No") X 100 (do not count N/A's).
YesNoN/AQuality Control Specification Number: 01 45 00.10 22 (QUALITY CONTROL FOR CONSTRUCTION)
YesNoN/A1. Quality Control Admin
1Is there a Government accepted QC Plan, which is required before the start of work. (para 1.4.2)
2Does the QC Plan include within the organization an approved alternate Quality Control Mananger (para 1.5.2)
3Does QC Manager report to an officer of the firm, he must not be subordinate to the Project Superintendent or the Project Manager. (para 1.4)
4If there has been any organizational changes within the QC Plan, have they been accepted by the KO ? (para 1.4.3)
5Has a Coordination and Mutual Understanding Meeting been held prior to the start of construction with meeting minutes available. (para 1.7)
6Does the quality Control Mananger have a Construction Quality Management for Contractors current training certificate ? (para 1.5.1.3)
7Are QC meetings held once every week at the work site with the superintendent and the foreman responsible for the ongoing and upcoming work. (para 1.8)
8Does weekly QC Meeting cover the following: a. Review previous minutes; b. Review schedule and status of work and rework; c. Review status of submittals and RFIs; d. Review work for next two weeks and documentation required; e. Resolve QC and production items (RFIs, etc.); f. Address items potential changes to QC plan; g. Review APP; h. Review environmental requirements and procedures; i. Review Waste Management Plan; j. Review IAQ Mngmnt Plan; k. Review Environmental Mngmnt Plan; l. Review the status of training completion; m. Review the progress of As-Builts and O&M and eOMSI Documentation; n. Review Non-Compliance Notices and actions required to address non-complaint work/actions. o. Review Special Inspections (Section 01 45 35) and any deficiencies identified by Special Inspectors. Review actions taken or planned actions to correct deficiencies noted. (para 1.8)
9Are CQC Reports submitted to KO by the next working day, with copies of Special Inspectors daily reports, and any discrepancies observed that are not corrected? (para. 1.3.a)
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (1) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A2.Three Phases of Control (Preparatory Phase)
1For each DFOW, is the QC Manager; holding a preparatory phase meeting? (para 1.9.1)
2Are the results of the preparatory phase actions documented in the daily CQC Report and in the QC prepertory checklist? (para 1.9.1)
3If there is off site work taking place, does the QC Mananger hold prepertory meetings for the off-site work? (para 1.9)
4Preparatory Meetings are only held if shop drawings or submittals have been approved, APP and appropriate AHA related to the DFOW are submitted and appropriate personel are present for the meeting. The QC Manager is conducting meetings and attended by QC Specialists, Project Superintendent, CxC, Special Inspector, Special Inspector of Record, and foreman responsible for the DFOW or as approved by Contracting Officer. When DFOW will be accomplished by a Subcontractor, that Subcontractor's foreman attends the preparatory phase meeting. (para 1.9.1)
Are Prepertory meetings addressing the following:
5Review of each paragraph from the applicable specification sections.
6Review of the contract drawings.
7Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved.
8Verify receipt of approved factory test results, when required.
9Review the testing plan and ensure that provisions have been made to provide the required QC testing.
10Examine the work area to ensure that the required preliminary work has been completed.
11Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data.
12Review the APP and appropriate AHA to ensure that applicable safety requirements are met, and required Safety Data Sheets are submitted.
13Discuss the QC documentation required to be collected as part of the work.
14Identify any changed conditions or modifications that may impact the execution of the work.
15Review the processes/strategies that will be implemented to address any issues if the work does does go as planned or if any unforeseen conditions are encountered or if any changes arise that may impact the successful execution of the work.
16Review the QA inspections that may be implemented as part of the execution of the work.
17Review Environmental requirements and proceedures to include: (a)Environmental Management Plan (b) Waste Management Plan. (c) IAQ Management Plan.
18Review any Special Inspections (Section 01 45 35) required as part of the execution of the work.
19Review demolition work plan to ensure compliance with EM 385-1-1 Section 23 Demolition, Renovation and Re-Occupancy.
20For excavation, review Utility Locating Requirements. (Note: Special attention is required Hazardous or Mission Critical Utilities (as identified in the Scope of Work & Drawings) are located within the excavation area. The PWD ME Dig Safe Coordinator, PWD-ME CM/ET, PWD-ME DM and the assigned PWD-ME Project Civil Engineer must be present at the meeting to review requirements, and to ensure safety and preservation of critical utilities is discussed with adequate focus.
21If work includes excavation, review Soil Management Requirements (Note: Special attention is required if the work is within an IR site or Hazardous Soils are within the excavation area. Include Code 106.3 Representatives at this meeting to discuss Soil Management processes and procedures. SWR form is being used.
22If the work is subject to environmental (EV) permitting, Archaeological Monitoring, or SHPO approvals, review terms and conditions of the applicable permits and any supplemental controls/ approvals required to complete the work. (Note: Include PWD-ME EV Representatives at this meeting to review the project specific requirements).
23If work includes the removal and disposal of Hazardous materials, review the appropriate work plans to ensure the work plans have been approved and any comments are understood by the work execution team. (Note: Include Code 106.3 Representatives at this meeting to discuss Hazardous Materials handling and disposal processes and procedures.)
24Discuss specific controls used and construction methods, construction tolerances, Layout/survey controls (horizontal & Vertical controls) necessary, workmanship standards, and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.
25Non-Compliance Notices and any actions required to address non-complaint work/actions associated with the DFOW.
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (2) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A3. Three Phases of Control (Initial Phase Meetings)
1Is the Initial Phase meeting conducted with the proper personal in attendence; foreman responsible for that DFOW and when the DFOW will be accomplished by a subcontractor, that subcontractor's foreman shall attend the initial phase meeting?
2Is the Initial Phase meeting results documented in the daily CQCReport and on the Initial Phase checklist.
3Is the CQM conducting site inspections to ensure that it complies with contract requirements.
4Has the CQM ensured that the testing is performed by the approved laboratory and complies with specific testing requirements.
5Is the CQM checking work procedures for compliance with the APP checking appropriate AHA to ensure that applicable safety requirements are met.
6It is critical to Conduct additional preparatory and initial phase meetings on the same Definable Feature of Work (DFOW) for all work that is on-going where one or more of the following circumstances apply, is this being accomplished?

