This document provides an amendment to a solicitation for repair work on a submarine training facility. The amendment updates the instructions to offerors section, providing additional details on proposal submissions, evaluations, and requirements. Price and non-price proposals must be submitted electronically by the designated due dates, with hard copy binders to follow. Evaluation will be based on price and four non-price factors: corporate experience, safety, past performance, and technical solution. Offerors must meet minimum experience requirements and provide safety records, past performance questionnaires, and a technical narrative within defined page limits. The Navy will first evaluate proposals based on price alone and then technical merit if the lowest price is not acceptable. This solicitation from the Naval Facilities Engineering Command seeks repairs to Building 488 at the Submarine A School in New London, Connecticut, including upgrades to fire protection, interior finishes, HVAC, plumbing, and the building exterior enclosure.

View the file

Other files

File Type Posted
19095 SKS-001.pdf PDF
Amendment 0009.pdf PDF
02 03 44.pdf PDF
Amendment 0008.pdf PDF
B488_ELMR_Antenna_SOW_NAVFAC.docx DOCX document
Attachment F - Price Proposal Form REVISED.docx DOCX document
Amendment 0006.pdf PDF
06 20 00.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
20R0034 Site Visit Log 2.pdf PDF
Amendment 0003.pdf PDF
20R0034 Site Visit Log.pdf PDF
Amendment 0002.pdf PDF
1600393dwg07of11-FIRE ALARM - corrected.pdf PDF
Amendment 0001.pdf PDF
1600393dwg02of11-CIVIL.pdf PDF
Attachment C - Construction Experience Project Data Sheet.docx DOCX document
Attachment A - Pre-Proposal Inquiry Log Template.xlsx XLSX spreadsheet
1600393dwg11of11-ELECTRICAL.pdf PDF
1600393dwg07of11-FIRE ALARM.pdf PDF
1600393dwg08of11-FIRE PROTECTION.pdf PDF
1600393dwg10of11-MECHANICAL.pdf PDF
1600393spec01of02.pdf PDF
1600393dwg06of11-LIFE SAFETY.pdf PDF
1600393dwg09of11-PLUMBING.pdf PDF
Attachment D - Past Performance Questionnaire.docx DOCX document
Attachment B - SECNAV_5512_1_11787-One Day Past Request.pdf PDF
Attachment F - Price Proposal Form.docx DOCX document
1600393dwg05of11-INTERIORS.pdf PDF
1600393dwg03of11-STRUCTURAL.pdf PDF
1600393spec02of02.pdf PDF
1600393dwg01of11-GENERAL.pdf PDF
20R0034 Solicitation.pdf PDF
1600393dwg04of11-ARCHITECTURAL.pdf PDF
Attachment E - Small Business Subcontracting Plan.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

DESIGN-BID-BUILD, REPAIR FAILING (CI 58) SUBMARINE A SCHOOL BQ 488, NEW LONDON, CT

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Rachel Honecker; rachel.honecker@navy.mil; 757-341-1652

1. CONTRACT ID CODE PAGE OF PAGES

J 1 13

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Mar-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520R0034

X 9B. DATED (SEE ITEM 11)

14-Feb-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Mar-2020

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008520R0034

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0007

The purpose of this Amendment is to provide the following:

1. Updated Instructions to Offerors

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

INSTRUCTIONS TO OFFERORS

TABLE OF CONTENTS

1. GENERAL

1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS

1.2 GENERAL OVERVIEW OF CONTRACT

2. BASIS FOR AWARD

3. EVALUATION FACTORS FOR AWARD

4. PROPOSAL REQUIREMENTS

4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT

4.2 PROPOSAL SUBMISSION INSTRUCTIONS

4.3 PRE-PROPOSAL INQUIRIES (PPIs)

4.4. BETASAM.GOV

5. ATTACHMENTS: Will be located on beta.SAM.gov under additional documents.

1: GENERAL INFORMATION

DESIGN-BID-BUILD, REPAIR FAILING (CI 58) SUBMARINE A SCHOOL BQ 488, NEW LONDON, CT

1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS

1.1.1 This acquisition is being solicited on an unrestricted basis, with Full and Open Competition.

1.1.2 In accordance with DFARS 236.204, The Magnitude of Construction for this Project is between $25,000,000 and $100,000,000.

