0200000 – Management and Administration
SECTION F: DELIVERIES OR PERFORMANCE
Section F – 0200000 Management and Administration
DELIVERABLES
Annex/ Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.2.1.2
N/A Request to Work Outside Government’s Regular Working Hours
At least seven calendar days prior to requested day.
KO and
COR
1 As required
0200000/ 2.3.1
N/A Sign-In Sheets and Minutes
Within two working days.
KO, COR
and all attendees
1 As required
0200000/ 2.3.1
N/A Final Revision of Minutes
Within two working days.
KO, COR
and all attendees
1 As required
0200000/ 2.3.4
N/A Permits and Licenses
Before work commences and as requested by the KO.
KO and
COR
1 As specified
0200000/ 2.3.5
N/A Certificate of Insurance
At least 30 calendar days prior to start of contract performance.
KO and
COR
1 As specified
0200000/ 2.6.6.2
J-0200000-06 Service Provider Flat-file
By the end of the following work day when updates are required
KO and
COR
1 As required
0200000/ 2.6.6.2
J-0200000-07 Asset Flat-file By the end of the following work day when updates are required
KO and
COR
1 As required
0200000/ 2.6.6.2
J-0200000-08 Asset Specification Flat-file
By the end of the following work day when updates are required
KO and
COR
1 As required
0200000/ 2.6.6.2
J-0200000-09 Characteristic Meter Flat-file
By the end of the following work day when updates are required
KO and
COR
1 As required
0200000/ 2.6.6.2
J-0200000- 06,07,08,09
Sample Delimited Flat-file
At least 30 calendar days prior to start of contract performance.
KO and
COR
1 As specified
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.6.6.3
N/A List of Personnel Requiring
MAXIMO
Accounts
At least 30 calendar days prior to start of contract performance and within 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.6.7.1
N/A Quality Management Plan
At least 30 calendar days prior to start of contract performance and within 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.6.7.2
N/A QC Inspection File Within five calendar days of completion/ termination of the contract.
KO and
COR
1 As specified
0200000/ 2.6.7.3
J-0200000-5E Contractor Quality Inspection and Surveillance Report
First work day of each month.
KO and
1 Monthly
0200000/ 2.6.8
N/A Property Management Plan
At least 30 calendar days prior to start of contract performance.
N/A
KO and
N/A
2.7.1
N/A List of Key Personnel and Qualifications
At least 30 calendar days prior to start of contract performance.
KO and
COR
1 As specified
0200000/ 2.7.1
N/A Organizational Chart
At least 15 calendar days prior to start of contract performance.
KO and
COR
1 As specified
0200000/ 2.7.2.6
N/A Proof of Legal Residency
Prior to be admitted to site of work.
KO and
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.7.3
N/A Contractor Labor Hours (eCMRA) Report
No later than 31 October.
KO and
COR
1 Annually for labor executed during the period of performance during each Government fiscal year
(FY)
0200000/ 2.8.1
N/A Employee List Upon request. KO and
COR
1 As required
0200000/ 2.8.8
N/A Personnel Security Investigation (PSI), Fingerprint Card (FD87), and OF- 306 Declaration for Federal Employment
Prior to employee access to sensitive unclassified information.
KO, COR,
and
Security Manager
1 As required
0200000/ 2.9.1
N/A Accident Prevention Plan
At least 30 calendar days prior to start of contract performance and 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.9.2
N/A Activity Hazard Analysis
Together with the Accident Prevention Plan and for changes.
KO and
COR
1 As specified
0200000/ 2.9.3
N/A Compliance Plans, Programs, and Procedures
Together with the Accident Prevention Plan and for changes.
KO and
COR
1 As specified
0200000/ 2.9.5
J-0200000- 05D
NAVFAC
Contractor Incident Reporting System
(CIRS)
Within five calendar days of accident.
KO and
COR
1 As required
0200000/ 2.9.5
J-0200000- 05B
Weight Handling Equipment Accident Report
Within 15 working days of accident.
KO and
COR
1 As required
0200000/ 2.9.5
J-0200000- 05C
Crane and Rigging Gear Near Miss Report
Within 15 working days of accident.
KO and
COR
1 As required
0200000/ 2.9.7
J-0200000- 05F
Monthly On-Site Labor Report
First work day of each month.
KO and
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.9.8
N/A OSHA Citations and Violations Corrective Action Report
Within 48 hours after receiving a citation.
KO and
COR
1 As required
0200000/ 2.9.10
N/A Safety Certifications
At least 15 calendar days prior to start of contract performance and prior to expiration of certifications.
KO and
COR
1 As specified
0200000/ 2.10.1.1
N/A Water Conservation Plan
At least 30 calendar days prior to start of contract performance and 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.10.2.1
N/A Written Sampling Plan
Prior to each sampling event
N/A
KO and
1 As required
2.10.2.1
N/A Sampling Results Within 24 hours after receipt of laboratory analysis
N/A
KO and
2.10.2.2
N/A Class I and II ODS Report
Within 24 hours following delivery of refrigerant to
DLA
KO, EV
and COR
1 As required
0200000/ 2.10.2.3
N/A Solid Waste Management Reports
Within three months after start of contract performance and annually by October 10th thereafter
N/A
KO and
2.10.2.3
N/A Recycling Weight Ticket Receipts
As Specified
N/A
KO and
2 Quarterly
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.10.2.5
N/A Waste Stream Determination
At least 30 calendar days prior to start of contract performance and within 14 days of identification of any new waste stream.
N/A
KO and
2.10.2.7
N/A Spill Report Within 48 hours of spill occurrence
KO, EV
and COR
1 As required
0200000/ 2.10.2.8
J-0200000- 05H
Emergency Planning and Community Right- To-Know Act (EPCRA) Report
At least 15 calendar days prior to start of contract performance and not less than 10 working days prior to planned use of hazardous material.
KO, EV
and COR
2 As specified
0200000/ 2.10.2.8
J-0200000-13 Contractor Hazardous Material Inventory Log
Within 15 calendar days after the end of each calendar year and at termination of the contract.
KO, EV
and COR
2 Annually
0200000/ 2.10.2.12
N/A Asbestos Containing Material (ACM)
Written notification within 24 hours of discovery
KO, EV
and COR
2 As specified
0200000/ 2.10.2.13
J-0200000-05I Hazardous Air Pollutant (HAP) Monthly Data
First work day of each month.
KO, EV
and COR
1 Monthly
0200000/ 2.10.2.13
J-0200000-05I Hazardous Air Pollutant (HAP) Semi-annual Report
Semi-annually by July 10th and January 10th
KO, EV
and COR
1 Semi- Annually
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.10.3
N/A Sustainable Procurement and Practices Plan
At least 15 calendar days prior to start of contract performance and within 15 calendar days after exercised option periods.
KO and
COR
1 Annually
0200000/ 2.10.3
N/A Sustainable Delivery of Services Report
Within five calendar days after each contract period.
KO and
COR
1 Annually
0200000/ 2.10.3.2
N/A Recovered Material Certification
As specified KO and
COR
1 When a product containing recovered materials is equal to or better than the original and could be used.
0200000/ 2.14.1
N/A Detailed Scope of Work and Detailed Estimate
Within two work days
KO and
COR
2 As required
0200000/ 2.15.2.1
N/A Non-Recurring Work Proposals
Within two working days following receipt of request
KO and
COR
1 As required
0200000/ 2.15.1.1
N/A Non-Recurring Work Quantities Ordered via FedMall
First work day of each month.
N/A
KO and