1. If there are any quality control issues or if the work is determined to be unacceptable.

2. The quality control personnel are not the same that were initially briefed at the original meetings.

3. The on-site production supervision or subcontractor/work crew have changed.

4. Work on a DFOW is resumed after a substantial period (1 month) of inactivity.

5. The Contracting Officers Representative determines additional meetings are needed to address any other problems.

6. If there are any deviations/changes/modifications to the scope of the DFOW elements modified from the original meeting.

7. If there are any changes to the methods of execution, weather conditions that may impact the execution or quality of the work.

8. If there are any changes to the work or conditions thet could effect compliance with the terms & condition of the state/federal permits.

Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (3) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A4. Three Phases of Control (Follow-up Phase)
1Are daily inspections being conducted to ensure the quality of workmanship is in compliance with contract requirements and and document in the daily CQC

Report ?

2Has a rework item tracker been established and is it being utilized to ensure that rework items are being corrected and in a timely manner?
3Assure manufacturers representatives are performing necessary inspections, if required ?
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (4) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A5. Submittal Procedures and Initial Submittal Register:
1Are there procedures for reviewing, approving, and managing submittals?
2Is there a list of name(s) of people in the QC organization authorized to review and certify submittals?
3Is the initial Submittal Register being maintained and updated as per Spec; SECTION 01 33 00 Para 1.7
4Are there submittals that have been returned Revise/Resubmit more than twice?
5Are Contractor Approved submittals being tracked.
6Are submittals being submitted for review as per Spec; SECTION 01 33 00 Para 1.4.2 a. Project title and location.b. Construction Contract Number.c. Date of the drawings d. revisions.d. Name, address, and telephone number of Subcontractor, supplier,manufacturer, and any other Subcontractor associated with the submittal. e. Section number of the specification by which submittal is required.f. Submittal description (SD) number of each component of submittal. g. For a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.h. Product identification and location in project.
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (5) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A(6) Documentation
1Are files being maintained for current and complete records of on-site and off-site QC program ?
Daily Quality Control Reports; Are reports being submitted in accordance with the following requirements:
2Timely submission, reports are due to the KO by 10:00am follow each workday and signed by the CQM.
3Reports are required for each day work is performed. Account for each calendar day throughout the life of the contract.
4The reporting of work shall be identified by terminology consistent with the construction schedule.
5In the "remarks" section in this report which will contain pertinent information including directions received, problems encountered during

construction, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, delays encountered and a record of visitors to the work site. For each remark given, identify the Schedule Activity No. that is associated with the remark.