1.1.3 NAICS Code: 236220 and the Size Standard is $39,500,000.

1.1.4 This solicitation is formatted as a Request for Proposal according to FAR Part 15. This method permits evaluation of proposals based on price competition, technical merit and other factors; permits impartial and comprehensive evaluation of offerors' proposals; permits discussions if necessary; and ensures selection of the source whose performance provides the best value to the Government.

1.1.5 Contractor Performance Information: Contractor’s performance will be evaluated using the respective contractor performance evaluation report entry system located on the website http://www.cpars.gov/. Prior to commencement of work, the contractor is required to provide the government with the name, phone number and email address of the “Contractor’s Representative” that will be responsible for receipt and review of draft performance evaluations prepared by the government in the appropriated system. It is the contractor’s responsibility to keep this contract information current.

1.2 BETA.SAM.GOV WEBSITE: All attachments, drawings, and specifications will be posted on beta.SAM.gov at https://beta.sam.gov. Amendments will be posted directly to the website. Additionally, other postings will be made to the website, such as the Pre-Proposal Inquiries (PPI) log, drawings, etc. Postings to the website, DO NOT generate an automated email to offerors. It is the offeror’s responsibility to check beta.SAM.gov periodically to see if additional postings have been made.

2: BASIS OF AWARD

2.1 The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the lowest priced, technically acceptable offer.

2.2 The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals

2.3 The LPTA process is selected as appropriate for this acquisition because the best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price.

2.4 In order to permit efficient competition, the Navy will utilize the following methodology. Proposals will initially be screened for price and placed in order (lowest price to highest price). The Navy will then evaluate the technical factors of the lowest priced proposal. If the lowest priced proposal is not found to be technically acceptable then the next lowest price proposal shall be evaluated. If that proposal is also not found to be technically acceptable, then the process described will be conducted again as many times as necessary, until such time as the Government identifies a technically acceptable proposal. Accordingly, under this methodology, the technical factors of some proposals may not be evaluated by the Navy. If discussions are deemed necessary by the Contracting Officer, all proposals will be evaluated (both technical and price) for the purpose of establishing a competitive range.

2.5 An overall non-price factors rating must be at least “ACCEPTABLE” in order to be eligible for award. An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal being rated “UNACCEPTABLE” unless corrected through discussions. An overall non-price factors rating of “UNACCEPTABLE” makes a proposal ineligible for award.

3: EVALUATION FACTORS FOR AWARD

3.1 The solicitation requires the evaluation of price and the following non-price factors.

Factor 1 - Corporate Experience Factor 2 - Safety

Factor 3 - Past Performance Factor 4 - Technical Solution

The distinction between Corporate Experience and Past Performance is Corporate Experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past Performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

3.2 Basis of Evaluation and Submittal Requirements for Each Factor.

(a) Price:

(1) Solicitation Submittal Requirements:

Due to DoD Guidance concerning COVID-19, it is necessary to submit the Price Proposal, inclusive of all listed below, electronically to rachel.honecker@navy.mil by the designated price due date and time.

