J-1502000-25 Hot and Cold Closed Loop HVAC.pdf

PDF 64 KB Posted

Attached to
HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) Maintenance and Repair Services and Direct Digital Controls (DDC)
Solicitation number
N4008520R2502
Issued by

View the file

Other files

File Type Posted
N4008520R250200003.pdf PDF
N4008520R25020002.pdf PDF
J-0200000-04 Invoice Form.pdf PDF
N4008520R25010001.pdf PDF
J-1502000-12A NAVSUBASE NLON FY14 UPV CERT CARDS.pdf PDF
J-1502000-08B BOILER INVENTORY REVISED 2.xls XLS spreadsheet
J-0200000-02D CBA Sup 30OCT19.pdf PDF
J-0200000-02C CBA.pdf PDF
N4008520R2502.pdf PDF
J-0200000-09 - CHARACTERISTIC METER READING INFORMATION v2 - 2016-09-30.xlsx XLSX spreadsheet
HVAC 1502000 WBS Facility Investment.pdf PDF
HVAC 1502000 SECTION J.pdf PDF
J-1502000-20 Service Order Summary Report.xls XLS spreadsheet
J-1502000-16 Navy Sub Systems Water Testing.xlsx XLSX spreadsheet
J-0200000-05F On site Labor Summary Report reviewed.xls XLS spreadsheet
J-1502000-05A HVAC-CALLS 1-1-15 to 12-31-15.xls XLS spreadsheet
J-0200000-15 ACM HISTORICAL DATA.xls XLS spreadsheet
J-1502000-21 Monthly Preventative Maintenance Summary Report.xls XLS spreadsheet
J-0200000-02B SCA 2015-4111.pdf PDF
J-0200000-16 UEM Contractor Outage Process 20141120.pdf PDF
J-1502000-09 BUILDING INVENTORY FOR BAS.xlsx XLSX spreadsheet
0200000 F Management and Administration.pdf PDF
J-1502000-8A Unfired Pressure Vessels NEWLON.xlsx XLSX spreadsheet
J-0200000-07 - ASSET INFORMATION v2 - 2017-04-26.xlsx XLSX spreadsheet
J-1502000-24 Asset Condition Report 2018.xlsx XLSX spreadsheet
J-0200000-06 - SERVICE PROVIDER INFORMATION v1 - 2013-07-07.xlsx XLSX spreadsheet
J-0200000-05E Quality Inspection and Surveillance report reviewed.xls XLS spreadsheet
HVAC 1502000 SECTION F.pdf PDF
J-1502000-19 Direct Condition Rating Guidance.pdf PDF
J-0200000-12 Installation Spill Control Plan.pdf PDF
0200000 C Management and Administration.pdf PDF
0200000 J Management and Administration.pdf PDF
J-0200000-05D contractor incident report system.pdf PDF
J-1502000-10A Refrigerant Appliance Disposal.pdf PDF
J-1502000-05B HVAC-CALLS 1-1-16 to 12-31-16.xls XLS spreadsheet
J-1502000-06 PROPERTY ASSET INVENTORY revised.xls XLS spreadsheet
J-1502000-5D HVAC 2018 Call Log.xlsx XLSX spreadsheet
J-1502000-12B NAVSUBASE NLON FY14 BOILER CERT CARDS.pdf PDF
J-1502000-17 HVAC Systems Seasonal Start-Up and Shutodwn.xlsx XLSX spreadsheet
J-1502000-03 BUILDING INVENTORY.xls XLS spreadsheet
J-1502000-22 Prescriptive Maintenance Summary Report.xls XLS spreadsheet
J-1502000-5C HVAC 2017 Call Log.xlsx XLSX spreadsheet
0100000 C General Information.pdf PDF
J-1502000-10B Refrigerant Appliance Installation.pdf PDF
J-1502000-18 Uniformat Classification.pdf PDF
HVAC BID SCHEDULE.xls XLS spreadsheet
J-0200000-08 - ASSET SPECIFICATION v1 - 2016-01-20.xlsx XLSX spreadsheet
J-1502000-23 MP-217_D_00_SB.pdf PDF
J-0200000-02A DBA WD CT20190024.pdf PDF
HVAC 1502000 SECTION C.pdf PDF
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT J-1502000-26