Quality Control Validation; Establish and maintain the following in a series of three ring binders, Binders shall be divided and tabbed as indicated.
6All completed Preparatory and Initial Phase Checklists, arranged by specification section.
7All milestone inspections, arranged by Activity/Event Number.
8A current up-to-date copy of the Testing and Plan Log with supporting field test reports, arranged by specification section.
9Copies of all contract modifications, arranged in numerical order. Also include documentation that modified work was accomplished.
10A current up-to-date copy of the Rework Items List.
11Maintain up-to-date copies of all punch lists issued by the QC Staff on the Contractor and Sub-Contractors and all punch lists issued by the Government if applicable.
12Are As-Built Drawings being maintained by the CQM reflecting and contract changes vis modification # or RFI#. CQM shall initial any changes upon completion of work.
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (6) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A(7) NON-COMPLIANT WORK QC ACTIONS
1Does the CQM maintain a current up-to-date Rework Items List with dates of findings and corrections?
2Has work progressed without the KO Rep. notifying the CQM of any Non Compliant work? (01 45 00.10 22 Para:1.15 (field notification))
3Has the work progressed without notification of stop work due to Non -Compliance work not being corrected ? (01 45 00.10 22 Para:1.15)
4Has all work to date been completed without receiving a written Non Compliance notifications by the KO.
5If a written Non compliance notification been recieved has it been returned to the KO with corrective actions completed?
6Has work been completed to date without receiving a Letter of Concern or Cure Letter from the KO concerning the Coontractor Quality Control Program ?
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (7) Score#'s
YesTotal
Yes + No%Yes
YesNoN/A(8) Project Closeout
At the end of construction the CQM shall coordinate the Completing Inspections as follows:
1Has the CQM conducted the completion inspection Per Spec 01 45 00.13 (a) Punch-Out Inspection (b) Pre-Final Inspection © Final Acceptance Inspection.
2Has a Real Property Equipment listing been provided to the KO at the time of transfer all inclusive list shall include; description of item, location (by room number), model number, serial number, capacity, name and address of manufacturer, name and address of equipment supplier, condition, spare parts list, manufacturer's catalog, and warranty.
3Has the CQM reviewed and approved the Operation and Maintenance Data (O&M Manuals) (SECTION 01 78 23 Para 1.3)
4Has the CQM submitted a writen Training Plan, must be submitted least 60 calendar days prior to the scheduled training. Training plan must be approved by the Quality Control Manager (QC) prior to submission.
5Working Record and Final Record Drawings SECTION 01 78 00.00 22 Para:1.2 Has Final Drawing been submitted equal in quality and detail to that of the original contract drawings and per PWD-ME CADD & As built CADD Standards.
6All contract requirements for building commissioning shall be completed prior to contract completion.
7Has a Warranty Management Plan been submitted and approved.
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
Section (8) Score#'s
YesTotal
Yes + No%Yes
SCORE FOR EACH CATEGORY:
ERROR:#DIV/0!1. Quality Control Admin
ERROR:#DIV/0!2. Three Phases of Control (Preparatory Phase)
ERROR:#DIV/0!3. Three Phases of Control (Initial Phase Meetings)
ERROR:#DIV/0!4. Three Phases of Control (Follow-up Phase)
ERROR:#DIV/0!5. Submittal Procedures and Initial Submittal Register
ERROR:#DIV/0!6. Documentation
ERROR:#DIV/0!7. Non-Compliant Work QC Actions
ERROR:#DIV/0!8. Project Closeout
TOTAL SCORING: Total "Yes" for all attributes divided by sum of ("Yes" + "No"). (N/A's are not included in count)
Sum00000ERROR:#DIV/0!(<80% copy to Supervisor)
TOTAL OVERALL SCORE#'s
YesTotal
Yes + No%Yes

&16Page &P of &N