At this time, price binders will be requested at a later date. Price Binders must mirror the electronic version submitted. In the event of discrepancy between the electronic and hard copies, the electronic copy received by the due date and time will be the governing document

The offeror shall submit one (1) original electronically, marked “Original”, and at a later date to be determined, submit one (1) hard copy original, marked “Original”, and one (1) hard copy, marked “Copy”, in a separate three ring binder (1/2 inch minimum) with the following:

1. Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS Number, Cage Code, Point of Contact, and E-mail Address;

2. Completed SF 1442 signed with all amendments acknowledged;

3. Price Proposal Form that includes completion of all contract line item numbers (CLINS);

4. Copy of Representation and Certifications and proof of registration in System for Award Management

(SAM);

5. Confirmation of filing of Veterans’ Employment and Training (VETS) VETS-4212 for the 2017 filing cycle;

6. Bid Guarantee in accordance with FAR 52.228-1 – Bid Guarantee (amount shall be at least 20 percent of the proposed price, but shall not exceed $3 million); and

7. Responsibility Determination Information (see below).

8. Small Business Subcontracting Plan Information (see below).

In the event of a discrepancy between the original and copies, the original version of the proposal will govern.

Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued. Furthermore, any price information within the technical proposal (non-price proposal) will not be considered. Likewise, any technical/non-price information within the price proposal will not be considered.

RESPONSIBILITY DETERMINATION INFORMATION – In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically FAR 9.104-1, General Standards. In a separate tab, the offeror shall provide the following information in the price proposal package:

1. One (1) signed bank reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).

2. The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.

3. Description of offeror’s facilities and equipment.

4. Other offeror’s work presently under contract.

SMALL BUSINESS SUBCONTRACTING PLAN INFORMATION - reference FAR 52.219-9 Alt II and DFARS 252.219-7003).

NAVFAC's command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging small business subcontracting goals for this acquisition.

Offerors representing as other than small businesses shall establish small business subcontracting plan goals and shall document in their subcontracting plans the basis for all proposed goals. Plans shall be submitted with initial offers.

SB 40%

SDB 5%

HUBZone SB 3%

WOSB 9%

SDVOSB 3%

Small businesses identified by name shall be listed in small business subcontracting plans submitted pursuant to FAR 52.219-9 in order to facilitate compliance with DFARS 252.219-7003(e).

See the Small Business Subcontracting Plan Template (Attachment E) for format.

Although required to be submitted with offeror’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.

(2) Basis of Evaluation:

The Government will evaluate price based on the total price. Total price consists of the entire work, in accordance with the drawings and specifications. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

(i) Comparison of proposed prices received in response to the RFP.

(ii) Comparison of proposed prices with the IGCE.

(iii) Comparison of proposed prices with available historical information.

(iv) Comparison of market survey results.

(b) Non-Price Factors:

Due to DoD Guidance concerning COVID-19, it is necessary to submit the Non-Price Proposal adhering to bullets listed below, electronically to rachel.honecker@navy.mil by the designated non-price due date and time.

At this time, non-price binders will be requested at a later date. Non-Price Binders must mirror the electronic version submitted. In the event of discrepancy between the electronic and hard copies, the electronic copy received by the due date and time will be the governing document.

The offeror shall submit one (1) original electronically, marked “Original”, and at a later date to be determined one

(1) hard copy original, marked “Original”, and four (4) hard copies, marked “Copy”, each in a separate three ring binder with the following:

- Cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, Phone Number, and Email Address;

- 8 ½ x 11 paper, 12-point font;

- Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated; and

- Submit price and non-price binders on one CD-ROM. In case of variation, the original hard copy proposal takes precedence over electronic or copies.

(1) Factor 1, Corporate Experience:

(i) Solicitation Submittal Requirements:

Submit up to a maximum of five (5) construction projects for the offeror that best demonstrates your experience on relevant projects (similar in size, scope, and complexity to the RFP). An offeror must submit a minimum of three

(3) relevant projects to receive a rating of Acceptable. For purposes of this evaluation, a relevant project is defined as follows:

Size/Scope: Renovation of at least 50,000 square feet within multi-story existing facility.

Complexity: To be deemed Acceptable, the offeror must demonstrate experience with renovation (full replacement or overhaul) of all of the following systems:

- HVAC

- Plumbing

- Electrical

- Fire Protection

- Architectural/Interior Finishes

- Elevator Systems

- Also includes mold abatement.