CLEANING & WATER TREATMENT INSTRUCTIONS FOR COLD AND HOT WATER

CLOSED LOOP SYSTEMS

I. CLEANING CLOSED LOOP SYSTEMS SHALL BE PERFORMED ONCE DURING THE

PERIOD OF THE CONTRACT

REQUIREMENT:

Adding cleaning chemical solution shall be performed by a certified technician with a minimum of five years experienced.

Add recommended cleaning chemical solution to treat corrosion, microbiological growth and corrosion fouling deposits and break down scales deposit. Circulate the recommended quantity of chemical solution into the system, the required length of time of circulation shall be determine by the Technician in charge or the manufacturer recommendation until the internal of the pipe is completely treated and clean.

Drain closed loop system and flush with fresh water to completely remove all cleaning solutions in the system (repeat as necessary).

Add Polymers treatment in the closed loop system for internal coating. Follow manufacturer, Industrial standard and UFC guideline for Corrosion and Polymeric Coatings application

Clean, neutral closed loop water system need never be drained except in an emergency or due to necessary servicing of the equipment, flushing and draining necessitates adding of make-up water, which may cause corrosion, scale and other problems.

Chemical treatment added into the system shall not have a negative impact on pump seals, valve seals and gasket etc.

A closed loop system that contain acid will usually have one or more of the following symptoms:

1. Gas formation (air troubles)

2. Pump seal and gland problems (water leaking)

3. Air vent valves sticking or leaking.

4. Frequent relief valve operation.

5. Pipe joint leaking.

6. All water leaks shall be repaired.

The contractor shall submit monthly pH level testing; record of pH level reading and quantity of chemical added into the system loop shall be submitted to the Government in accordance with Section F.

ATTACHMENT J-1502000-26

CLEANING & WATER TREATMENT INSTRUCTIONS FOR COLD AND HOT WATER

CLOSED LOOP SYSTEMS

II. WATER TREATMENT FOR ALL HOT AND COLD WATER CLOSED LOOP SYSTEMS

REQUIREMENT:

Adding chemical treatment solution to neutralize the acid, micro biocides and other chemical treatment in the closed loop system shall be performed by a certified technician with a minimum of five years experienced.

The system must be thoroughly cleaned before effective control chemical treatment such as corrosion inhibitors etc., can be added.

Clean neutral closed loop water system need never be drained except in an emergency or due to necessary servicing of the equipment. If the system is drained for repair, a liquid chemical control treatment shall be added to maintain the recommended pH level.

Monthly pH level testing shall be required and recorded for pH level and quantity of chemical added into the system loop. Recorded reading taken shall be forwarded to the Government for review.

Level of pH shall be monitored weekly for the first two months, once system pH loop reading has been stabilize, then monthly pH testing shall be performed.

Test result with a pH reading below recommended level indicates that the system water contains acid and shall be treated immediately.

The system loop shall be treated to bring the pH level back to the recommended 8 to 9 pH level.

Chemical added into the system shall not have a negative impact on pump seals, valve seals and gasket etc.

Existing shunt feeders shall be clean and tested for operation prior of used.

III. REFER TO UFC 3-240-13FN FOR ADDITIONAL INSTRUCTION AND INFORMATION ON

COLD AND HOT WATER CLOSED LOOP TREATMENT.

IV. BUILDINGS WITH HOT AND CHILL WATER CLOSED LOOP SYSTEMS (see reference-

1502000-16)

Notes: On systems using ethylene glycols, an inhibited non-automotive grade should be used (the recommended pH level is 8-10). When using ethylene glycols, a supplemental inhibitor package of sodium nitrate and borate at startup. Manufacture’s recommendations may also be followed.

Cleaning and treatment of closed loop system shall comply with central plant Industry standard, UFC 3-

240-13FN.