This document is an amendment to a solicitation for a Design-Build/Design-Bid-Build, Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) to provide general construction services at Naval Submarine Base New London in Connecticut and Naval Station Newport in Rhode Island. The amendment incorporates responses to potential offeror questions, clarifying that no new water, sanitary, or storm systems are required, existing windows do not need to meet anti-terrorism standards, and the asset value of the existing building is $9,368,699 for code-related upgrade calculations.

View the file

Other files

File Type Posted
21R0078 0018.pdf PDF
21R0078 0017.pdf PDF
21R0078 0016.pdf PDF
PPI 196 Photos.pdf PDF
21R0078 0015.pdf PDF
Site Visit Attendance Log.JPG JPG image
21R0078 0014.pdf PDF
21R0078 0013.pdf PDF
Attachment A - Construction and Design Experience Project Data Sheet 10-12.docx DOCX document
21R0078 0012.pdf PDF
SECNAV FORM 5512-NSNPT - JUL 2019.pdf PDF
SECNAV 5512 exp 2024 TEMPLATE.pdf PDF
21R0078 0011.pdf PDF
Attachment A - Construction and Design Experience Project Data Sheet.docx DOCX document
21R0078 0009.pdf PDF
B345_CommsInfo.pdf PDF
REFERENCEInfoBldg345Comms.pdf PDF
21R0078 0008.pdf PDF
21R0078 0007.pdf PDF
21R0078 0006.pdf PDF
Attachment C Con Des Exp Proj Data Standard.pdf PDF
NAVSTA soil management plan.pdf PDF
01 31 23.13 20 eCMS.docx DOCX document
21R0078 0005.pdf PDF
21R0078 0004.pdf PDF
SECNAV FORM 5512-NSNPT - DEC 2019.pdf PDF
21R0078 0003.pdf PDF
21R0078 0001.pdf PDF
21R0078 0002.pdf PDF
PPQ.pdf PDF
PPI Log.xlsx XLSX spreadsheet
Construction Des Project Data Sheet.pdf PDF
Bldg 344 Design Build RFP.pdf PDF
Price Schedule 7-3-21.docx DOCX document
21R0078 NPT NLON RFP.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment incorporates PPI responses. See continuation page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Sep-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008521R0078

X 9B. DATED (SEE ITEM 11)

03-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Sep-2021

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008521R0078

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

This amendment hereby incorporates PPI responses.

# Reference Question Response

178 2 PART

1.2 WILL THE ENTIRE BUILDING BE REQUIRED

TO BE BROUGHT UP TO CODE AS PART OF

THIS PROJECT?

Folow the specified scope of work in the RFP's Part

3. Part 4 of the RFP is used as a general standardized scope of work.

179 2 PART

1.2 IS AN ELEVATOR REQUIREMENT FOR THIS

PROJECT?

No elevator required.

180 55 PART

G20 WILL HANDICAPPED ACCESS TO THE

BUILDING BE REQUIRED AS PART OF THIS

PROJECT?

No handicapped access to the building is required.

181 6 PART

3.2 PARAGRAPH 3.2 SITE DEVELOPEMNT

INDICATES 'N/A' . PART 4 PAGE 48

PARAGRAPH G3010 WATER SUPPLY CALLS

FOR 'NEW WATER SYSTEM'. IS A NEW

WATER SYSTEM REQUIRED?

No new water system required for this project.

Please follow all-necessary tie-in requirements in Part 3 for the new Men's bathroom.

182 6 PART

3.2 PARAGRAPH 3.2 SITE DEVELOPEMNT

INDICATES 'N/A' . PART 4 PAGE 51

PARAGRAPH G3020 CALLS FOR 'NEW

SANITARY SYSTEM'. IS A NEW SANITARY

SYSTEM REQUIRED FOR THIS PROJECT?

No new sanitary system required for this project.

Please follow all work requirements in Part 3 for the new Men's bathroom.

183 6 PART

3.2 PARAGRAPH 3.2 SITE DEVELOPEMNT

INDICATES 'N/A' . PART 4 PAGE 57

PARAGRAPH G3030 CALLS FOR 'NEW

STORM SYSTEM'. IS A NEW STORM SYSTEM

REQUIRED FOR THIS PROJECT?

No new storm system required for this project.

184 9 PART

B2020 THIS SECTION CALLS FOR 'ALL WINDOWS

AND DOORS IN NEW OR EXISTING

BUILDINGS, WHICH ARE SUBJECT TO ANTI-

TERRORISM STNADARDS, MUST BE BLAST

RESISTANT'. ARE THE EXISTING WINDOWS

TO REMAIN REQUIRED TO BE ANTI-

TERRORISM AS PART OF THIS PROJECT?

Existing windows to remain, are not required to comply with Minimum Anti-Terrosism Standards.

185 FOR CODE RELATED UPGRADES

DICTACTED BY THE VALUE OF THE

RENOVATION WORK COMPARED TO THE

REPLACEMENT VALUE OF THE EXISTING

BUILDING, WHAT AMOUNT SHOULD BE

USED AS THE VALUE OF THE EXISTING

BUILDING?

Asset Value is at $9,368,699