Offerors are not required to demonstrate experience with all individual systems in each submitted project.

Experience with the individual systems may be demonstrated collectively through all of the projects submitted, but offeror must demonstrate experience with renovation of each listed system in a minimum of two (2) projects provided. [For example, each project submitted does not need to include HVAC renovations, but at least two projects submitted must demonstrate HVAC experience.]

Experience of proposed subcontractors will not be considered. Furthermore, the offeror’s experience as a subcontractor will not be considered.

Projects submitted for the offeror shall be completed within the past ten (10) years of the date of issuance of the

RFP.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project;

rather offerors shall submit the work performed under a task order as a project. Projects which are not complete as of the date of issuance of this RFP shall not be considered by the SSEB.

The attached Construction Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) double-sided pages (or four (4) single-sided pages).

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods). In addition, the description should also address any sustainable features for this project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process. Projects that are not sufficiently described so as to demonstrate compliance with the above Size, Scope, and Complexity requirements may be deemed not relevant.

If the offeror is a Joint Venture (JV), relevant project experience shall be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. If projects are submitted for the Joint Venture members, the projects must demonstrate the meaningful involvement of all parties of the Joint Venture (JV). Offerors who fail to submit experience for all Joint Venture members and who fail to demonstrate the meaningful involvement of all Joint Venture members will be rated lower. Offerors are still limited to a total of five (5) projects combined. For a JV, the offeror shall submit the signed JV agreement. For 8(a) Mentor-Protégé Joint Venture, the offeror shall submit the signed and U.S. Small Business Administration (SBA) approved Mentor-Protégé agreement.

If an offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.

(ii) Basis of Evaluation:

The basis of evaluation will include the offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects total. Any projects submitted in excess of the five (5) for Corporate Experience will not be considered. An offeror that does not submit a minimum of three

(3) relevant projects (as well as demonstrating two examples of renovation of each listed building system) as defined above will receive a rating of “Unacceptable” and will not be eligible for award.

(2) Factor 2, Safety:

(i) Solicitation Submittal Requirements:

The offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. EMR, DART and TRC Rates shall not be submitted for subcontractors.)

(a) Experience Modification Rate (EMR): Include three previous complete calendar years’ (2017, 2018, and 2019) worth of data. This rate compares company’s annual losses in insurance claims against its policy premiums. The offeror may submit an insurance company-provided equivalent rate if no EMR exists. If the offeror has no EMR or premium, for any year, affirmatively state so and explain why. Any extenuating circumstances that affect the EMR and negative trends should be addressed as part of the factor submission.

(b) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate: Submit three previous complete calendar years’ worth of data (2017, 2018, and 2019). If an offeror cannot submit an OSHA DART rate, for any year, the offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the OSHA DART rate data negatively must be addressed as part of this factor submission.

(c) Total Recordable Case (TRC) Rate: Submit three previous complete calendar years’ (2017, 2018, and 2019) worth of data. If an offeror cannot submit TRC rates, for any year, affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the TRC rate data negatively must be addressed as part of this factor submission.

(d) Technical Approach for Safety: The technical approach to safety narrative shall be limited to one (1) double-sided page (or two (2) singled-sided pages), and must address all items below.

1. The offeror shall describe the plan for safety that will be implemented to evaluate safety performance of potential subcontractors as part of the selection process for all levels of subcontractors.

2. The offeror shall describe the safety management system that will be used to oversee the safety compliance and performance of self-performed and subcontractor performed work.

3. The offeror shall describe any innovative methods that will be employed to ensure and monitor safe work practices at self-performed and/or all subcontractor levels.

4. The offeror shall describe the methodology to execute an effective program that facilitates sound mishap prevention techniques and processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps.

Note: The narrative shall be limited to two pages. For a partnership or joint venture, the submittal requirements are required for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. Safety narratives for joint ventures may be up to four pages in length.

(ii) Basis of Evaluation: The evaluation will collectively consider the following:

- Experience Modification Rate (EMR)

- OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART)

- Total Recordable Case (TRC) Rates

- Offeror Technical Approach to Safety

- Other sources of information available to the Government

(a) Experience Modification Rate (EMR): For the three previous complete calendar years the offeror will submit EMR. If no EMR exists, the offeror may submit an insurance company-provided equivalent rate explaining why not. If an insurance company-provided equivalent rate is provided, it will be treated the same as an EMR. Any extenuating circumstances that affected the EMR and negative trends should be addressed as part of this selection factor. The board will evaluate the EMR to determine if the offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.

(b) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rates: For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit their OSHA DART, as defined by the U.S.

Department of Labor, Occupational Safety and Health Administration. If unable to submit OSHA DART rates, affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the OSHA DART rate data and negative trends should be addressed as part of this element. The board will evaluate the OSHA DART rates to determine if the offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.

(c) Total Recordable Case (TRC) Rates: For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit their TRC, as defined by the U.S. Department of Labor, Occupational Safety and Health Administration. If unable to submit TRC rates, affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the TRC rate data and negative trends should be addressed as part of this element. The board will evaluate the TRC rates to determine if the offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.

(d) Technical Approach to Safety: The offeror will describe their plan to evaluate their safety performance and that of potential subcontractors. Also, describe any innovative methods that the offeror will employ to ensure and monitor safe work practices at all subcontractor levels. The Safety Narrative shall be limited to two pages. The board will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project. The board will evaluate the narrative to determine the degree to which innovations are being proposed that may enhance safety on this procurement and validate the contractor has addressed methodology to be used in the execution of an effective program that facilitates sound mishap prevention techniques/processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps.

(e) Other Sources of Information Available to the Government: Other sources for safety may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS) in Enterprise Safety Applications Management System (ESAMS), Contractor Performance Assessment Reporting System (CPARS) and other related databases.

The Government is seeking to determine that the offeror has consistently demonstrated a commitment to safety and that the offeror plans to properly manage and implement safety procedures for its self-performed work and the work of its sub-contractors. The Government will evaluate the offeror’s overall safety management system, safety performance record, and the offeror’s methodology of qualifying, evaluating, selecting and overseeing its subcontractors. The Government’s sources of information for evaluating safety will include, but are not limited to:

OSHA, NAVFAC’s Enterprise Safety Applications Management System (ESAMS) database, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), and other related databases. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete safety information regarding these submittal requirements rests with the Offeror. The Government will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project and the specific management practices that will be in place for providing deliberate safety program management and mishap prevention support.

(3) Factor 3, Past Performance:

(i) Solicitation Submittal Requirements:

IF A COMPLETED CPARS EVALUATION IS AVAILABLE, IT SHALL BE SUBMITTED WITH THE

PROPOSAL. IF THERE IS NOT A COMPLETED CPARS EVALUATION, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror to submit to the client for each project the offeror includes in its proposal for Factor 1 – Corporate Experience. AN OFFEROR SHALL NOT SUBMIT A PPQ

WHEN A COMPLETED CPARS IS AVAILABLE.

IF A CPARS EVALUATION IS NOT AVAILABLE, the offeror must ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror must complete and submit with the proposal the first page of the PPQ (Attachment D) with contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Gary Milton, via email at gary.milton1@navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), and any other known sources not provided by the offeror.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror. It is the responsibility of the offeror to provide accurate points of contact for each identified contract and current telephone numbers and/or email addresses.

Offerors are highly encouraged to provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Corporate Experience. Offerors are also highly encouraged to address any adverse past performance issues. Explanations shall not exceed two (2) double-sided pages (or four (4) single-sided pages) in total.

The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the offeror’s references or the references’ unwillingness to provide the information requested may affect the Government’s evaluation of this factor.

Performance award or additional information submitted will not be considered.

The evaluation focuses on how well the offeror performed on the relevant projects submitted under Factor 1 – Corporate Experience and past performance on other projects currently documented in known sources. Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.

The degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., PPIRS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance may include, but is not limited to:

- A pattern of successful completion of tasks;

- A pattern of deliverables that are timely and of good quality;

- A pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); and

- Recency of tasks performed that are identical to, similar to, or related to the task at hand

The Government will consider the recency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination.

In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “Acceptable”.

(4) Factor 4, Technical Solution:

(i) Solicitation Submittal Requirements:

Provide a narrative describing your approach to executing the project in a manner that meets or exceeds the requirements of the solicitation. The narrative shall address the following:

- Building envelope

- Building systems including HVAC, electrical, communications, and fire protection

- Elevator

- Mold remediation

- Project site work

- Site access and laydown

Narrative shall not exceed six (6) double-sided pages (or 12 single-sided pages).

Offeror shall use the design drawings and specifications provided as the basis for their technical solution.

The Government will evaluate the narrative considering the extent to which the Offeror demonstrates a clear understanding of the architectural and engineering requirements of the project. The Government will evaluate the Offeror’s technical solution to determine adherence to the technical requirements of the solicitation.

4: PROPOSAL REQUIREMENTS

4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT

Site Visit Information: Site visit will be held Wednesday, 26 February 2020 at 10:30 AM.

This will be the ONLY Government scheduled site visit.

Requirements and deadlines below will be strictly enforced. Late requests will not be processed in time for the site visit.

Requirements:

1. Contractors shall provide the names (first and last names) and the name of the company they represent to Tom Burgeson at thomas.burgeson@navy.mil (copy Kalyani Baxi at kalyani.baxi@navy.mil) no later than Monday, 24 February 2020.

2. Contractors must be U.S. citizens.

3. Contractors must present a verified driver’s license. If contractors do not have a verified driver’s license, then they will need to provide two forms of photo ID (driver’s license and U.S. Passport or birth certificate and social security card) at the Pass and ID Office located next to the main gate – New London Submarine Base, Groton, CT. B135 is the first two-story brick building on the left when you enter the base from the main gate #1. Cars can be parked at the building or across the road.

4. It takes approximately 20 minutes for the Security to do a background check. Please note that only one or two security officers complete the background checks. Contractors shall allow themselves enough time to have their background check completed before 10:15 AM.

5. Contractors shall gather at B135 – PWD Building no later than 10:15 AM.

6. For long term access, the following link provides required guidance:

https://www.cnic.navy.mil/om/dbids.html

If contractors need any assistance, please call Tom Burgeson at (860) 694-3226 or Kalyani Baxi at (860) 694-4997.

4.2 PROPOSAL SUBMISSION INSTRUCTIONS: In response to this Request for Proposal, the complete proposal shall include the Price Proposal and the Non-Cost/Price Factors Proposal, submitted in accordance with the above Basis of Evaluation and Submittal Requirements for each Factor and as follows:

4.2.1 The Price Proposal and the Non-Cost/Price Proposal shall be submitted electronically to rachel.honecker@navy.mil by the designated due date and time. The Price and Non-Cost/Price binders will be requested at a later date and shall be submitted in separate 3-ring binders. All pages shall be numbered and binders shall be appropriately tabbed, conforming to the proposal submittal requirements’ structure for each evaluation factor. Price and Non-Cost/Price Proposals must be submitted in sealed envelopes/boxes. Any pricing information included in the Non-Cost/Price Proposal will not be considered. Similarly, any Non-Cost/Price information included in the Price Proposal will not be considered. Proposals shall be labeled “PRICE PROPOSAL OR NON- COST/PRICE PROPOSAL FOR RFP N40085-20-R-0034, ATTN: RACHEL HONECKER; DO NOT OPEN IN

MAIL ROOM”.

4.2.2 All proposals shall be submitted electronically to rachel.honecker@navy.mil by the designated due date and time. Once hard copy proposals are requested, all proposals shall be mailed or hand carried to the following address:

Naval Facilities Engineering Command, Mid-Atlantic, ACQ22 Attn: Rachel Honecker, Contract Specialist 9324 Virginia Avenue Building Z-140, Room 225 Norfolk, VA 23511-3624

4.2.3 Hand Carried Proposals: Offerors who would like to hand deliver their proposal and who do not currently have a valid badge issued by the Department of Defense (DoD) to enter Naval Station Norfolk must do the following:

- Submit the completed one day pass request PDF document (form SEC-NAV_5512_1_11787 (Attachment B) NO LESS THAN 10 BUSINESS DAYS prior to the proposal due date. The pass request is uploaded in beta.SAM.gov. The request form shall be completed in its entirety and sent to Rachel Honecker at rachel.honecker@navy.mil. Note that Item 25, BASE SPONSER’S NAME should include the following name and telephone number: Rachel Honecker (757-341-1652). This request is separate from the site visit request. The PDF document is uploaded with this solicitation under Additional Documents.

- Present the following information at the pass office: Two forms of ID (i.e. Valid Driver’s License and (one of the following) US Social Security Card or Birth Certificate), Current Vehicle Registration and/or Rental Car Contract, Current State Safety Inspection, Current Proof of Insurance.

Naval Station Norfolk Pass & ID Office is located in Bldg. CD9 at 9040 Hampton Boulevard across from Gate 5.

All potential offerors must adhere to this notice in order to avoid delay in submitting your proposal. The level of security at the Naval Station Norfolk may change at any time. As the level of security heightens, the amount of time required to gain access to the Naval Station also increases. Early arrival is advised. To verify identity, visitors MUST present a second form of identification at the pass office from the list of A or B Documents found at http:www.uscis.gov/i-9-central/acceptable-documents.

Submission of a pass request form is no guarantee you will be able to get on the base. If for any reason you get to the gate and are not allowed onto the base (even if you have submitted a request form), you will need to find another way to get your proposal delivered. Government personnel may not be able to sponsor you on base to deliver your proposal. Ultimately, it is the contractor's responsibility to ensure timely proposal submission to the specified location. Due to heightened security, it is recommended that you allow sufficient time to get into the building and turn in your proposal. The submitted pass request only allows access on the proposal due date. If the proposal due date is extended, the Government will revise the date on the pass request. Submission of a new pass request form is not necessary. If any other information listed on a submitted pass request form changes, a new pass request form with the updated information must be submitted.

4.2.4 PROPOSALS SUBMITTED IN RESPONSE TO THIS REQUEST FOR PROPOSAL MUST BE RECEIVED NO LATER THAN THE DATE AND TIME SPECIFIED IN BLOCK 13A OF THE SF1442. Proposals not received by the time and date specified shall be treated in accordance with FAR 52.215-1 “Instructions to Offerors-- Competitive Acquisition” and may be rejected.

4.3 PRE-PROPOSAL INQUIRIES (PPIs): All inquiries must be submitted in writing and received by the Contract Specialist fourteen (14) calendar days prior to the solicitation closing date in order to permit adequate time to reply to the inquiry. There is no guarantee that PPI’s submitted after the cut-off date will be answered before the solicitation closes. Submit all questions to rachel.honecker@navy.mil. Use of the PPI Log template is required.

The PPI Log Template (Attachment A) can be found on the beta.SAM.gov website.

5: ATTACHMENTS

Attachment A – Pre-Proposal Inquiry Form Attachment B – SECNAV_5512_1_11787-One Day Pass Request Attachment C – Construction Experience Project Data Sheet

Attachment D – Past Performance Questionnaire Attachment E – Small Business Subcontracting Plan Attachment F – Price Proposal Form

(End of Summary of Changes)